325 N BEL-AIR ROAD 90077
Certificate Information: 325 N BEL-AIR ROAD 90077
- Application / Permit
- 19014-30000-01972
- Plan Check / Job No.
- B19WL02120
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION/ REMODEL TO SFD WITH ATTACHED GARAGE****
- Permit Issued
- Issued on 9/19/2019
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 9/19/2019
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/29/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/9/2019 | TARIK SAOUD |
| Corrections Issued | 5/13/2019 | TARIK SAOUD |
| Quality Review Completed | 5/23/2019 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 5/23/2019 | APPLICANT |
| Green Plans Picked Up | 6/4/2019 | APPLICANT |
| Plan Check Approved | 9/12/2019 | TARIK SAOUD |
| Issued | 9/19/2019 | LADBS |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 5/29/2019 | ZIXUAN CHEN |
| BHO/Hillside ordinance | Cleared | 5/29/2019 | ZIXUAN CHEN |
| BHO/Hillside ordinance | Cleared | 5/29/2019 | ZIXUAN CHEN |
| Eng Process Fee Ord 176,300 | Cleared | 5/29/2019 | ZIXUAN CHEN |
| Permit | Cleared | 5/29/2019 | ZIXUAN CHEN |
| Sewer availability | Cleared | 5/29/2019 | ZIXUAN CHEN |
| Low Impact Development | Cleared | 8/14/2019 | ANDRES COVARRUBIAS |
| CPC | Cleared | 8/20/2019 | SARAH GOLDMAN |
| Excavation more than 5-ft deep | Cleared | 8/20/2019 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 8/20/2019 | TARIK SAOUD |
| Green Code | Cleared | 8/20/2019 | RICHARD GARCIA |
| Roof/Waste drainage to street | Cleared | 8/20/2019 | CHRISTOPHER LAW |
Contact Information
| Architect | Wyatt,, Graham S; Lic. No.: C28040 | 1 PARK AVENUE 16TH FLOOR NEW YORK, NY 10016 |
| Contractor | Drake Construction & Development Inc; Lic. No.: 789617-B | 13949 VENTURA BLVD #312 SHERMAN OAKS, CA 91423 |
| Engineer | Logan,, Gene Thomas; Lic. No.: C56724 | PO BOX 19075 NEWBURY PARK, CA 91320 |
| Engineer | Mahn,, Jonathan Edward; Lic. No.: C60293 | 12848 FOOTHILL BLVD SYLMAR, CA 91381 |
| Engineer | Resnick,, Bruce Daniel; Lic. No.: S3293 | 1927 PONTIUS AVE LOS ANGELES, CA 90025 |
| Geologist | Triebold,, Mark John; Lic. No.: EG1796 | 6906 QUITO COURT CAMARILLO, CA 93012 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/6/2020 | Corrections Issued | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 8/10/2020 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 8/27/2020 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 9/29/2020 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 10/13/2020 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 11/24/2020 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 12/21/2020 | Partial Approval | MATT KELLERMAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2021 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 2/18/2021 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 3/25/2021 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 4/7/2021 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 5/12/2021 | Partial Approval | CHRISTOPHER WILSON |
| PLUMBING-Rough | 5/27/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2021 | Partial Approval | MATT KELLERMAN |
| Footing/Foundation/Slab | 6/25/2021 | Partial Approval | MATT KELLERMAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2021 | Partial Approval | CHRISTOPHER WILSON |
| PLUMBING-Rough | 10/15/2021 | Corrections Issued | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 11/18/2021 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Rough | 12/6/2021 | Partial Approval | CHRISTOPHER WILSON |
| Gas Test | 1/6/2022 | Partial Approval | CHRISTOPHER WILSON |
| PLUMBING-Rough | 1/6/2022 | Approved | CHRISTOPHER WILSON |
| Shower Pan | 1/6/2022 | Partial Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 1/20/2022 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 1/26/2022 | Approved | CHRISTOPHER WILSON |
| Underground Mechanical | 1/31/2022 | Partial Approval | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 2/15/2022 | Partial Approval | CHRISTOPHER WILSON |
| Underground Mechanical | 2/23/2022 | Partial Approval | CHRISTOPHER WILSON |
| HVAC-Rough | 2/28/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Final | 3/25/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| HVAC-Rough | 3/25/2022 | Corrections Issued | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 3/29/2022 | Approved | CHRISTOPHER WILSON |
| Green Building Rough | 3/29/2022 | Approved | CHRISTOPHER WILSON |
| Insulation | 4/12/2022 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 4/14/2022 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 4/27/2022 | Partial Approval | CHRISTOPHER WILSON |
| Drywall Nailing | 4/28/2022 | Approved | CLAYTON GRAHAM |
| Drywall Nailing | 5/16/2022 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 5/17/2022 | Partial Approval | CHRISTOPHER WILSON |
| Drywall Nailing | 7/28/2022 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 7/28/2022 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 8/24/2022 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 10/17/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Underground Mechanical | 10/17/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 10/28/2022 | Approved | CHRISTOPHER WILSON |
| Gas Test | 11/7/2022 | Approved | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 11/29/2022 | SGSOV Approved | CARLOS MATAMOROS |
| Pre-Inspection | 2/1/2023 | Partial Inspection | STEPHANIE SWANSON |
| Pre-Inspection | 2/8/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Final | 5/2/2023 | Corrections Issued | CHRISTOPHER WILSON |
| PLUMBING-Final | 5/3/2023 | Corrections Issued | CHRISTOPHER WILSON |
| HVAC-Final | 5/11/2023 | Approved | BRENDAN LOONEY |
| PLUMBING-Final | 5/11/2023 | Partial Approval | BRENDAN LOONEY |
| ELECTRICAL-Final | 5/24/2023 | Corrections Issued | CHRISTOPHER WILSON |
| PLUMBING-Final | 5/24/2023 | Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 6/13/2023 | Approved | CHRISTOPHER WILSON |
| Final | 9/1/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Green Building Final | 9/1/2023 | Approved | CHRISTOPHER WILSON |
| Smoke Detectors | 9/1/2023 | Approved | CHRISTOPHER WILSON |
| Structural Steel Frame | 9/1/2023 | Approved | CHRISTOPHER WILSON |