2815 S OCEAN AVE 90291
Certificate Information: 2815 S OCEAN AVE 90291
- Application / Permit
- 19014-30000-01032
- Plan Check / Job No.
- B19WL01110
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2ND STORY ADDITION AND REMODEL TO EXISTING 1-STORY SFD.
- Permit Issued
- Issued on 2/2/2021
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 6/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 3/21/2019 | EMMANUEL MARTINEZ |
| Corrections Issued | 3/27/2019 | EMMANUEL MARTINEZ |
| Quality Review Completed | 4/8/2019 | JOSE RODRIGUEZ |
| Green Plans Picked Up | 4/10/2019 | APPLICANT |
| Applicant returned to address corrections | 6/11/2019 | EMMANUEL MARTINEZ |
| Plan Check Approved | 7/2/2019 | EMMANUEL MARTINEZ |
| No Progress | 10/3/2020 | FERNANDO FLORES |
| Plan Check Approved | 1/19/2021 | GEORGE ALVAREZ |
| Building Plans Picked Up | 1/25/2021 | APPLICANT |
| Issued | 2/2/2021 | APPLICANT |
| CofO in Progress | 6/17/2024 | HERBERT GIRON |
| Permit Finaled | 6/24/2024 | DANIEL ORRANTE |
| CofO Issued | 6/24/2024 | DANIEL ORRANTE |
| Permit Finaled | 6/24/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 5/31/2019 | ANDRES COVARRUBIAS |
| Eng Process Fee Ord 176,300 | Cleared | 6/11/2019 | KARAN PATEL |
| Miscellaneous | Cleared | 6/11/2019 | ANNA VAN |
| Miscellaneous | Cleared | 6/11/2019 | ANNA VAN |
| Roof/Waste drainage to street | Cleared | 6/11/2019 | KARAN PATEL |
| Sewer availability | Cleared | 6/11/2019 | KARAN PATEL |
| ZI | Cleared | 6/11/2019 | ANNA VAN |
| ZI | Cleared | 6/11/2019 | ANNA VAN |
| Green Code | Cleared | 6/19/2019 | DONALD CRICHLOW |
| Coastal Zone | Cleared | 6/24/2019 | LATANYA ROUX |
| Miscellaneous | Cleared | 6/24/2019 | LATANYA ROUX |
| Specific Plan | Cleared | 6/24/2019 | LATANYA ROUX |
| ZI | Cleared | 6/24/2019 | LATANYA ROUX |
| ZI | Cleared | 6/24/2019 | LATANYA ROUX |
Contact Information
| Contractor | Klein Construction; Lic. No.: 891079-B | 13858 CHANDLER BLVD SHERMAN OAKS, CA 91401 |
| Engineer | Baad,, Katherine Firestone; Lic. No.: C64669 | 5232 ZAKON RD TORRANCE, CA 90505 |
| Engineer | Wood,, Donald Edwin; Lic. No.: C23276 | 8816 FOOTHILL BLVD RANCHO CUCAMONGA, CA 91730 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/4/2021 | No Access for Inspection | JOHNNY MIRANDA |
| Deputy Drilled-In Anchors | 2/5/2021 | Approved | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 2/5/2021 | Approved | JOHNNY MIRANDA |
| METHANE-Barrier | 2/5/2021 | Approved | JOHNNY MIRANDA |
| METHANE-Subgrade | 2/5/2021 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2021 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 2/24/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| METHANE-Rough | 2/24/2021 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 4/13/2021 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 4/13/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Rough | 4/13/2021 | Corrections Issued | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 4/14/2021 | Corrections Issued | JOHNNY MIRANDA |
| HVAC-Rough | 4/14/2021 | Corrections Issued | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 4/22/2021 | Approved | KENNETH NAGLE |
| HVAC-Rough | 4/22/2021 | Approved | KENNETH NAGLE |
| BUILDING-Rough-Frame | 4/23/2021 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 4/23/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Shower Pan | 4/26/2021 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 5/12/2021 | Approved | JOHNNY MIRANDA |
| Deputy Wood Construction | 5/12/2021 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2021 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 5/12/2021 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 5/12/2021 | Partial Approval | JOHNNY MIRANDA |
| Insulation | 5/17/2021 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 5/20/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Green Building Final | 5/20/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 5/20/2021 | SGSOV Not Ready | JOHNNY MIRANDA |
| Smoke Detectors | 5/20/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Drywall Nailing | 5/25/2021 | Approved | PIERRE VEGA |
| Interior/Exterior Lathing | 5/25/2021 | Approved | PIERRE VEGA |
| ELECTRICAL-Final | 9/7/2021 | Corrections Issued | JOHNNY MIRANDA |
| Final | 9/7/2021 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Final | 9/7/2021 | Corrections Issued | JOHNNY MIRANDA |
| HVAC-Final | 9/7/2021 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Final | 9/7/2021 | Corrections Issued | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 9/7/2021 | SGSOV Approved | JOHNNY MIRANDA |
| Smoke Detectors | 9/7/2021 | Approved | JOHNNY MIRANDA |
| Final | 5/21/2024 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 5/21/2024 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 6/4/2024 | Approved | HERBERT GIRON |
| Final | 6/4/2024 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Final | 6/4/2024 | Approved | HERBERT GIRON |
| Final | 6/17/2024 | OK to Issue CofO | HERBERT GIRON |
| HVAC-Final | 6/17/2024 | Approved | HERBERT GIRON |