4525 N CAMELLIA AVE 91602
Certificate Information: 4525 N CAMELLIA AVE 91602
- Application / Permit
- 19014-30000-01303
- Plan Check / Job No.
- B19WL01396
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1-STORY ADDITION TO (E) 1-STORY SFD W/ ATT. 2-CAR GARAGE.
- Permit Issued
- Issued on 12/17/2020
- Issuing Office
- Current Status
- CofO Issued on 8/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/14/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/11/2019 | REZA HAGHIGHAT |
| Corrections Issued | 4/15/2019 | REZA HAGHIGHAT |
| Green Plans Picked Up | 4/19/2019 | APPLICANT |
| Quality Review Completed | 4/26/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 6/17/2019 | SERGIO SILVA |
| Plan Check Approved | 9/5/2019 | REZA HAGHIGHAT |
| Issued | 12/17/2020 | APPLICANT |
| Building Plans Picked Up | 12/23/2020 | APPLICANT |
| CofO in Progress | 7/22/2022 | THOMAS FINNILA |
| Permit Finaled | 8/25/2022 | DANIEL ORRANTE |
| CofO Issued | 8/25/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/25/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/16/2019 | JOSE CRUZ RODRIGUEZ |
| Green Code | Cleared | 5/16/2019 | DONALD CRICHLOW |
| Sewer availability | Cleared | 5/16/2019 | JOSE CRUZ RODRIGUEZ |
| Highway dedication | Cleared | 6/7/2019 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 6/7/2019 | GUILLERMO PETRA |
| CPC | Cleared | 6/17/2019 | SHEILA GERSHON |
| CPC | Cleared | 6/17/2019 | SHEILA GERSHON |
| ZI | Cleared | 6/17/2019 | SHEILA GERSHON |
Contact Information
| Architect | Carson, Han, William; Lic. No.: C31806 | 3528 MULTIVIEW DRIVE LOS ANGELES, CA 90068 |
| Contractor | Goodhand Builders Inc; Lic. No.: 1026005-B | 2222 FOOTHILL BLVD SUITE E117 LA CANADA, CA 91011 |
| Engineer | Choi,, David; Lic. No.: S4784 | 1327 LOMA AVENUE LONG BEACH, CA 90804 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/30/2020 | Partial Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 1/8/2021 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2021 | Conditional Approval | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 3/3/2021 | Conditional Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 4/9/2021 | Corrections Issued | THOMAS FINNILA |
| HVAC-Rough | 4/9/2021 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 4/9/2021 | Approved | THOMAS FINNILA |
| ELECTRICAL-Rough | 6/14/2021 | Partial Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 6/28/2021 | Conditional Approval | THOMAS FINNILA |
| Green Building Rough | 6/28/2021 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 6/28/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Insulation | 7/21/2021 | Conditional Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 7/30/2021 | Partial Approval | THOMAS FINNILA |
| Drywall Nailing | 7/30/2021 | Approved | THOMAS FINNILA |
| Insulation | 7/30/2021 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 6/9/2022 | Approved | THOMAS FINNILA |
| ELECTRICAL-Final | 6/9/2022 | Approved | THOMAS FINNILA |
| HVAC-Final | 6/9/2022 | Approved | THOMAS FINNILA |
| MERV13>=Rough | 6/9/2022 | Approved | THOMAS FINNILA |
| PLUMBING-Final | 6/9/2022 | Approved | THOMAS FINNILA |
| Final | 7/14/2022 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 7/14/2022 | Approved | THOMAS FINNILA |
| Green Building Final | 7/14/2022 | Approved | THOMAS FINNILA |
| MERV13>=Final | 7/14/2022 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 7/14/2022 | SGSOV Approved | THOMAS FINNILA |
| Smoke Detectors | 7/14/2022 | Approved | THOMAS FINNILA |
| Final | 7/21/2022 | OK to Issue CofO | THOMAS FINNILA |