10348 W NORTHVALE ROAD 90064

Certificate Information: 10348 W NORTHVALE ROAD 90064

Application / Permit
19014-30000-01156
Plan Check / Job No.
B19WL01255
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO (E) SINGLE FAMILY DWELLING W/ATT GARAGE & INTERIOR/EXTERIOR REMODEL
Permit Issued
Issued on 9/11/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 7/21/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/7/2019 APPLICANT
Assigned to Plan Check Engineer 3/21/2019 LAMAR DAVIS
Corrections Issued 3/26/2019 LAMAR DAVIS
Green Plans Picked Up 3/27/2019 APPLICANT
Quality Review Completed 4/4/2019 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 4/5/2019 APPLICANT
Applicant returned to address corrections 6/5/2019 LAMAR DAVIS
Plan Check Approved 7/26/2019 LAMAR DAVIS
Issued 9/11/2019 LADBS
CofO in Progress 7/9/2021 EVAN COOPER
Permit Finaled 7/21/2021 KENNETH NAGLE
CofO Issued 7/21/2021 KENNETH NAGLE
Permit Finaled 7/21/2021 KENNETH NAGLE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/21/2019 TIMOTHY POWELL
Eng Process Fee Ord 176,300 Cleared 5/22/2019 KARAN PATEL
Low Impact Development Cleared 5/22/2019 RYAN HUDSON
Permit Cleared 5/22/2019 KARAN PATEL
Roof/Waste drainage to street Cleared 5/22/2019 KARAN PATEL
Sewer availability Cleared 5/22/2019 KARAN PATEL
Green Code Cleared 5/30/2019 RICHARD GARCIA
Trees in Parkway Cleared 6/26/2019 ADRIAN SANCHEZ
GPI Written Notices Cleared 7/16/2019 GRANT WOODS

Contact Information

Contractor M Y Construction Inc; Lic. No.: 1036168-B 10116 HILLGROVE DRIVE      BEVERLY HILLS, CA 90210
Engineer Snedaker,, Richard Martin; Lic. No.: L7565 PO BOX 2305      IRWINDALE, CA 91706
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/26/2019 Approved RONALD WEBER
Footing/Foundation/Slab 9/26/2019 Approved RONALD WEBER
PLUMBING-Rough 10/7/2019 Corrections Issued OGANES TARAKHCHYAN
PLUMBING-Rough 10/11/2019 Partial Approval RONALD WEBER
Wood Frame 10/11/2019 Partial Approval RONALD WEBER
Floor/Roof Diaphrgm/Shear Wall 11/19/2019 Approved RONALD WEBER
HVAC-Rough 1/30/2020 Corrections Issued RONALD WEBER
BUILDING-Rough-Frame 2/25/2020 Corrections Issued RONALD WEBER
ELECTRICAL-Rough 2/25/2020 Approved RONALD WEBER
Floor/Roof Diaphrgm/Shear Wall 2/25/2020 Approved RONALD WEBER
HVAC-Rough 2/25/2020 Approved RONALD WEBER
PLUMBING-Rough 2/25/2020 Corrections Issued RONALD WEBER
Floor/Roof Diaphrgm/Shear Wall 3/9/2020 Approved RONALD WEBER
Insulation 3/9/2020 Approved RONALD WEBER
Interior/Exterior Lathing 3/9/2020 Approved RONALD WEBER
Drywall Nailing 3/23/2020 Approved CARLOS MATAMOROS
Green Building Rough 3/23/2020 Approved CARLOS MATAMOROS
Shower Pan 5/14/2020 Not Ready for Inspection KEVIN SARGSYAN
Interior/Exterior Lathing 6/10/2020 Approved KEVIN SARGSYAN
Shower Pan 6/10/2020 Approved KEVIN SARGSYAN
Service/Power Release 7/15/2020 Corrections Issued KEVIN SARGSYAN
Gas Test 8/14/2020 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Final 8/20/2020 Not Ready for Inspection KEVIN SARGSYAN
Gas Test 8/20/2020 Approved KEVIN SARGSYAN
Service/Power Release 8/20/2020 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Final 9/4/2020 Approved KEVIN SARGSYAN
Special/Order Compliance 9/10/2020 Partial Inspection KEVIN SARGSYAN
HVAC-Final 9/17/2020 Corrections Issued KEVIN SARGSYAN
PLUMBING-Final 9/17/2020 Corrections Issued KEVIN SARGSYAN
Service/Power Release 9/21/2020 Approved KENNETH NAGLE
HVAC-Final 10/1/2020 Corrections Issued KEVIN SARGSYAN
PLUMBING-Final 10/1/2020 Corrections Issued KEVIN SARGSYAN
HVAC-Final 10/7/2020 Corrections Issued KEVIN SARGSYAN
PLUMBING-Final 10/7/2020 Approved KEVIN SARGSYAN
HVAC-Final 10/15/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
MERV13>=Final 10/15/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
HVAC-Final 11/9/2020 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 4/26/2021 Approved KEVIN SARGSYAN
Final 4/26/2021 Corrections Issued KEVIN SARGSYAN
Green Building Final 4/26/2021 Approved KEVIN SARGSYAN
MERV13>=Final 4/26/2021 Approved KEVIN SARGSYAN
MERV13>=Rough 4/26/2021 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 4/26/2021 SGSOV Approved KEVIN SARGSYAN
Smoke Detectors 4/26/2021 Approved KEVIN SARGSYAN
Final 6/9/2021 Corrections Issued KEVIN SARGSYAN
Final 6/22/2021 Not Ready for Inspection KEVIN SARGSYAN
Final 7/9/2021 Conditional Approval EVAN COOPER