942 E INDIANA AVE 90291
Certificate Information: 942 E INDIANA AVE 90291
- Application / Permit
- 19014-30000-02165
- Plan Check / Job No.
- B19WL02321
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-story addition and interior remodel to (e) SFD.
- Permit Issued
- Issued on 6/10/2021
- Issuing Office
- Current Status
- CofO Issued on 9/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/6/2019 | MANUEL GARCIA |
| Corrections Issued | 7/30/2019 | MANUEL GARCIA |
| Quality Review Completed | 8/6/2019 | FELIX FIGUEROA |
| Building Plans Picked Up | 8/7/2019 | APPLICANT |
| Green Plans Picked Up | 8/7/2019 | APPLICANT |
| Applicant returned to address corrections | 11/14/2019 | MANUEL GARCIA |
| Plan Check Approved | 12/17/2019 | MANUEL GARCIA |
| Issued | 6/10/2021 | APPLICANT |
| CofO in Progress | 9/16/2022 | DAVID FEILER |
| Permit Finaled | 9/22/2022 | DANIEL ORRANTE |
| CofO Issued | 9/22/2022 | DANIEL ORRANTE |
| Permit Finaled | 9/22/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/29/2019 | ERIK BEASLEY |
| Low Impact Development | Cleared | 9/23/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 9/23/2019 | JEANIE LAM |
| Sewer availability | Cleared | 9/23/2019 | JEANIE LAM |
| Green Code | Cleared | 10/10/2019 | RICHARD GARCIA |
Contact Information
| Contractor | Alisal Builders Corp; Lic. No.: 732777-B | P O BOX 6038 SAN PEDRO, CA 90734 |
| Engineer | Herrera,, Edgar E; Lic. No.: C67603 | 1971 S SUNRISE DRIVE MONTEREY PARK, CA 91754 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/9/2021 | Corrections Issued | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 9/14/2021 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 10/4/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2021 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 10/4/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2021 | Partial Approval | RICHARD STEINBACH |
| Wood Frame | 11/5/2021 | Partial Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 1/5/2022 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 1/11/2022 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Rough | 1/11/2022 | Not Ready for Inspection | DAVID FEILER |
| Green Building Rough | 1/11/2022 | Not Ready for Inspection | DAVID FEILER |
| Wood Frame | 1/11/2022 | Not Ready for Inspection | DAVID FEILER |
| ELECTRICAL-Rough | 1/12/2022 | Corrections Issued | DAVID FEILER |
| HVAC-Rough | 1/12/2022 | Not Ready for Inspection | DAVID FEILER |
| ELECTRICAL-Rough | 2/7/2022 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 2/7/2022 | Approved | RYAN SALAZAR |
| Deputy Drilled-In Anchors | 2/8/2022 | Conditional Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 2/10/2022 | Partial Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2022 | Approved | DAVID FEILER |
| HVAC-Rough | 2/10/2022 | No Access for Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 2/24/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Green Building Rough | 2/24/2022 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Rough | 2/24/2022 | Corrections Issued | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 3/2/2022 | Approved | DAVID FEILER |
| Green Building Rough | 3/2/2022 | Partial Approval | DAVID FEILER |
| HVAC-Rough | 3/2/2022 | Partial Approval | DAVID FEILER |
| Interior/Exterior Lathing | 3/2/2022 | Not Ready for Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 3/9/2022 | Approved | DAVID FEILER |
| Green Building Rough | 3/9/2022 | Approved | DAVID FEILER |
| Insulation | 3/9/2022 | Approved | DAVID FEILER |
| Shower Pan | 3/9/2022 | Approved | DAVID FEILER |
| Drywall Nailing | 3/17/2022 | Approved | DAVID FEILER |
| Gas Test | 6/23/2022 | Not Ready for Inspection | DAVID FEILER |
| Service/Power Release | 7/5/2022 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Final | 7/11/2022 | Not Ready for Inspection | DAVID FEILER |
| Service/Power Release | 7/11/2022 | Not Ready for Inspection | DAVID FEILER |
| ELECTRICAL-Final | 7/13/2022 | Approved | DAVID FEILER |
| Service/Power Release | 7/13/2022 | Approved | DAVID FEILER |
| Special/Order Compliance | 7/13/2022 | Partial Inspection | RICHARD STEINBACH |
| HVAC-Final | 8/8/2022 | Corrections Issued | STEPHANIE SWANSON |
| Gas Test | 8/11/2022 | Approved | DAVID FEILER |
| PLUMBING-Final | 8/11/2022 | Corrections Issued | DAVID FEILER |
| Final | 8/17/2022 | Corrections Issued | DAVID FEILER |
| Green Building Final | 8/17/2022 | Corrections Issued | DAVID FEILER |
| HVAC-Final | 8/17/2022 | Partial Approval | DAVID FEILER |
| PLUMBING-Final | 8/17/2022 | Approved | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 8/17/2022 | SGSOV Approved | DAVID FEILER |
| Smoke Detectors | 8/17/2022 | Approved | DAVID FEILER |
| Final | 8/29/2022 | Partial Inspection | DAVID FEILER |
| Green Building Final | 8/29/2022 | Approved | DAVID FEILER |
| HVAC-Final | 8/29/2022 | Approved | DAVID FEILER |
| Final | 8/31/2022 | Partial Approval | DAVID FEILER |
| Final | 9/7/2022 | Not Ready for Inspection | DAVID FEILER |
| Final | 9/14/2022 | Not Ready for Inspection | DAVID FEILER |
| Final | 9/16/2022 | OK to Issue CofO | DAVID FEILER |