3522 S GREENFIELD AVE 90034

Certificate Information: 3522 S GREENFIELD AVE 90034

Application / Permit
19014-30000-01535
Plan Check / Job No.
B19WL01647
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition and remodel to (E) single family dwelling.
Permit Issued
Issued on 3/9/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 11/18/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/27/2019 APPLICANT
Assigned to Plan Check Engineer 4/25/2019 ALFREDO JARA
Green Plans Picked Up 4/25/2019 APPLICANT
Corrections Issued 4/29/2019 ALFREDO JARA
Quality Review Completed 5/10/2019 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 5/13/2019 APPLICANT
Plan Check Approved 3/4/2020 ALFREDO JARA
Issued 3/9/2020 LADBS
CofO in Progress 11/18/2020 KENNETH NAGLE
Permit Finaled 11/18/2020 VINCENT COTTON
CofO Issued 11/18/2020 VINCENT COTTON
Permit Finaled 11/18/2020 VINCENT COTTON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/11/2020 DINAH GARIN
Grading Pre-Inspection Cleared 2/11/2020 ALFREDO JARA
Roof/Waste drainage to street Cleared 2/11/2020 HISASHI KOBAYAKAWA
ZA Case Cleared 2/11/2020 NOAH MCCOY
Green Code Cleared 3/4/2020 DONALD CRICHLOW

Contact Information

Architect Zellman,, Harold Alan; Lic. No.: C12968 553 MUSKINGUM PLACE      PACIFIC PALISADES, CA 90272
Contractor Capper Construction; Lic. No.: 413563-B 19222 KENYA STREET      NORTHRIDGE, CA 91326
Engineer Mezey,, Steven William; Lic. No.: S2665 14017 HARTSOOK ST      SHERMAN OAKS, CA 91423

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/26/2020 Conditional Approval EVAN COOPER
Footing/Foundation/Slab 3/27/2020 Approved EVAN COOPER
BUILDING-Rough-Frame 4/14/2020 Partial Approval OGANES TARAKHCHYAN
Green Building Rough 4/14/2020 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 4/14/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 4/30/2020 Partial Approval TIM CHRISTENSEN
Special/Order Compliance 4/30/2020 Corrections Issued TIM CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 5/5/2020 Partial Inspection KENNETH NAGLE
ELECTRICAL-Rough 6/11/2020 Partial Approval JUSTIN CURTIS
HVAC-Rough 6/11/2020 Approved JUSTIN CURTIS
PLUMBING-Rough 6/11/2020 Partial Approval JUSTIN CURTIS
Insulation 6/19/2020 Corrections Issued CARLOS MATAMOROS
BUILDING-Rough-Frame 6/22/2020 Conditional Approval JUSTIN CURTIS
Green Building Rough 6/22/2020 Approved JUSTIN CURTIS
Insulation 6/22/2020 Approved JUSTIN CURTIS
Drywall Nailing 6/25/2020 Approved JUSTIN CURTIS
ELECTRICAL-Final 8/21/2020 Not Ready for Inspection EVAN COOPER
Interior/Exterior Lathing 8/21/2020 Approved EVAN COOPER
ELECTRICAL-Final 10/21/2020 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Final 10/21/2020 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Final 10/21/2020 Not Ready for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 10/29/2020 Approved EVAN COOPER
Final 10/29/2020 Corrections Issued EVAN COOPER
Green Building Final 10/29/2020 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 10/29/2020 SGSOV Approved EVAN COOPER
Smoke Detectors 10/29/2020 Approved EVAN COOPER
Service/Power Release 11/10/2020 Approved KENNETH NAGLE
Final 11/18/2020 OK to Issue CofO KENNETH NAGLE