12531 W PRESTON WAY 90066
Certificate Information: 12531 W PRESTON WAY 90066
- Application / Permit
- 19014-30000-02209
- Plan Check / Job No.
- B19WL02354
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1ST & 2ND STORY ADDITION TO (E) 1-STORY S.F.D
- Permit Issued
- Issued on 6/24/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 7/7/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/29/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/9/2019 | VLADIMIR ARUTYUNYAN |
| Green Plans Picked Up | 5/14/2019 | APPLICANT |
| Corrections Issued | 5/15/2019 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 5/24/2019 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 6/3/2019 | APPLICANT |
| Plan Check Approved | 6/21/2019 | VLADIMIR ARUTYUNYAN |
| Issued | 6/24/2019 | LADBS |
| CofO in Progress | 6/23/2021 | ENRIQUE MIRELES |
| CofO in Progress | 6/23/2021 | ENRIQUE MIRELES |
| CofO Issued | 7/7/2021 | VINCENT COTTON |
| Permit Finaled | 7/7/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Low Impact Development | Cleared | 6/19/2019 | ANDRES COVARRUBIAS |
| Eng Process Fee Ord 176,300 | Cleared | 6/20/2019 | HISASHI KOBAYAKAWA |
| Green Code | Cleared | 6/20/2019 | RICHARD GARCIA |
| Roof/Waste drainage to street | Cleared | 6/20/2019 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 6/20/2019 | HISASHI KOBAYAKAWA |
| Grading Pre-Inspection | Cleared | 6/21/2019 | BARTON HOLMES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 5525 CANOGA AVE APT 208 WOODLAND HILLS, CA 91367 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/22/2019 | Not Ready for Inspection | JUAN VALENZUELA |
| Footing/Foundation/Slab | 8/22/2019 | No Access for Inspection | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 8/27/2019 | Corrections Issued | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 9/4/2019 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 9/4/2019 | Not Ready for Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 9/12/2019 | Corrections Issued | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 9/23/2019 | Corrections Issued | RONALD WEBER |
| Footing/Foundation/Slab | 9/23/2019 | Partial Approval | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 10/1/2019 | Partial Inspection | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 10/1/2019 | Partial Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 10/8/2019 | Approved | CRAIG DAVIS |
| Deputy Drilled-In Anchors | 12/18/2019 | No Access for Inspection | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 1/31/2020 | Partial Approval | JOHNNY MIRANDA |
| Deputy Drilled-In Anchors | 2/20/2020 | Conditional Approval | JOHNNY MIRANDA |
| Underground Mechanical | 2/24/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 4/30/2020 | Partial Approval | DAVID HEINE |
| Footing/Foundation/Slab | 5/4/2020 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 6/16/2020 | Partial Approval | JOHN KIDWELL |
| Pre-Inspection | 7/20/2020 | Partial Inspection | JUAN VALENZUELA |
| Footing/Foundation/Slab | 8/3/2020 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2020 | Corrections Issued | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2020 | Corrections Issued | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2020 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 11/16/2020 | Partial Approval | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 11/16/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Rough | 11/16/2020 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 11/16/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Underground Mechanical | 11/16/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 12/7/2020 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 12/7/2020 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 12/7/2020 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 12/7/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 12/7/2020 | Approved | ENRIQUE MIRELES |
| Shower Pan | 12/14/2020 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 12/16/2020 | Approved | ENRIQUE MIRELES |
| Insulation | 12/16/2020 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 12/28/2020 | Approved | ENRIQUE MIRELES |
| Final | 4/16/2021 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 4/16/2021 | Approved | ENRIQUE MIRELES |
| Green Building Final | 4/16/2021 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 4/16/2021 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 4/16/2021 | Approved | ENRIQUE MIRELES |
| Final | 6/3/2021 | Corrections Issued | ENRIQUE MIRELES |
| Final | 6/23/2021 | OK to Issue CofO | ENRIQUE MIRELES |