1515-1517 S DURANGO AVE 90035

Certificate Information: 1515-1517 S DURANGO AVE 90035

Application / Permit
19014-30000-02019
Plan Check / Job No.
B19WL02166
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
(N) recreation room attached to (E) garage.
Permit Issued
Issued on 8/27/2019
Issuing Office
Metro
Current Status
CofO Issued on 6/11/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/19/2019 APPLICANT
Assigned to Plan Check Engineer 4/19/2019 ALFREDO JARA
Corrections Issued 4/19/2019 ALFREDO JARA
Plan Check Approved 8/15/2019 ALFREDO JARA
Plan Check Approved 8/15/2019 HELEN NGUYEN
Issued 8/27/2019 LADBS
CofO in Progress 5/19/2020 KENNETH NAGLE
Permit Finaled 6/11/2020 VINCENT COTTON
CofO Issued 6/11/2020 VINCENT COTTON
Permit Finaled 6/11/2020 VINCENT COTTON

Permit Application Clearance Information

Construction near power lines Cleared 8/1/2019 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 8/14/2019 CELINA MORENO
Grading Pre-Inspection Cleared 8/14/2019 PATRICK MISCHLICH
Low Impact Development Cleared 8/14/2019 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 8/14/2019 CELINA MORENO

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Braum Construction And Management; Lic. No.: 959860-B 6551 VAN NUYS BLVD, MEZZ FLOOR      VAN NUYS, CA 91401

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/3/2019 Corrections Issued EVAN COOPER
BUILDING-Rough-Frame 10/4/2019 Corrections Issued EVAN COOPER
Green Building Rough 10/4/2019 Not Ready for Inspection EVAN COOPER
METHANE-Rough 10/4/2019 Not Ready for Inspection EVAN COOPER
Deputy Drilled-In Anchors 11/5/2019 No Access for Inspection ROBERT SHELLY
Excavation/Setback/Form/Re-Bar 11/7/2019 Not Ready for Inspection EVAN COOPER
Excavation/Setback/Form/Re-Bar 11/14/2019 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 12/5/2019 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 1/31/2020 Partial Approval EVAN COOPER
ELECTRICAL-Rough 1/31/2020 Not Ready for Inspection EVAN COOPER
Green Building Rough 1/31/2020 Not Ready for Inspection EVAN COOPER
HVAC-Rough 1/31/2020 Corrections Issued EVAN COOPER
METHANE-Rough 1/31/2020 Approved EVAN COOPER
PLUMBING-Rough 1/31/2020 Not Ready for Inspection EVAN COOPER
Service/Power Release 3/19/2020 Approved KENNETH NAGLE
BUILDING-Rough-Frame 4/13/2020 Approved EVAN COOPER
Final 4/13/2020 Not Ready for Inspection EVAN COOPER
Footing/Foundation/Slab 4/13/2020 Approved EVAN COOPER
Green Building Final 4/13/2020 Not Ready for Inspection EVAN COOPER
Green Building Rough 4/13/2020 Approved EVAN COOPER
METHANE-Barrier 4/13/2020 Approved EVAN COOPER
METHANE-Subgrade 4/13/2020 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 4/13/2020 SGSOV Approved EVAN COOPER
Smoke Detectors 4/13/2020 Approved EVAN COOPER
Service/Power Release 4/14/2020 Approved EVAN COOPER
Final 4/17/2020 Corrections Issued EVAN COOPER
Green Building Final 4/17/2020 Not Ready for Inspection EVAN COOPER
Final 4/28/2020 Conditional Approval EVAN COOPER
Green Building Final 4/28/2020 Approved EVAN COOPER