2815 S OCEAN AVE 90291

Certificate Information: 2815 S OCEAN AVE 90291

Application / Permit
19014-30000-01032
Plan Check / Job No.
B19WL01110
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2ND STORY ADDITION AND REMODEL TO EXISTING 1-STORY SFD.
Permit Issued
Issued on 2/2/2021
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2019 APPLICANT
Assigned to Plan Check Engineer 3/21/2019 EMMANUEL MARTINEZ
Corrections Issued 3/27/2019 EMMANUEL MARTINEZ
Quality Review Completed 4/8/2019 JOSE RODRIGUEZ
Green Plans Picked Up 4/10/2019 APPLICANT
Applicant returned to address corrections 6/11/2019 EMMANUEL MARTINEZ
Plan Check Approved 7/2/2019 EMMANUEL MARTINEZ
No Progress 10/3/2020 FERNANDO FLORES
Plan Check Approved 1/19/2021 GEORGE ALVAREZ
Building Plans Picked Up 1/25/2021 APPLICANT
Issued 2/2/2021 APPLICANT
CofO in Progress 6/17/2024 HERBERT GIRON
Permit Finaled 6/24/2024 DANIEL ORRANTE
CofO Issued 6/24/2024 DANIEL ORRANTE
Permit Finaled 6/24/2024 DANIEL ORRANTE

Permit Application Clearance Information

Low Impact Development Cleared 5/31/2019 ANDRES COVARRUBIAS
Eng Process Fee Ord 176,300 Cleared 6/11/2019 KARAN PATEL
Miscellaneous Cleared 6/11/2019 ANNA VAN
Miscellaneous Cleared 6/11/2019 ANNA VAN
Roof/Waste drainage to street Cleared 6/11/2019 KARAN PATEL
Sewer availability Cleared 6/11/2019 KARAN PATEL
ZI Cleared 6/11/2019 ANNA VAN
ZI Cleared 6/11/2019 ANNA VAN
Green Code Cleared 6/19/2019 DONALD CRICHLOW
Coastal Zone Cleared 6/24/2019 LATANYA ROUX
Miscellaneous Cleared 6/24/2019 LATANYA ROUX
Specific Plan Cleared 6/24/2019 LATANYA ROUX
ZI Cleared 6/24/2019 LATANYA ROUX
ZI Cleared 6/24/2019 LATANYA ROUX

Contact Information

Contractor Klein Construction; Lic. No.: 891079-B 13858 CHANDLER BLVD      SHERMAN OAKS, CA 91401
Engineer Baad,, Katherine Firestone; Lic. No.: C64669 5232 ZAKON RD      TORRANCE, CA 90505
Engineer Wood,, Donald Edwin; Lic. No.: C23276 8816 FOOTHILL BLVD      RANCHO CUCAMONGA, CA 91730

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/4/2021 No Access for Inspection JOHNNY MIRANDA
Deputy Drilled-In Anchors 2/5/2021 Approved JOHNNY MIRANDA
Footing/Foundation/Slab 2/5/2021 Approved JOHNNY MIRANDA
METHANE-Barrier 2/5/2021 Approved JOHNNY MIRANDA
METHANE-Subgrade 2/5/2021 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 2/24/2021 Partial Approval JOHNNY MIRANDA
Green Building Rough 2/24/2021 Not Ready for Inspection JOHNNY MIRANDA
METHANE-Rough 2/24/2021 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 4/13/2021 Partial Approval JOHNNY MIRANDA
Green Building Rough 4/13/2021 Not Ready for Inspection JOHNNY MIRANDA
PLUMBING-Rough 4/13/2021 Corrections Issued JOHNNY MIRANDA
ELECTRICAL-Rough 4/14/2021 Corrections Issued JOHNNY MIRANDA
HVAC-Rough 4/14/2021 Corrections Issued JOHNNY MIRANDA
ELECTRICAL-Rough 4/22/2021 Approved KENNETH NAGLE
HVAC-Rough 4/22/2021 Approved KENNETH NAGLE
BUILDING-Rough-Frame 4/23/2021 Partial Approval JOHNNY MIRANDA
Green Building Rough 4/23/2021 Not Ready for Inspection JOHNNY MIRANDA
Shower Pan 4/26/2021 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 5/12/2021 Approved JOHNNY MIRANDA
Deputy Wood Construction 5/12/2021 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 5/12/2021 Approved JOHNNY MIRANDA
Green Building Rough 5/12/2021 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 5/12/2021 Partial Approval JOHNNY MIRANDA
Insulation 5/17/2021 Approved JOHNNY MIRANDA
Drywall Nailing 5/20/2021 Not Ready for Inspection JOHNNY MIRANDA
Green Building Final 5/20/2021 Not Ready for Inspection JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 5/20/2021 SGSOV Not Ready JOHNNY MIRANDA
Smoke Detectors 5/20/2021 Not Ready for Inspection JOHNNY MIRANDA
Drywall Nailing 5/25/2021 Approved PIERRE VEGA
Interior/Exterior Lathing 5/25/2021 Approved PIERRE VEGA
ELECTRICAL-Final 9/7/2021 Corrections Issued JOHNNY MIRANDA
Final 9/7/2021 Corrections Issued JOHNNY MIRANDA
Green Building Final 9/7/2021 Corrections Issued JOHNNY MIRANDA
HVAC-Final 9/7/2021 Corrections Issued JOHNNY MIRANDA
PLUMBING-Final 9/7/2021 Corrections Issued JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 9/7/2021 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 9/7/2021 Approved JOHNNY MIRANDA
Final 5/21/2024 Corrections Issued HERBERT GIRON
Green Building Final 5/21/2024 Approved HERBERT GIRON
ELECTRICAL-Final 6/4/2024 Approved HERBERT GIRON
Final 6/4/2024 Not Ready for Inspection HERBERT GIRON
PLUMBING-Final 6/4/2024 Approved HERBERT GIRON
Final 6/17/2024 OK to Issue CofO HERBERT GIRON
HVAC-Final 6/17/2024 Approved HERBERT GIRON