830 W MARCO PL 90291
Certificate Information: 830 W MARCO PL 90291
- Application / Permit
- 19014-30000-02421
- Plan Check / Job No.
- B19WL02552
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1ST, 2ND, AND 3RD FLOOR ADDITION TO EXISTING 1-STORY TYPE VB SINGLE FAMILY DWELLING, EQUIPPED THROUGHOUT WITH NFPA 13D FIRE SPRINKLERS.
- Permit Issued
- Issued on 1/17/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/8/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/13/2019 | SERGIO SILVA |
| Corrections Issued | 6/20/2019 | SERGIO SILVA |
| Green Plans Picked Up | 6/20/2019 | APPLICANT |
| Quality Review Completed | 6/25/2019 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 7/3/2019 | APPLICANT |
| Applicant returned to address corrections | 8/15/2019 | SERGIO SILVA |
| Plan Check Approved | 9/25/2019 | SERGIO SILVA |
| Issued | 1/17/2020 | LADBS |
| CofO in Progress | 11/1/2022 | DAVID FEILER |
| Permit Finaled | 11/3/2022 | DANIEL ORRANTE |
| CofO Issued | 11/3/2022 | DANIEL ORRANTE |
| Permit Finaled | 11/3/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 7/12/2019 | JEREMY CARTER |
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2019 | NIKTA MOUSAVI |
| Permit | Cleared | 7/19/2019 | NIKTA MOUSAVI |
| Sewer availability | Cleared | 7/19/2019 | NIKTA MOUSAVI |
| ZI | Cleared | 8/20/2019 | LAMBERT GIESSINGER |
| Low Impact Development | Cleared | 9/13/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 9/13/2019 | ERIK BEASLEY |
| Coastal Zone | Cleared | 9/19/2019 | SARAH GOLDMAN |
| Green Code | Cleared | 9/19/2019 | DONALD CRICHLOW |
| Specific Plan | Cleared | 9/19/2019 | SARAH GOLDMAN |
| ZA Case | Cleared | 9/19/2019 | SARAH GOLDMAN |
| ZA Case | Cleared | 9/19/2019 | SARAH GOLDMAN |
| ZA Case | Cleared | 9/19/2019 | SARAH GOLDMAN |
| ZA Case | Cleared | 9/19/2019 | SARAH GOLDMAN |
Contact Information
| Architect | Rechtszajd,, Daniela; Lic. No.: C31333 | 5410 VILLAGE GREEN LOS ANGELES, CA 90016 |
| Contractor | Celtic Design And Construction; Lic. No.: 778960-B | 2633 LINCOLN BLVD #304 SANTA MONICA, CA 90405 |
| Engineer | Barajas,, Jorge Luis; Lic. No.: L8399 | 3635 SHADOW GROVE RD PASADENA, CA 91107 |
| Engineer | Chen,, Peter Su-Chien; Lic. No.: M29734 | 1 TIERRA PLANO RANCHO SANTA MARGARITA, CA 92688 |
| Engineer | Phillips,, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/13/2020 | Partial Approval | DAVID HEINE |
| Footing/Foundation/Slab | 4/13/2020 | Partial Approval | DAVID HEINE |
| Excavation/Setback/Form/Re-Bar | 5/8/2020 | Partial Approval | DAVID HEINE |
| Footing/Foundation/Slab | 5/8/2020 | Partial Approval | DAVID HEINE |
| Wood Frame | 5/18/2020 | Partial Approval | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2020 | Partial Approval | DAVID HEINE |
| Footing/Foundation/Slab | 9/30/2020 | Not Ready for Inspection | DAVID HEINE |
| Sewer | 9/30/2020 | Approved | DAVID HEINE |
| ELECTRICAL-Rough | 11/10/2020 | Approved | DAVID HEINE |
| HVAC-Rough | 11/10/2020 | Not Ready for Inspection | DAVID HEINE |
| Special/Order Compliance | 11/10/2020 | Partial Inspection | PIERRE VEGA |
| Shower Pan | 11/16/2020 | No Access for Inspection | DAVID HEINE |
| HVAC-Rough | 11/18/2020 | Corrections Issued | JUAN VALENZUELA |
| HVAC-Rough | 11/24/2020 | Corrections Issued | DAVID HEINE |
| Shower Pan | 11/24/2020 | Corrections Issued | DAVID HEINE |
| PLUMBING-Rough | 12/3/2020 | Approved | DAVID HEINE |
| BUILDING-Rough-Frame | 12/10/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| Green Building Rough | 12/10/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| HVAC-Rough | 12/10/2020 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 1/7/2021 | Partial Approval | DAVID HEINE |
| Shower Pan | 1/7/2021 | Approved | DAVID HEINE |
| Interior/Exterior Lathing | 1/12/2021 | Partial Approval | DAVID HEINE |
| Deck | 1/29/2021 | Not Ready for Inspection | DAVID HEINE |
| Insulation | 1/29/2021 | Not Ready for Inspection | DAVID HEINE |
| Deck | 2/9/2021 | Partial Approval | JOHNNY MIRANDA |
| Insulation | 2/9/2021 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 3/31/2021 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 3/31/2021 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 8/19/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Final | 8/19/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Service/Power Release | 8/19/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| ELECTRICAL-Final | 9/2/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Green Building Final | 9/2/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| HVAC-Final | 9/2/2021 | Conditional Approval | BRENDAN LOONEY |
| PLUMBING-Final | 9/2/2021 | Conditional Approval | BRENDAN LOONEY |
| ELECTRICAL-Final | 9/8/2021 | Corrections Issued | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 9/8/2021 | Approved | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 9/8/2021 | Approved | JOHNNY MIRANDA |
| Gas Test | 9/8/2021 | Approved | JOHNNY MIRANDA |
| Green Building Final | 9/8/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| HVAC-Final | 9/8/2021 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Final | 9/8/2021 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 9/10/2021 | Approved | JOHNNY MIRANDA |
| Green Building Final | 9/10/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| HVAC-Final | 9/10/2021 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 10/12/2021 | Approved | JOHNNY MIRANDA |
| Final | 10/12/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Green Building Final | 10/12/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 10/12/2021 | SGSOV Not Ready | JOHNNY MIRANDA |
| Smoke Detectors | 10/12/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Structural Steel Frame | 10/12/2021 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 10/21/2021 | SGSOV Approved | DAVID FEILER |
| Green Building Final | 11/2/2021 | Approved | DAVID FEILER |
| Service/Power Release | 11/2/2021 | Approved | DAVID FEILER |
| Smoke Detectors | 11/2/2021 | Approved | DAVID FEILER |
| Final | 9/20/2022 | Corrections Issued | DAVID FEILER |
| Final | 10/20/2022 | Partial Approval | DAVID FEILER |
| Final | 11/1/2022 | OK to Issue CofO | DAVID FEILER |