1515-1517 S DURANGO AVE 90035
Certificate Information: 1515-1517 S DURANGO AVE 90035
- Application / Permit
- 19014-30000-02019
- Plan Check / Job No.
- B19WL02166
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- (N) recreation room attached to (E) garage.
- Permit Issued
- Issued on 8/27/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/11/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/19/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/19/2019 | ALFREDO JARA |
| Corrections Issued | 4/19/2019 | ALFREDO JARA |
| Plan Check Approved | 8/15/2019 | ALFREDO JARA |
| Plan Check Approved | 8/15/2019 | HELEN NGUYEN |
| Issued | 8/27/2019 | LADBS |
| CofO in Progress | 5/19/2020 | KENNETH NAGLE |
| Permit Finaled | 6/11/2020 | VINCENT COTTON |
| CofO Issued | 6/11/2020 | VINCENT COTTON |
| Permit Finaled | 6/11/2020 | VINCENT COTTON |
Permit Application Clearance Information
| Construction near power lines | Cleared | 8/1/2019 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 8/14/2019 | CELINA MORENO |
| Grading Pre-Inspection | Cleared | 8/14/2019 | PATRICK MISCHLICH |
| Low Impact Development | Cleared | 8/14/2019 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 8/14/2019 | CELINA MORENO |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Braum Construction And Management; Lic. No.: 959860-B | 6551 VAN NUYS BLVD, MEZZ FLOOR VAN NUYS, CA 91401 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/3/2019 | Corrections Issued | EVAN COOPER |
| BUILDING-Rough-Frame | 10/4/2019 | Corrections Issued | EVAN COOPER |
| Green Building Rough | 10/4/2019 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Rough | 10/4/2019 | Not Ready for Inspection | EVAN COOPER |
| Deputy Drilled-In Anchors | 11/5/2019 | No Access for Inspection | ROBERT SHELLY |
| Excavation/Setback/Form/Re-Bar | 11/7/2019 | Not Ready for Inspection | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 11/14/2019 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 12/5/2019 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 1/31/2020 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 1/31/2020 | Not Ready for Inspection | EVAN COOPER |
| Green Building Rough | 1/31/2020 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 1/31/2020 | Corrections Issued | EVAN COOPER |
| METHANE-Rough | 1/31/2020 | Approved | EVAN COOPER |
| PLUMBING-Rough | 1/31/2020 | Not Ready for Inspection | EVAN COOPER |
| Service/Power Release | 3/19/2020 | Approved | KENNETH NAGLE |
| BUILDING-Rough-Frame | 4/13/2020 | Approved | EVAN COOPER |
| Final | 4/13/2020 | Not Ready for Inspection | EVAN COOPER |
| Footing/Foundation/Slab | 4/13/2020 | Approved | EVAN COOPER |
| Green Building Final | 4/13/2020 | Not Ready for Inspection | EVAN COOPER |
| Green Building Rough | 4/13/2020 | Approved | EVAN COOPER |
| METHANE-Barrier | 4/13/2020 | Approved | EVAN COOPER |
| METHANE-Subgrade | 4/13/2020 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 4/13/2020 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 4/13/2020 | Approved | EVAN COOPER |
| Service/Power Release | 4/14/2020 | Approved | EVAN COOPER |
| Final | 4/17/2020 | Corrections Issued | EVAN COOPER |
| Green Building Final | 4/17/2020 | Not Ready for Inspection | EVAN COOPER |
| Final | 4/28/2020 | Conditional Approval | EVAN COOPER |
| Green Building Final | 4/28/2020 | Approved | EVAN COOPER |