631 N EDINBURGH AVE 90048
Certificate Information: 631 N EDINBURGH AVE 90048
- Application / Permit
- 19014-30000-01882
- Plan Check / Job No.
- B19WL02024
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ADU WITH ADDITION PER AB 494 AND SB 229. PER ENGINEERED DESIGN.
- Permit Issued
- Issued on 6/21/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2019 | ALFREDO JARA |
| Corrections Issued | 4/22/2019 | ALFREDO JARA |
| Building Plans Picked Up | 4/24/2019 | APPLICANT |
| Plan Check Approved | 6/14/2019 | ALFREDO JARA |
| Issued | 6/21/2019 | LADBS |
| CofO in Progress | 1/17/2024 | LILIANA PORTILLO |
| No Progress | 1/26/2024 | DEROLD HAUFF |
| Permit Finaled | 2/28/2024 | DEROLD HAUFF |
| CofO Issued | 2/28/2024 | DEROLD HAUFF |
| Permit Finaled | 2/28/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/24/2019 | JOSE CRUZ RODRIGUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/24/2019 | JOSE CRUZ RODRIGUEZ |
| Construction near power lines | Cleared | 5/18/2019 | RIDWAN HARDY |
| Low Impact Development | Cleared | 6/10/2019 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 6/10/2019 | ELENA LOPEZ |
| Sewer availability | Cleared | 6/10/2019 | ELENA LOPEZ |
Contact Information
| Architect | Bambrough,, Patrick; Lic. No.: C34299 | 4132 ALLA ROAD LOS ANGELES, CA 90066 |
| Contractor | Owner-Builder | , |
| Engineer | Garestani,, Siamak; Lic. No.: M26426 | 6345 BALBOA BLVD #288 ENCINO, CA 91316 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Barrier | 7/5/2019 | Approved | JOSEPH MCGARRY |
| METHANE-Subgrade | 7/5/2019 | Approved | JOSEPH MCGARRY |
| Pre-Inspection | 7/5/2019 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 7/29/2019 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 8/13/2019 | Corrections Issued | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 8/19/2019 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Deputy Wood Construction | 12/24/2020 | No Access for Inspection | ELMER BLAND |
| Wood Frame | 12/29/2020 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 1/5/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 1/5/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 1/5/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| HVAC-Rough | 1/5/2021 | Approved | CHRIS CHRISTENSEN |
| METHANE-Rough | 1/5/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 1/5/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 1/22/2021 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 3/3/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 3/3/2021 | Approved | CHRIS CHRISTENSEN |
| Insulation | 3/3/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 3/3/2021 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 5/14/2021 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 9/16/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Special/Order Compliance | 4/4/2022 | Corrections Issued | JOSEPH MCGARRY |
| Underground Mechanical | 4/4/2022 | Partial Approval | JOSEPH MCGARRY |
| Gas Test | 4/21/2022 | Approved | ADAM ESCOTO |
| Underground Mechanical | 4/21/2022 | Approved | ADAM ESCOTO |
| Special/Order Compliance | 6/23/2023 | Corrections Issued | LILIANA PORTILLO |
| Final | 8/29/2023 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 8/29/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 8/29/2023 | Conditional Approval | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 8/29/2023 | SGSOV Approved | LILIANA PORTILLO |
| Smoke Detectors | 8/29/2023 | Approved | LILIANA PORTILLO |
| Final | 9/28/2023 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 9/28/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Final | 12/22/2023 | Approved | LILIANA PORTILLO |
| Final | 12/22/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Final | 12/22/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 12/22/2023 | Approved | LILIANA PORTILLO |
| Final | 1/16/2024 | OK to Issue CofO | LILIANA PORTILLO |
| Green Building Final | 1/16/2024 | Approved | LILIANA PORTILLO |