2826 S BARRINGTON AVE 90064

Certificate Information: 2826 S BARRINGTON AVE 90064

Application / Permit
19014-30000-01701
Plan Check / Job No.
B19WL01814
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Addition and conversion of existing detached garage into storage and accessory dwelling unit per AB 494 and SB 229
Permit Issued
Issued on 1/3/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 1/16/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/3/2019 APPLICANT
Assigned to Plan Check Engineer 5/2/2019 MARJAN SHENASI
Green Plans Picked Up 5/8/2019 APPLICANT
Corrections Issued 5/14/2019 MARJAN SHENASI
Quality Review Completed 5/24/2019 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 5/28/2019 APPLICANT
Applicant returned to address corrections 7/23/2019 MARJAN SHENASI
Applicant returned to address corrections 9/26/2019 MARJAN SHENASI
Applicant returned to address corrections 10/3/2019 MARJAN SHENASI
Plan Check Approved 10/25/2019 MARJAN SHENASI
Issued 1/3/2020 LADBS
CofO in Progress 1/16/2021 KENNETH NAGLE
Permit Finaled 1/16/2021 KENNETH NAGLE
CofO Issued 1/16/2021 KENNETH NAGLE
Permit Finaled 1/16/2021 KENNETH NAGLE

Permit Application Clearance Information

Address approval Cleared 7/5/2019 JOSE CRUZ RODRIGUEZ
Permit Cleared 7/5/2019 JOSE CRUZ RODRIGUEZ
Green Code Cleared 7/31/2019 DONALD CRICHLOW
Trees in Parkway Cleared 8/21/2019 ADRIAN SANCHEZ
Construction near power lines Cleared 9/11/2019 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 9/26/2019 DINAH GARIN
Low Impact Development Cleared 9/26/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 9/26/2019 DINAH GARIN
Sewer availability Cleared 10/3/2019 DINAH GARIN
Hydrant and Access approval Cleared 10/24/2019 GEORGE SUCHAND

Contact Information

Contractor Bayview Construction Inc; Lic. No.: 667400-B 2701 11TH STREET      SANTA MONICA, CA 90405
Engineer Zhang,, Jiefu; Lic. No.: S5270 1205 SOUTH 4TH ST      ALHAMBRA, CA 91801

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Test 1/31/2020 Approved OGANES TARAKHCHYAN
Sewer 1/31/2020 Approved OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 2/6/2020 Approved ANDREW NAVE
Footing/Foundation/Slab 2/6/2020 Approved ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 2/28/2020 Partial Approval KEVIN BEAULIEU
BUILDING-Rough-Frame 4/1/2020 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 4/1/2020 Partial Approval OGANES TARAKHCHYAN
Green Building Rough 4/1/2020 Approved OGANES TARAKHCHYAN
Rough-Elec/Plmb/HVAC 4/1/2020 Approved OGANES TARAKHCHYAN
Insulation 4/8/2020 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 4/8/2020 Approved CARLOS MATAMOROS
Shower Pan 4/8/2020 Approved CARLOS MATAMOROS
Drywall Nailing 4/15/2020 Approved EVAN COOPER
Interior/Exterior Lathing 4/15/2020 Approved EVAN COOPER
Service/Power Release 5/18/2020 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 7/28/2020 Approved EVAN COOPER
Final 7/28/2020 Corrections Issued EVAN COOPER
Green Building Final 7/28/2020 Approved EVAN COOPER
HVAC-Final 7/28/2020 Approved EVAN COOPER
PLUMBING-Final 7/28/2020 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 7/28/2020 SGSOV Approved EVAN COOPER
Smoke Detectors 7/28/2020 Conditional Approval EVAN COOPER
Final 8/17/2020 Partial Approval OGANES TARAKHCHYAN
Smoke Detectors 8/17/2020 Approved OGANES TARAKHCHYAN