247 S LARCHMONT BLVD 90004

Certificate Information: 247 S LARCHMONT BLVD 90004

Application / Permit
19014-30000-01707
Plan Check / Job No.
B19WL01825
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADU addition to (e) garage per AB494 & SB229.
Permit Issued
Issued on 1/29/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 12/27/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/4/2019 APPLICANT
Assigned to Plan Check Engineer 4/10/2019 RICARDO RAMIREZ
Corrections Issued 4/11/2019 RICARDO RAMIREZ
Building Plans Picked Up 4/16/2019 APPLICANT
Applicant returned to address corrections 11/7/2019 REZA HAGHIGHAT
Plan Check Approved 1/29/2020 ALFREDO JARA
Issued 1/29/2020 LADBS
CofO in Progress 2/16/2022 ARTHUR SARGSYAN
CofO in Progress 2/16/2022 ARTHUR SARGSYAN
Permit Finaled 12/27/2022 DEROLD HAUFF
CofO Issued 12/27/2022 DEROLD HAUFF
Permit Finaled 12/27/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/8/2019 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 5/8/2019 HISASHI KOBAYAKAWA
Miscellaneous Cleared 5/8/2019 TREVOR MARTIN
Miscellaneous Cleared 5/8/2019 TREVOR MARTIN
Sewer availability Cleared 5/8/2019 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 11/7/2019 ANTHONY MAINEZ
CPC Cleared 11/13/2019 MAX LODER
CPC Cleared 11/13/2019 MAX LODER
CPC Cleared 11/13/2019 MAX LODER
Construction near power lines Cleared 11/13/2019 OSCAR CASTRO
HPOZ Cleared 11/13/2019 MAX LODER
Hydrant and Access approval Cleared 11/13/2019 JEREMY CARTER
ZI Cleared 11/13/2019 MAX LODER

Contact Information

Contractor Markei Contractors; Lic. No.: 789090-B 4879 E LA PALMA AVE STE 206      ANAHEIM, CA 92807
Engineer Yaghi,, Shucri Ibrahim; Lic. No.: C43205 112 E CHAPMAN AVE STE D      ORANGE, CA 92866

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/22/2021 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 6/24/2021 Partial Approval JOSEPH MCGARRY
METHANE-Barrier 6/24/2021 Approved JOSEPH MCGARRY
METHANE-Subgrade 6/24/2021 Approved JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 8/3/2021 Partial Approval ARTHUR SARGSYAN
Green Building Rough 8/3/2021 Not Ready for Inspection ARTHUR SARGSYAN
METHANE-Rough 8/3/2021 Not Ready for Inspection ARTHUR SARGSYAN
Deputy Wood Construction 8/6/2021 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 8/30/2021 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 8/30/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 8/30/2021 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 8/30/2021 Approved CHRIS CHRISTENSEN
METHANE-Rough 8/30/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 8/30/2021 Approved CHRIS CHRISTENSEN
Wood Frame 8/30/2021 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 9/8/2021 Conditional Approval JOSEPH MCGARRY
Footing/Foundation/Slab 9/8/2021 Approved JOSEPH MCGARRY
Green Building Rough 9/8/2021 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 9/8/2021 Partial Approval JOSEPH MCGARRY
Insulation 9/15/2021 Approved ARTHUR SARGSYAN
Drywall Nailing 9/20/2021 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 10/19/2021 Approved ARTHUR SARGSYAN
Shower Pan 10/19/2021 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 1/24/2022 Approved CRAIG DAVIS
Final 1/24/2022 Corrections Issued CRAIG DAVIS
Green Building Final 1/24/2022 Corrections Issued CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 1/24/2022 SGSOV Not Ready CRAIG DAVIS
Smoke Detectors 1/24/2022 Approved CRAIG DAVIS
ELECTRICAL-Final 2/15/2022 Approved ARTHUR SARGSYAN
Final 2/15/2022 OK to Issue CofO ARTHUR SARGSYAN
Green Building Final 2/15/2022 Approved ARTHUR SARGSYAN
HVAC-Final 2/15/2022 Approved ARTHUR SARGSYAN
PLUMBING-Final 2/15/2022 Approved ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 2/15/2022 SGSOV Approved ARTHUR SARGSYAN