10236 W CHARING CROSS ROAD 90024

Certificate Information: 10236 W CHARING CROSS ROAD 90024

Application / Permit
19014-30000-00804
Plan Check / Job No.
B19WL00855
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF (42'-3"x 23'-1") 1-STORY SOLARIUM ABOVE (E) BASEMENT AND ALTERATION/ INTERIOR REMODEL TO (E) SINGLE FAMILY DWELLING. WORK PER ENGINEER.
Permit Issued
Issued on 7/2/2019
Issuing Office
Valley
Current Status
CofO Issued on 10/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/19/2019 APPLICANT
Assigned to Plan Check Engineer 2/28/2019 TROY DEGUZMAN
Green Plans Picked Up 2/28/2019 APPLICANT
Corrections Issued 3/4/2019 TROY DEGUZMAN
Quality Review Completed 3/12/2019 MARJAN SHENASI
Building Plans Picked Up 3/14/2019 APPLICANT
Applicant returned to address corrections 4/18/2019 TROY DEGUZMAN
Applicant returned to address corrections 5/1/2019 TROY DEGUZMAN
Applicant returned to address corrections 5/6/2019 TROY DEGUZMAN
Applicant returned to address corrections 7/1/2019 TROY DEGUZMAN
Plan Check Approved 7/2/2019 TROY DEGUZMAN
Issued 7/2/2019 LADBS
CofO in Progress 10/17/2024 CHRISTOPHER WILSON
Permit Finaled 10/22/2024 RICHARD STEINBACH
CofO Issued 10/22/2024 RICHARD STEINBACH
Permit Finaled 10/22/2024 RICHARD STEINBACH

Permit Application Clearance Information

City Hist. Cultural Monument Cleared 3/15/2019 LAMBERT GIESSINGER
Historic monument Cleared 3/15/2019 LAMBERT GIESSINGER
Grading Pre-Inspection Cleared 5/1/2019 TROY DEGUZMAN
Green Code Cleared 5/22/2019 DONALD CRICHLOW
Hydrant and Access approval Cleared 5/22/2019 JOHN CONNEALLY
ZA Case Cleared 6/6/2019 TREVOR MARTIN
Low Impact Development Cleared 6/11/2019 ANDRES COVARRUBIAS
Eng Process Fee Ord 176,300 Cleared 6/21/2019 ELAINE LEI
Roof/Waste drainage to street Cleared 6/21/2019 ELAINE LEI
Sewer availability Cleared 6/21/2019 ELAINE LEI
ZA Case Cleared 7/2/2019 NOAH MCCOY

Contact Information

Architect Landry,, Richard; Lic. No.: C21848 1818 S.SEPULVEDA BLVD      LOS ANGELES, CA 90025
Contractor Owner-Builder       ,
Engineer Resnick,, Bruce Daniel; Lic. No.: S3293 1927 PONTIUS AVE      LOS ANGELES, CA 90025

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/7/2019 Not Ready for Inspection TIM CHRISTENSEN
Deputy Shotcrete 11/19/2019 Conditional Approval GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 1/14/2020 Partial Approval MATT KELLERMAN
Green Building Rough 1/14/2020 Partial Approval MATT KELLERMAN
Footing/Foundation/Slab 2/28/2020 Not Ready for Inspection MATT KELLERMAN
BUILDING-Rough-Frame 4/21/2020 Partial Approval MATT KELLERMAN
Green Building Rough 4/21/2020 Partial Approval MATT KELLERMAN
Excavation/Setback/Form/Re-Bar 5/11/2020 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 5/11/2020 Partial Inspection CHRISTOPHER WILSON
Wood Frame 5/14/2020 Partial Approval MATT KELLERMAN
Excavation/Setback/Form/Re-Bar 6/4/2020 Corrections Issued MATT KELLERMAN
Footing/Foundation/Slab 6/5/2020 Partial Approval MATT KELLERMAN
Excavation/Setback/Form/Re-Bar 6/12/2020 Corrections Issued CHRISTOPHER WILSON
Reinforced Concrete Frame 6/15/2020 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 6/25/2020 Partial Approval MATT KELLERMAN
Footing/Foundation/Slab 7/9/2020 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 7/13/2020 Partial Approval MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 7/16/2020 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 7/16/2020 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 7/16/2020 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 8/6/2020 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 8/10/2020 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 8/13/2020 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 8/26/2020 Not Ready for Inspection MATT KELLERMAN
Footing/Foundation/Slab 8/26/2020 Not Ready for Inspection MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 8/28/2020 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 9/1/2020 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 9/21/2020 Partial Approval MATT KELLERMAN
Interior/Exterior Lathing 9/29/2020 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 9/29/2020 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 10/6/2020 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 10/6/2020 Partial Approval MATT KELLERMAN
Underground Mechanical 10/6/2020 Partial Approval MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 10/7/2020 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 10/7/2020 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 10/14/2020 Partial Approval MATT KELLERMAN
Deputy Reinf. Concrete 10/15/2020 Approved MATT KELLERMAN
Reinforced Concrete Frame 10/15/2020 Partial Approval MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 10/27/2020 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 10/27/2020 Corrections Issued CHRISTOPHER WILSON
Reinforced Concrete Frame 10/29/2020 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 10/29/2020 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 11/6/2020 Corrections Issued MATT KELLERMAN
Reinforced Concrete Frame 11/6/2020 Partial Approval MATT KELLERMAN
Footing/Foundation/Slab 11/19/2020 Partial Approval MATT KELLERMAN
Footing/Foundation/Slab 11/24/2020 Partial Approval MATT KELLERMAN
PLUMBING-Rough 12/2/2020 Corrections Issued CHRISTOPHER WILSON
Reinforced Concrete Frame 12/7/2020 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 12/7/2020 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 12/9/2020 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 12/9/2020 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 12/11/2020 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 12/11/2020 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 12/14/2020 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 12/17/2020 Partial Approval MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 1/5/2021 Partial Approval MATT KELLERMAN
Underground Mechanical 1/5/2021 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 1/13/2021 Partial Approval MATT KELLERMAN
Footing/Foundation/Slab 1/21/2021 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 1/21/2021 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 1/25/2021 Partial Approval MATT KELLERMAN
Deputy Reinf. Concrete 1/26/2021 Conditional Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 1/28/2021 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 2/1/2021 Not Ready for Inspection CHRISTOPHER WILSON
Underground Mechanical 2/1/2021 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 2/2/2021 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 2/4/2021 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 2/10/2021 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 2/11/2021 Partial Approval MATT KELLERMAN
Underground Mechanical 2/11/2021 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 2/17/2021 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 2/19/2021 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 2/19/2021 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 2/22/2021 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 2/22/2021 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 2/24/2021 Partial Approval MATT KELLERMAN
Footing/Foundation/Slab 2/26/2021 Corrections Issued MATT KELLERMAN
Underground Mechanical 2/26/2021 Partial Approval MATT KELLERMAN
Underground Mechanical 3/4/2021 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 3/5/2021 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 3/8/2021 Partial Approval MATT KELLERMAN
Footing/Foundation/Slab 3/10/2021 Partial Approval MATT KELLERMAN
Underground Mechanical 3/10/2021 Partial Approval MATT KELLERMAN
Underground Mechanical 3/15/2021 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 3/18/2021 Conditional Approval MATT KELLERMAN
Underground Mechanical 3/18/2021 Conditional Approval MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 3/24/2021 Partial Approval MATT KELLERMAN
Footing/Foundation/Slab 3/25/2021 Not Ready for Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 3/26/2021 Partial Approval MATT KELLERMAN
PLUMBING-Rough 3/30/2021 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 3/30/2021 Partial Approval MATT KELLERMAN
Footing/Foundation/Slab 3/31/2021 Partial Approval MATT KELLERMAN
Underground Mechanical 4/5/2021 Partial Approval MATT KELLERMAN
Footing/Foundation/Slab 4/7/2021 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 4/12/2021 Partial Approval MATT KELLERMAN
Underground Mechanical 4/28/2021 Partial Approval MATT KELLERMAN
Drywall Nailing 4/30/2021 Partial Approval MATT KELLERMAN
ELECTRICAL-Rough 4/30/2021 Not Ready for Inspection MATT KELLERMAN
PLUMBING-Rough 4/30/2021 Not Ready for Inspection MATT KELLERMAN
Wood Frame 4/30/2021 Partial Approval MATT KELLERMAN
HVAC-Rough 5/3/2021 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 5/3/2021 Partial Approval CHRISTOPHER WILSON
Deputy Steel/Welding 5/4/2021 Approved MATT KELLERMAN
Excavation/Setback/Form/Re-Bar 5/4/2021 Partial Approval MATT KELLERMAN
Structural Steel Frame 5/4/2021 Partial Approval MATT KELLERMAN
Deputy Steel/Welding 5/5/2021 Conditional Approval CHRISTOPHER WILSON
HVAC-Rough 5/6/2021 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 5/7/2021 Partial Approval MATT KELLERMAN
BUILDING-Rough-Frame 5/11/2021 Partial Approval MATT KELLERMAN
Green Building Rough 5/11/2021 Partial Approval MATT KELLERMAN
Structural Steel Frame 5/11/2021 Partial Approval MATT KELLERMAN
HVAC-Rough 5/12/2021 Partial Approval MATT KELLERMAN
PLUMBING-Rough 5/14/2021 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 5/17/2021 Conditional Approval MATT KELLERMAN
Insulation 5/25/2021 Partial Approval MATT KELLERMAN
Underground Mechanical 5/25/2021 Partial Approval MATT KELLERMAN
Drywall Nailing 6/4/2021 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 6/9/2021 Partial Approval MATT KELLERMAN
Structural Steel Frame 6/9/2021 Partial Approval MATT KELLERMAN
Drywall Nailing 6/14/2021 Partial Approval MATT KELLERMAN
Drywall Nailing 6/15/2021 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 6/15/2021 Partial Approval MATT KELLERMAN
Underground Mechanical 6/15/2021 Partial Approval MATT KELLERMAN
ELECTRICAL-Rough 6/16/2021 Not Ready for Inspection MATT KELLERMAN
HVAC-Rough 6/16/2021 Not Ready for Inspection MATT KELLERMAN
PLUMBING-Rough 6/16/2021 Not Ready for Inspection MATT KELLERMAN
BUILDING-Rough-Frame 6/21/2021 No Access for Inspection MATT KELLERMAN
ELECTRICAL-Rough 6/21/2021 No Access for Inspection MATT KELLERMAN
Green Building Rough 6/21/2021 Not Ready for Inspection MATT KELLERMAN
HVAC-Rough 6/21/2021 No Access for Inspection MATT KELLERMAN
Insulation 6/21/2021 No Access for Inspection MATT KELLERMAN
PLUMBING-Rough 6/21/2021 No Access for Inspection MATT KELLERMAN
Rough-Elec/Plmb/HVAC 6/22/2021 Partial Approval MATT KELLERMAN
PLUMBING-Rough 6/29/2021 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 6/29/2021 No Access for Inspection MATT KELLERMAN
Underground Mechanical 6/29/2021 Partial Approval MATT KELLERMAN
Underground Mechanical 7/6/2021 Not Ready for Inspection MATT KELLERMAN
Special/Order Compliance 7/7/2021 Partial Approval ANTHONY MCDOWALL
Underground Mechanical 7/7/2021 Partial Approval MATT KELLERMAN
Interior/Exterior Lathing 7/9/2021 Partial Approval MATT KELLERMAN
PLUMBING-Rough 7/13/2021 Approved MATT KELLERMAN
ELECTRICAL-Rough 7/14/2021 Partial Approval MATT KELLERMAN
HVAC-Rough 7/16/2021 Not Ready for Inspection MATT KELLERMAN
Interior/Exterior Lathing 7/16/2021 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 7/16/2021 Not Ready for Inspection MATT KELLERMAN
Interior/Exterior Lathing 7/20/2021 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 7/23/2021 Partial Approval MATT KELLERMAN
Structural Steel Frame 7/23/2021 Approved MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 7/28/2021 Partial Approval MATT KELLERMAN
Shower Pan 8/2/2021 Partial Approval MATT KELLERMAN
Structural Steel Frame 8/2/2021 Approved MATT KELLERMAN
ELECTRICAL-Rough 8/6/2021 Partial Approval MATT KELLERMAN
Footing/Foundation/Slab 8/6/2021 Partial Approval MATT KELLERMAN
HVAC-Rough 8/9/2021 Partial Approval MATT KELLERMAN
Excavation/Setback/Form/Re-Bar 8/11/2021 Partial Approval MATT KELLERMAN
Footing/Foundation/Slab 8/11/2021 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 8/11/2021 Approved MATT KELLERMAN
Drywall Nailing 8/17/2021 Partial Approval MATT KELLERMAN
Interior/Exterior Lathing 8/17/2021 Partial Approval MATT KELLERMAN
PLUMBING-Rough 8/17/2021 Partial Approval MATT KELLERMAN
Shower Pan 8/17/2021 Partial Approval MATT KELLERMAN
ELECTRICAL-Rough 8/19/2021 Partial Approval MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 8/19/2021 Partial Approval MATT KELLERMAN
Gas Test 8/19/2021 Partial Approval MATT KELLERMAN
HVAC-Rough 8/19/2021 Partial Approval MATT KELLERMAN
PLUMBING-Rough 8/19/2021 Partial Approval MATT KELLERMAN
Underground Mechanical 8/19/2021 Partial Approval MATT KELLERMAN
Wood Frame 8/19/2021 Partial Approval MATT KELLERMAN
Structural Steel Frame 8/20/2021 Partial Approval MATT KELLERMAN
Structural Steel Frame 8/25/2021 Partial Approval MATT KELLERMAN
Underground Mechanical 8/26/2021 Partial Approval MATT KELLERMAN
Drywall Nailing 8/30/2021 Partial Approval MATT KELLERMAN
Footing/Foundation/Slab 8/30/2021 Partial Approval MATT KELLERMAN
Underground Mechanical 8/30/2021 Partial Approval MATT KELLERMAN
Drywall Nailing 9/1/2021 Partial Approval MATT KELLERMAN
Footing/Foundation/Slab 9/2/2021 Partial Approval MATT KELLERMAN
Underground Mechanical 9/2/2021 Partial Approval MATT KELLERMAN
Drywall Nailing 9/3/2021 Partial Approval MATT KELLERMAN
ELECTRICAL-Rough 9/3/2021 Partial Approval MATT KELLERMAN
PLUMBING-Rough 9/3/2021 Partial Approval MATT KELLERMAN
Structural Steel Frame 9/3/2021 Partial Approval MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 9/7/2021 Partial Approval MATT KELLERMAN
Underground Mechanical 9/7/2021 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 9/10/2021 Partial Approval MATT KELLERMAN
BUILDING-Rough-Frame 9/14/2021 Partial Approval MATT KELLERMAN
Green Building Rough 9/14/2021 Partial Inspection MATT KELLERMAN
Reinforced Concrete Frame 9/14/2021 Partial Approval MATT KELLERMAN
Underground Mechanical 9/14/2021 Not Ready for Inspection MATT KELLERMAN
BUILDING-Rough-Frame 9/17/2021 Not Ready for Inspection CHRISTOPHER WILSON
Pre-Inspection 9/17/2021 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 9/22/2021 Partial Approval MATT KELLERMAN
Underground Mechanical 9/22/2021 Partial Approval MATT KELLERMAN
Underground Mechanical 9/28/2021 Partial Approval MATT KELLERMAN
ELECTRICAL-Rough 9/29/2021 Partial Approval MATT KELLERMAN
PLUMBING-Rough 9/29/2021 Partial Approval MATT KELLERMAN
Structural Steel Frame 9/29/2021 Partial Approval MATT KELLERMAN
Wood Frame 9/29/2021 Partial Approval MATT KELLERMAN
Drywall Nailing 10/1/2021 Partial Approval MATT KELLERMAN
Footing/Foundation/Slab 10/1/2021 Partial Approval MATT KELLERMAN
BUILDING-Rough-Frame 10/13/2021 Not Ready for Inspection CHRISTOPHER WILSON
Drywall Nailing 10/13/2021 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 10/13/2021 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Rough 10/13/2021 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 10/13/2021 Not Ready for Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 10/13/2021 Partial Approval CHRISTOPHER WILSON
Deputy Shotcrete 10/14/2021 Conditional Approval CHRISTOPHER WILSON
Drywall Nailing 10/14/2021 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 10/14/2021 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 10/15/2021 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 10/19/2021 Partial Approval MATT KELLERMAN
Footing/Foundation/Slab 10/19/2021 Not Ready for Inspection MATT KELLERMAN
Reinforced Concrete Frame 10/19/2021 Not Ready for Inspection MATT KELLERMAN
ELECTRICAL-Rough 10/20/2021 Partial Approval MATT KELLERMAN
Reinforced Masonry Frame 10/20/2021 Partial Approval MATT KELLERMAN
Underground Mechanical 10/20/2021 Partial Approval MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 10/22/2021 Partial Approval MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 11/2/2021 Partial Approval MATT KELLERMAN
Footing/Foundation/Slab 11/16/2021 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 11/19/2021 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 11/22/2021 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 11/22/2021 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 11/22/2021 Partial Approval CHRISTOPHER WILSON
Structural Steel Frame 11/22/2021 Corrections Issued CHRISTOPHER WILSON
Underground Mechanical 11/22/2021 Not Ready for Inspection CHRISTOPHER WILSON
Wood Frame 11/22/2021 Partial Approval CHRISTOPHER WILSON
Wood Frame 11/24/2021 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 11/29/2021 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 11/29/2021 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 12/6/2021 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 12/6/2021 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 12/6/2021 Partial Approval CHRISTOPHER WILSON
Wood Frame 12/6/2021 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 12/8/2021 Partial Approval DEANDRE HOFFMAN
Footing/Foundation/Slab 12/10/2021 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 12/10/2021 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 12/13/2021 Partial Approval CHRISTOPHER WILSON
Insulation 12/13/2021 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 12/13/2021 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 12/17/2021 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 12/21/2021 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 1/4/2022 Partial Approval BRENDAN LOONEY
Underground Mechanical 1/7/2022 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 1/10/2022 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 1/12/2022 Corrections Issued CHRISTOPHER WILSON
Drywall Nailing 1/12/2022 Partial Approval CHRISTOPHER WILSON
Green Building Rough 1/12/2022 Partial Inspection CHRISTOPHER WILSON
Underground Mechanical 1/12/2022 Not Ready for Inspection CHRISTOPHER WILSON
Wood Frame 1/12/2022 Not Ready for Inspection CHRISTOPHER WILSON
Underground Mechanical 1/14/2022 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 1/18/2022 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 1/18/2022 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 1/19/2022 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 1/19/2022 Partial Approval CHRISTOPHER WILSON
Green Building Rough 1/19/2022 Not Ready for Inspection CHRISTOPHER WILSON
Drywall Nailing 1/21/2022 Approved DEANDRE HOFFMAN
Drywall Nailing 1/24/2022 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 1/24/2022 Not Ready for Inspection CHRISTOPHER WILSON
HVAC-Rough 1/24/2022 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 1/24/2022 Not Ready for Inspection CHRISTOPHER WILSON
HVAC-Rough 1/26/2022 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 1/26/2022 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 1/26/2022 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 1/28/2022 Not Ready for Inspection CHRISTOPHER WILSON
Shower Pan 1/28/2022 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 1/28/2022 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 2/4/2022 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 2/8/2022 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 2/11/2022 Partial Inspection BRENDAN LOONEY
BUILDING-Rough-Frame 2/22/2022 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 2/22/2022 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 2/22/2022 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 2/22/2022 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 2/23/2022 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 2/24/2022 Corrections Issued CHRISTOPHER WILSON
HVAC-Rough 2/24/2022 Partial Approval CHRISTOPHER WILSON
Insulation 2/24/2022 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 2/24/2022 Partial Approval CHRISTOPHER WILSON
Wood Frame 2/24/2022 Not Ready for Inspection CHRISTOPHER WILSON
Drywall Nailing 2/28/2022 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 2/28/2022 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 2/28/2022 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 2/28/2022 Partial Approval CHRISTOPHER WILSON
Pre-Inspection 2/28/2022 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 2/28/2022 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 3/1/2022 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 3/4/2022 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 3/4/2022 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 3/4/2022 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 3/4/2022 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 3/4/2022 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 3/4/2022 Partial Approval CHRISTOPHER WILSON
Insulation 3/7/2022 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 3/9/2022 Partial Approval BRENDAN LOONEY
Drywall Nailing 3/10/2022 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 3/10/2022 Not Ready for Inspection CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 3/10/2022 Corrections Issued CHRISTOPHER WILSON
Interior/Exterior Lathing 3/10/2022 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 3/11/2022 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 3/11/2022 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 3/11/2022 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 3/14/2022 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 3/14/2022 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 3/15/2022 Partial Approval RYAN SALAZAR
Drywall Nailing 3/17/2022 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 3/17/2022 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 3/22/2022 Not Ready for Inspection CHRISTOPHER WILSON
Underground Mechanical 3/22/2022 Corrections Issued CHRISTOPHER WILSON
Underground Mechanical 3/24/2022 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 3/29/2022 Partial Approval CHRISTOPHER WILSON
Light Gage Steel Frame 3/29/2022 Not Ready for Inspection CHRISTOPHER WILSON
BUILDING-Rough-Frame 4/8/2022 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 4/8/2022 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 4/8/2022 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 4/8/2022 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 4/13/2022 Partial Approval CHRISTOPHER WILSON
Insulation 4/18/2022 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 4/19/2022 Corrections Issued CHRISTOPHER WILSON
Wood Frame 4/27/2022 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 4/28/2022 Corrections Issued CHRISTOPHER WILSON
BUILDING-Rough-Frame 4/29/2022 Partial Approval CHRISTOPHER WILSON
Rough-Elec/Plmb/HVAC 4/29/2022 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 5/5/2022 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 5/5/2022 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 5/11/2022 Partial Approval BRENDAN LOONEY
ELECTRICAL-Rough 6/7/2022 Partial Approval CHRISTOPHER WILSON
Final 6/13/2022 Corrections Issued CHRISTOPHER WILSON
Underground Mechanical 6/13/2022 Partial Approval CHRISTOPHER WILSON
Gas Test 6/14/2022 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 6/14/2022 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 6/20/2022 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 6/20/2022 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 6/20/2022 Partial Approval CHRISTOPHER WILSON
Light Gage Steel Frame 6/20/2022 Not Ready for Inspection CHRISTOPHER WILSON
Underground Mechanical 6/20/2022 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 6/24/2022 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 6/24/2022 Corrections Issued CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 6/24/2022 Partial Approval CHRISTOPHER WILSON
Gas Test 6/24/2022 Corrections Issued CHRISTOPHER WILSON
Light Gage Steel Frame 6/24/2022 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 6/24/2022 Not Ready for Inspection CHRISTOPHER WILSON
Gas Test 6/27/2022 Partial Approval CHRISTOPHER WILSON
Light Gage Steel Frame 6/27/2022 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 6/29/2022 Partial Approval JUAN VALENZUELA
ELECTRICAL-Rough 7/7/2022 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 7/7/2022 Partial Approval CHRISTOPHER WILSON
Sewer 7/18/2022 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Rough 7/19/2022 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 7/19/2022 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 7/19/2022 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 7/19/2022 Corrections Issued CHRISTOPHER WILSON
Reinforced Concrete Frame 7/21/2022 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 7/25/2022 Corrections Issued CHRISTOPHER WILSON
Drywall Nailing 7/26/2022 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 7/26/2022 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 7/27/2022 Partial Approval CHRISTOPHER WILSON
Pre-Inspection 7/27/2022 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 7/29/2022 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 7/29/2022 Not Ready for Inspection CHRISTOPHER WILSON
HVAC-Rough 7/29/2022 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 7/29/2022 Not Ready for Inspection CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 8/3/2022 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 8/3/2022 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 8/5/2022 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 8/5/2022 Not Ready for Inspection CHRISTOPHER WILSON
HVAC-Rough 8/5/2022 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 8/5/2022 Not Ready for Inspection CHRISTOPHER WILSON
Wood Frame 8/5/2022 Not Ready for Inspection CHRISTOPHER WILSON
Insulation 8/8/2022 Partial Approval CHRISTOPHER WILSON
Wood Frame 8/8/2022 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 8/10/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 8/10/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 8/10/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Wood Frame 8/10/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 8/11/2022 Partial Approval ANDREW NAVE
Insulation 8/15/2022 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 8/15/2022 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 8/16/2022 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 8/16/2022 Partial Approval CHRISTOPHER WILSON
Insulation 8/16/2022 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 8/16/2022 Not Ready for Inspection CHRISTOPHER WILSON
Drywall Nailing 8/18/2022 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 8/19/2022 Not Ready for Inspection CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 8/19/2022 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 8/19/2022 Partial Approval CHRISTOPHER WILSON
Wood Frame 8/19/2022 Not Ready for Inspection CHRISTOPHER WILSON
Drywall Nailing 9/19/2022 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 9/19/2022 Not Ready for Inspection CHRISTOPHER WILSON
Underground Mechanical 9/20/2022 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 9/26/2022 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 9/26/2022 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 9/30/2022 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 9/30/2022 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 10/3/2022 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 10/4/2022 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 10/4/2022 Partial Approval CHRISTOPHER WILSON
Green Building Rough 10/4/2022 Not Ready for Inspection CHRISTOPHER WILSON
HVAC-Rough 10/4/2022 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 10/4/2022 Not Ready for Inspection CHRISTOPHER WILSON
Wood Frame 10/4/2022 Not Ready for Inspection CHRISTOPHER WILSON
BUILDING-Rough-Frame 10/5/2022 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 10/5/2022 Partial Approval CHRISTOPHER WILSON
Insulation 10/5/2022 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 10/19/2022 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 10/19/2022 Not Ready for Inspection CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 10/19/2022 SGSOV Not Ready CHRISTOPHER WILSON
Underground Mechanical 10/19/2022 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 10/27/2022 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 10/27/2022 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 10/27/2022 Partial Approval CHRISTOPHER WILSON
Light Gage Steel Frame 10/27/2022 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 10/27/2022 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 10/27/2022 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 11/3/2022 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 11/3/2022 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 11/3/2022 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Rough 11/3/2022 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 11/3/2022 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 11/3/2022 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 11/7/2022 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 11/7/2022 Not Ready for Inspection CHRISTOPHER WILSON
Drywall Nailing 11/17/2022 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 11/22/2022 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 11/22/2022 Partial Approval CARLOS MATAMOROS
Reinforced Concrete Frame 11/22/2022 Partial Approval CARLOS MATAMOROS
Underground Mechanical 12/8/2022 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 12/19/2022 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 12/19/2022 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Rough 12/19/2022 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 1/6/2023 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 1/6/2023 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 1/12/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 1/12/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 1/12/2023 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Wood Frame 1/12/2023 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 1/18/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 1/18/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 1/23/2023 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 1/23/2023 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 1/23/2023 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 1/23/2023 Partial Approval CHRISTOPHER WILSON
Structural Steel Frame 1/23/2023 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 1/24/2023 Partial Approval CHRISTOPHER WILSON
Sewer 1/24/2023 Partial Approval CHRISTOPHER WILSON
Structural Steel Frame 1/27/2023 Corrections Issued CHRISTOPHER WILSON
Underground Mechanical 1/27/2023 Corrections Issued CHRISTOPHER WILSON
Wood Frame 1/27/2023 Not Ready for Inspection CHRISTOPHER WILSON
Structural Steel Frame 1/31/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Underground Mechanical 1/31/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Wood Frame 1/31/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Underground Mechanical 2/6/2023 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 2/9/2023 Partial Approval STEPHANIE SWANSON
Underground Mechanical 2/15/2023 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Underground Mechanical 2/16/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 2/23/2023 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 3/9/2023 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 3/9/2023 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 3/9/2023 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 3/9/2023 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 3/22/2023 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 3/22/2023 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 3/22/2023 Not Ready for Inspection CHRISTOPHER WILSON
Underground Mechanical 3/22/2023 Not Ready for Inspection CHRISTOPHER WILSON
Wood Frame 3/22/2023 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 4/3/2023 Not Ready for Inspection CHRISTOPHER WILSON
Underground Mechanical 4/3/2023 Not Ready for Inspection CHRISTOPHER WILSON
HVAC-Rough 4/11/2023 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 4/11/2023 Corrections Issued CHRISTOPHER WILSON
Wood Frame 4/11/2023 Corrections Issued CHRISTOPHER WILSON
BUILDING-Rough-Frame 4/13/2023 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 4/13/2023 Partial Approval CHRISTOPHER WILSON
Green Building Rough 4/13/2023 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 4/13/2023 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 4/13/2023 Partial Approval CHRISTOPHER WILSON
Insulation 4/17/2023 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 4/21/2023 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 4/26/2023 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 4/26/2023 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 4/26/2023 Partial Approval CHRISTOPHER WILSON
Wood Frame 4/26/2023 Partial Approval CHRISTOPHER WILSON
Insulation 5/5/2023 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 5/5/2023 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 5/5/2023 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 5/9/2023 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 5/11/2023 Approved BRENDAN LOONEY
ELECTRICAL-Rough 5/12/2023 Not Ready for Inspection CHRISTOPHER WILSON
HVAC-Rough 5/12/2023 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 5/12/2023 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 5/16/2023 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 5/16/2023 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 5/16/2023 Partial Approval CHRISTOPHER WILSON
Wood Frame 5/16/2023 Partial Approval CHRISTOPHER WILSON
Structural Steel Frame 5/18/2023 Approved CHRISTOPHER WILSON
Drywall Nailing 5/22/2023 Partial Approval CHRISTOPHER WILSON
Structural Steel Frame 5/22/2023 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 5/23/2023 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 5/23/2023 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 5/23/2023 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 5/26/2023 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 5/26/2023 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 5/26/2023 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 5/26/2023 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 5/31/2023 Corrections Issued CHRISTOPHER WILSON
Drywall Nailing 6/1/2023 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 6/1/2023 Partial Approval CHRISTOPHER WILSON
Underground Mechanical 6/1/2023 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 6/7/2023 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 6/13/2023 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 6/13/2023 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 6/13/2023 Not Ready for Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 6/13/2023 Corrections Issued CHRISTOPHER WILSON
Wood Frame 6/13/2023 Not Ready for Inspection CHRISTOPHER WILSON
Drywall Nailing 6/14/2023 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 6/14/2023 Off-Hour Fees Due
HVAC-Rough 6/14/2023 Off-Hour Fees Due
PLUMBING-Rough 6/14/2023 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 6/14/2023 Off-Hour Fees Due
Reinforced Concrete Frame 6/16/2023 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 6/27/2023 Not Ready for Inspection CHRISTOPHER WILSON
HVAC-Rough 6/27/2023 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 6/27/2023 Not Ready for Inspection CHRISTOPHER WILSON
Structural Steel Frame 6/27/2023 Not Ready for Inspection CHRISTOPHER WILSON
Wood Frame 6/27/2023 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 6/29/2023 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 6/29/2023 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 6/29/2023 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 6/29/2023 Partial Approval CHRISTOPHER WILSON
Wood Frame 6/29/2023 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 7/7/2023 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 7/7/2023 Not Ready for Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 7/7/2023 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 7/13/2023 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 7/13/2023 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 7/13/2023 Partial Approval CHRISTOPHER WILSON
Wood Frame 7/13/2023 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 7/26/2023 Partial Approval BRENDAN LOONEY
Pre-Inspection 8/1/2023 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 8/4/2023 Partial Approval CHRISTOPHER WILSON
Insulation 8/8/2023 Not Ready for Inspection CHRISTOPHER WILSON
Special/Order Compliance 8/9/2023 Corrections Issued CHRISTOPHER WILSON
Drywall Nailing 8/16/2023 Not Ready for Inspection CHRISTOPHER WILSON
Pre-Inspection 8/23/2023 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 9/1/2023 Partial Approval CHRISTOPHER WILSON
Special/Order Compliance 9/1/2023 Corrections Issued CHRISTOPHER WILSON
Pre-Inspection 9/5/2023 Partial Approval CHRISTOPHER WILSON
Pre-Inspection 9/6/2023 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 9/14/2023 Approved CHRISTOPHER WILSON
Pre-Inspection 9/14/2023 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 10/25/2023 Partial Approval CHRISTOPHER WILSON
Shower Pan 10/25/2023 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 10/26/2023 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 10/26/2023 Not Ready for Inspection CHRISTOPHER WILSON
Light Gage Steel Frame 10/26/2023 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 10/26/2023 Not Ready for Inspection CHRISTOPHER WILSON
Drywall Nailing 11/15/2023 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 11/17/2023 Not Ready for Inspection CHRISTOPHER WILSON
Deputy Steel/Welding 12/1/2023 Conditional Approval MICHAEL PELHAM
ELECTRICAL-Final 12/2/2023 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Final 12/2/2023 Off-Hour Fees Due
ELECTRICAL-Rough 12/2/2023 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 12/9/2023 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 12/12/2023 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 12/14/2023 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 12/16/2023 Off-Hour Fees Due
ELECTRICAL-Rough 12/16/2023 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 12/19/2023 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 12/20/2023 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 12/21/2023 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 12/22/2023 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 1/4/2024 Partial Approval STEPHANIE SWANSON
Pre-Inspection 1/10/2024 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 2/17/2024 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 2/17/2024 Off-Hour Fees Due
Underground Mechanical 2/20/2024 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 2/26/2024 Partial Approval CHRISTOPHER WILSON
Green Building Rough 2/26/2024 Partial Approval CHRISTOPHER WILSON
Rough-Elec/Plmb/HVAC 2/26/2024 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 2/27/2024 Approved CHRISTOPHER WILSON
Insulation 2/27/2024 Approved CHRISTOPHER WILSON
Drywall Nailing 3/4/2024 Approved CHRISTOPHER WILSON
Pre-Inspection 3/22/2024 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 5/10/2024 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Final 5/13/2024 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 5/13/2024 Approved CHRISTOPHER WILSON
Service/Power Release 5/13/2024 Approved CHRISTOPHER WILSON
ELECTRICAL-Rough 5/15/2024 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 5/17/2024 Not Ready for Inspection SEAN HAUPT
ELECTRICAL-Rough 5/21/2024 Partial Approval CHRISTOPHER WILSON
Gas Test 5/29/2024 Corrections Issued STEPHANIE SWANSON
Gas Test 6/3/2024 Partial Approval CHRISTOPHER WILSON
Gas Test 6/6/2024 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 7/16/2024 Corrections Issued CHRISTOPHER WILSON
HVAC-Final 9/4/2024 Partial Approval SEAN HAUPT
PLUMBING-Final 9/5/2024 Not Ready for Inspection STEPHANIE SWANSON
Gas Test 9/12/2024 Partial Approval CHRISTOPHER WILSON
Gas Test 9/13/2024 Partial Approval CHRISTOPHER WILSON
HVAC-Final 9/13/2024 Corrections Issued CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 9/13/2024 SGSOV Not Ready CHRISTOPHER WILSON
Special/Order Compliance 9/13/2024 Partial Approval ASHLEY THOMPSON
BUILDING-Rough-Frame 9/14/2024 Approved CHRISTOPHER WILSON
Final 9/14/2024 Corrections Issued CHRISTOPHER WILSON
Green Building Final 9/14/2024 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Rough 9/14/2024 Approved CHRISTOPHER WILSON
Smoke Detectors 9/14/2024 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Final 9/17/2024 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 9/18/2024 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Final 9/19/2024 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 9/20/2024 Corrections Issued CHRISTOPHER WILSON
Final 9/21/2024 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Final 9/21/2024 Approved CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 9/21/2024 SGSOV Approved CHRISTOPHER WILSON
Smoke Detectors 9/21/2024 Not Ready for Inspection CHRISTOPHER WILSON
HVAC-Final 9/23/2024 Partial Approval CHRISTOPHER WILSON
Final 9/24/2024 Not Ready for Inspection CHRISTOPHER WILSON
HVAC-Final 9/24/2024 Approved CHRISTOPHER WILSON
PLUMBING-Final 9/25/2024 Not Ready for Inspection CHRISTOPHER WILSON
BUILDING-Rough-Frame 9/26/2024 Approved CHRISTOPHER WILSON
HVAC-Final 9/26/2024 Approved CHRISTOPHER WILSON
PLUMBING-Final 9/26/2024 Corrections Issued CHRISTOPHER WILSON
Final 9/28/2024 Corrections Issued CHRISTOPHER WILSON
Service/Power Release 9/28/2024 Off-Hour Fees Due
Smoke Detectors 9/28/2024 Corrections Issued CHRISTOPHER WILSON
Pre-Inspection 10/7/2024 Partial Approval CHRISTOPHER WILSON
Final 10/16/2024 OK to Issue CofO CHRISTOPHER WILSON
Smoke Detectors 10/16/2024 Approved CHRISTOPHER WILSON