9455 W EDEN DR 90210
Certificate Information: 9455 W EDEN DR 90210
- Application / Permit
- 19014-30000-00787
- Plan Check / Job No.
- B19WL00844
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition of 2nd floor to (e) 1-story SFD and interior alteration.
- Permit Issued
- Issued on 7/19/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/15/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/21/2019 | MANUEL GARCIA |
| Corrections Issued | 2/26/2019 | MANUEL GARCIA |
| Building Plans Picked Up | 2/28/2019 | APPLICANT |
| Plan Check Approved | 7/2/2019 | ALFREDO JARA |
| No Progress | 7/2/2019 | ALFREDO JARA |
| Plan Check Approved | 7/2/2019 | ALFREDO JARA |
| Issued | 7/19/2019 | LADBS |
| CofO in Progress | 9/10/2022 | RAUL BARAJAS |
| No Progress | 4/1/2023 | MICHAEL PELHAM |
| CofO in Progress | 4/13/2023 | RAUL BARAJAS |
| Permit Finaled | 4/15/2023 | DANIEL ORRANTE |
| CofO Issued | 4/15/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/15/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 6/14/2019 | ALYCIA WITZLING |
| Eng Process Fee Ord 176,300 | Cleared | 7/2/2019 | KRISTEN LY |
| Grading Pre-Inspection | Cleared | 7/2/2019 | MANUEL GARCIA |
| Roof/Waste drainage to street | Cleared | 7/2/2019 | KRISTEN LY |
| Sewer availability | Cleared | 7/2/2019 | KRISTEN LY |
| ZA Case | Cleared | 7/2/2019 | NOAH MCCOY |
| ZA Case | Cleared | 7/2/2019 | NOAH MCCOY |
Contact Information
| Contractor | Aram G Construction Inc; Lic. No.: 961066-B | 441 E SAN JOSE AVENUE #301 BURBANK, CA 91501 |
| Engineer | Song,, Zhenyu Michael; Lic. No.: S5266 | 12540 DESTINO ST CERRITOS, CA 90703 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/22/2019 | Partial Inspection | RICHARD STEINBACH |
| Special/Order Compliance | 5/1/2020 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 6/11/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Wood Frame | 6/11/2020 | Corrections Issued | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2020 | Corrections Issued | RAUL BARAJAS |
| Interior/Exterior Lathing | 6/24/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Deputy Wood Construction | 6/25/2020 | No Access for Inspection | ELMER BLAND |
| BUILDING-Rough-Frame | 6/26/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Rough | 6/26/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Interior/Exterior Lathing | 6/26/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Interior/Exterior Lathing | 8/25/2020 | Partial Approval | RAUL BARAJAS |
| ELECTRICAL-Rough | 9/30/2020 | Approved | RAUL BARAJAS |
| HVAC-Rough | 9/30/2020 | Corrections Issued | RAUL BARAJAS |
| Interior/Exterior Lathing | 9/30/2020 | Approved | RAUL BARAJAS |
| Shower Pan | 9/30/2020 | Approved | RAUL BARAJAS |
| Pre-Inspection | 11/6/2020 | Corrections Issued | RAUL BARAJAS |
| HVAC-Rough | 2/25/2021 | Partial Approval | RAUL BARAJAS |
| Pre-Inspection | 2/25/2021 | Corrections Issued | RAUL BARAJAS |
| PLUMBING-Rough | 3/11/2021 | Corrections Issued | RAUL BARAJAS |
| PLUMBING-Rough | 4/1/2021 | Partial Approval | RAUL BARAJAS |
| BUILDING-Rough-Frame | 4/8/2021 | Not Ready for Inspection | RAUL BARAJAS |
| ELECTRICAL-Rough | 4/8/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Rough | 4/8/2021 | Approved | RAUL BARAJAS |
| ELECTRICAL-Rough | 4/27/2021 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 5/7/2021 | Approved | RAUL BARAJAS |
| Insulation | 5/20/2021 | Approved | RAUL BARAJAS |
| Drywall Nailing | 6/14/2021 | Approved | WILLIAM WREN |
| Footing/Foundation/Slab | 6/25/2021 | Approved | RAUL BARAJAS |
| Masonry Wall/Backfill | 8/5/2021 | Partial Inspection | RICHARD STEINBACH |
| Underground Mechanical | 8/26/2021 | Approved | RAUL BARAJAS |
| Underground Mechanical | 12/1/2021 | Approved | RAUL BARAJAS |
| ELECTRICAL-Final | 12/29/2021 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Final | 12/29/2021 | Partial Inspection | RAUL BARAJAS |
| Service/Power Release | 12/29/2021 | Partial Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 1/6/2022 | Approved | RAUL BARAJAS |
| Final | 1/6/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Gas Test | 1/6/2022 | Approved | RAUL BARAJAS |
| Green Building Final | 1/6/2022 | Not Ready for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 1/6/2022 | SGSOV Approved | RAUL BARAJAS |
| Smoke Detectors | 1/6/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Gas Test | 1/10/2022 | Approved | RAUL BARAJAS |
| ELECTRICAL-Final | 8/10/2022 | Approved | RYAN SALAZAR |
| HVAC-Final | 8/10/2022 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 8/10/2022 | Approved | RYAN SALAZAR |
| Green Building Final | 8/15/2022 | Approved | RAUL BARAJAS |
| Final | 9/9/2022 | OK to Issue CofO | RAUL BARAJAS |
| Smoke Detectors | 9/9/2022 | Approved | RAUL BARAJAS |