6465 W 87TH PL 90045

Certificate Information: 6465 W 87TH PL 90045

Application / Permit
19014-30000-00910
Plan Check / Job No.
B19WL01014
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1-story addition and alteration to (e) 1-story s.f.d.
Permit Issued
Issued on 11/29/2022
Issuing Office
Valley
Current Status
Issued on 11/29/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 2/25/2019 APPLICANT
Green Plans Picked Up 3/8/2019 APPLICANT
Assigned to Plan Check Engineer 3/14/2019 REZA HAGHIGHAT
Corrections Issued 3/18/2019 REZA HAGHIGHAT
Quality Review Completed 3/28/2019 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 3/29/2019 APPLICANT
Plan Check Approved 11/22/2022 REZA HAGHIGHAT
Issued 11/29/2022 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 8/20/2022 STEVEN JIN
Eng Process Fee Ord 176,300 Cleared 9/15/2022 HISASHI KOBAYAKAWA
Green Code Cleared 11/22/2022 DONALD CRICHLOW
Roof/Waste drainage to street Cleared 11/22/2022 HISASHI KOBAYAKAWA

Contact Information

Contractor Leli Construction Inc; Lic. No.: 1067323-B 45 N SAN MARINO AVE      PASADENA, CA 91107
Engineer Yaprak,, Taskin Tolga; Lic. No.: C72927 708 SOUTH REDONDO AVE      MANHATTAN BEACH, CA 90266

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/7/2023 Corrections Issued HERBERT GIRON
Excavation/Setback/Form/Re-Bar 4/17/2023 Approved BOBBY KEY
Footing/Foundation/Slab 4/17/2023 Approved BOBBY KEY
Sewer 4/21/2023 Approved BOBBY KEY
BUILDING-Rough-Frame 5/3/2023 Conditional Approval HERBERT GIRON
PLUMBING-Rough 5/3/2023 Conditional Approval HERBERT GIRON
BUILDING-Rough-Frame 5/5/2023 Partial Approval HERBERT GIRON
Insulation 5/5/2023 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 5/8/2023 Partial Approval BOBBY KEY
PLUMBING-Rough 5/8/2023 Corrections Issued BOBBY KEY
PLUMBING-Rough 5/11/2023 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 5/30/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 6/7/2023 Not Ready for Inspection BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 6/7/2023 Corrections Issued BOBBY KEY
HVAC-Rough 6/7/2023 Corrections Issued BOBBY KEY
PLUMBING-Rough 6/7/2023 Approved BOBBY KEY
BUILDING-Rough-Frame 6/14/2023 Approved BOBBY KEY
ELECTRICAL-Rough 6/14/2023 Approved BOBBY KEY
Green Building Rough 6/14/2023 Approved BOBBY KEY
HVAC-Rough 6/14/2023 Approved BOBBY KEY
Interior/Exterior Lathing 6/14/2023 Partial Approval BOBBY KEY
PLUMBING-Rough 6/14/2023 Approved BOBBY KEY
Insulation 6/26/2023 Approved BOBBY KEY
Drywall Nailing 7/3/2023 Approved BOBBY KEY
Insulation 7/21/2023 Approved BOBBY KEY
Interior/Exterior Lathing 7/21/2023 Approved BOBBY KEY
Shower Pan 7/21/2023 Approved BOBBY KEY
Shower Pan 7/21/2023 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Final 7/2/2024 Corrections Issued BOBBY KEY
Final 7/2/2024 Corrections Issued BOBBY KEY
Green Building Final 7/2/2024 Approved BOBBY KEY
HVAC-Final 7/2/2024 Corrections Issued BOBBY KEY
PLUMBING-Final 7/2/2024 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 7/2/2024 SGSOV Approved BOBBY KEY
Smoke Detectors 7/2/2024 Approved BOBBY KEY