720 W WOODLAWN AVE 90291
Certificate Information: 720 W WOODLAWN AVE 90291
- Application / Permit
- 19014-30000-01543
- Plan Check / Job No.
- B19WL01655
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition to SFD and new attached 1-car garage.
- Permit Issued
- Issued on 1/30/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 5/11/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/28/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/11/2019 | MANUEL GARCIA |
| Green Plans Picked Up | 4/12/2019 | APPLICANT |
| Corrections Issued | 4/16/2019 | MANUEL GARCIA |
| Quality Review Completed | 4/25/2019 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 4/26/2019 | APPLICANT |
| Applicant returned to address corrections | 7/18/2019 | MANUEL GARCIA |
| Plan Check Approved | 10/4/2019 | MANUEL GARCIA |
| Issued | 1/30/2020 | LADBS |
| CofO in Progress | 5/5/2021 | PIERRE VEGA |
| Permit Finaled | 5/11/2021 | VINCENT COTTON |
| CofO Issued | 5/11/2021 | VINCENT COTTON |
| Permit Finaled | 5/11/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Construction near power lines | Cleared | 5/2/2019 | OSCAR CASTRO |
| Green Code | Cleared | 7/11/2019 | DONALD CRICHLOW |
| Miscellaneous | Cleared | 8/27/2019 | JOE LUCKEY |
| Miscellaneous | Cleared | 8/27/2019 | JOE LUCKEY |
| Miscellaneous | Cleared | 8/27/2019 | JOE LUCKEY |
| Miscellaneous | Cleared | 8/27/2019 | JOE LUCKEY |
| Specific Plan | Cleared | 8/27/2019 | JOE LUCKEY |
| ZI | Cleared | 8/27/2019 | JOE LUCKEY |
| ZI | Cleared | 8/27/2019 | JOE LUCKEY |
| Eng Process Fee Ord 176,300 | Cleared | 9/6/2019 | JEANETTE VONG |
| Low Impact Development | Cleared | 9/6/2019 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 9/6/2019 | JEANETTE VONG |
| Sewer availability | Cleared | 9/6/2019 | JEANETTE VONG |
| Coastal Zone | Cleared | 10/4/2019 | JOE LUCKEY |
| Miscellaneous | Cleared | 10/4/2019 | JOE LUCKEY |
| ZA Case | Cleared | 10/4/2019 | JOE LUCKEY |
Contact Information
| Contractor | Brunskill Construction Inc; Lic. No.: 847411-B | 2711 N SEPULVEDA BLVD #410 MANHATTAN BEACH, CA 90266 |
| Engineer | Phillips,, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Service/Power Release | 2/6/2020 | Approved | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 4/3/2020 | Approved | CRAIG DAVIS |
| PLUMBING-Rough | 4/3/2020 | Approved | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2020 | Partial Approval | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2020 | Partial Approval | DAVID HEINE |
| PLUMBING-Rough | 7/1/2020 | Approved | DAVID HEINE |
| ELECTRICAL-Rough | 7/13/2020 | Approved | DAVID HEINE |
| Green Building Rough | 7/13/2020 | Not Ready for Inspection | DAVID HEINE |
| HVAC-Rough | 7/13/2020 | Approved | DAVID HEINE |
| BUILDING-Rough-Frame | 8/6/2020 | Partial Approval | DAVID HEINE |
| Green Building Rough | 8/6/2020 | Not Ready for Inspection | DAVID HEINE |
| BUILDING-Rough-Frame | 8/27/2020 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 8/27/2020 | Approved | CARLOS MATAMOROS |
| Shower Pan | 8/27/2020 | Approved | CARLOS MATAMOROS |
| Insulation | 9/11/2020 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 9/11/2020 | Partial Approval | JOHNNY MIRANDA |
| Drywall Nailing | 9/21/2020 | Approved | DAVID HEINE |
| Interior/Exterior Lathing | 10/5/2020 | Approved | DAVID HEINE |
| Gas Test | 12/3/2020 | Corrections Issued | JOHNNY MIRANDA |
| Gas Test | 12/10/2020 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 2/3/2021 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 2/5/2021 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 2/5/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Final | 2/26/2021 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 2/26/2021 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 2/26/2021 | SGSOV Approved | ENRIQUE MIRELES |
| Service/Power Release | 2/26/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Smoke Detectors | 2/26/2021 | Approved | ENRIQUE MIRELES |
| Final | 3/31/2021 | Corrections Issued | ENRIQUE MIRELES |
| Service/Power Release | 3/31/2021 | Approved | ENRIQUE MIRELES |
| Final | 4/23/2021 | Conditional Approval | ENRIQUE MIRELES |
| Special/Order Compliance | 5/7/2021 | Approved | ENRIQUE MIRELES |