4066 S ALLA ROAD 90066
Certificate Information: 4066 S ALLA ROAD 90066
- Application / Permit
- 19014-30000-01723
- Plan Check / Job No.
- B19WL01852
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and remodel to (e) SFD w/ new attached 1-car garage.
- Permit Issued
- Issued on 3/6/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 9/7/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/4/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2019 | REZA HAGHIGHAT |
| Corrections Issued | 4/22/2019 | REZA HAGHIGHAT |
| Quality Review Completed | 5/3/2019 | KAMRAN GHOTBI RAVANDI |
| Green Plans Picked Up | 5/7/2019 | APPLICANT |
| Applicant returned to address corrections | 8/20/2019 | REZA HAGHIGHAT |
| Plan Check Approved | 9/24/2019 | REZA HAGHIGHAT |
| Issued | 3/6/2020 | LADBS |
| CofO in Progress | 7/27/2021 | BRENDAN LOONEY |
| Permit Finaled | 9/7/2021 | RONALD MYRICK |
| CofO Issued | 9/7/2021 | RONALD MYRICK |
| Permit Finaled | 9/7/2021 | RONALD MYRICK |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/20/2019 | OSCAR GUTIERREZ |
| Sewer availability | Cleared | 8/20/2019 | OSCAR GUTIERREZ |
| Low Impact Development | Cleared | 9/16/2019 | RYAN HUDSON |
| Green Code | Cleared | 9/18/2019 | RICHARD GARCIA |
| Roof/Waste drainage to street | Cleared | 9/24/2019 | DINAH GARIN |
Contact Information
| Engineer | Trevellin,, Maurizio; Lic. No.: C71368 | 707 ASHLAND AVE 2 SANTA MONICA, CA 90405 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/16/2020 | Conditional Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 6/23/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Reinf. Concrete | 6/24/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 7/1/2020 | Partial Approval | ANTHONY MCDOWALL |
| BUILDING-Rough-Frame | 7/15/2020 | Partial Approval | DAVID HEINE |
| Green Building Rough | 7/15/2020 | Not Ready for Inspection | DAVID HEINE |
| Wood Frame | 7/17/2020 | Approved | DAVID HEINE |
| BUILDING-Rough-Frame | 8/20/2020 | Partial Approval | KENNETH NAGLE |
| PLUMBING-Rough | 8/20/2020 | Partial Approval | KENNETH NAGLE |
| BUILDING-Rough-Frame | 9/17/2020 | Not Ready for Inspection | CRAIG DAVIS |
| ELECTRICAL-Rough | 9/17/2020 | Corrections Issued | CRAIG DAVIS |
| Green Building Rough | 9/17/2020 | Not Ready for Inspection | CRAIG DAVIS |
| HVAC-Rough | 9/17/2020 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Rough | 9/17/2020 | Partial Approval | CRAIG DAVIS |
| ELECTRICAL-Rough | 9/21/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 9/22/2020 | Not Ready for Inspection | PIERRE VEGA |
| ELECTRICAL-Rough | 9/22/2020 | Not Ready for Inspection | PIERRE VEGA |
| Green Building Rough | 9/22/2020 | Not Ready for Inspection | PIERRE VEGA |
| PLUMBING-Rough | 9/22/2020 | Approved | PIERRE VEGA |
| Shower Pan | 9/22/2020 | Approved | PIERRE VEGA |
| BUILDING-Rough-Frame | 9/29/2020 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 9/29/2020 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 9/29/2020 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 9/29/2020 | Approved | ENRIQUE MIRELES |
| Insulation | 10/6/2020 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 10/15/2020 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 10/16/2020 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 1/5/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| HVAC-Final | 1/5/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Final | 1/5/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| ELECTRICAL-Final | 1/15/2021 | Corrections Issued | ENRIQUE MIRELES |
| HVAC-Final | 1/15/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 1/15/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Final | 1/19/2021 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 1/19/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 1/19/2021 | Approved | ENRIQUE MIRELES |
| Final | 1/22/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 1/22/2021 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 1/22/2021 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 1/22/2021 | Approved | ENRIQUE MIRELES |
| Final | 2/1/2021 | Corrections Issued | ENRIQUE MIRELES |
| Final | 7/26/2021 | OK to Issue CofO | BRENDAN LOONEY |
| Service/Power Release | 7/26/2021 | Approved | BRENDAN LOONEY |