9455 W EDEN DR 90210

Certificate Information: 9455 W EDEN DR 90210

Application / Permit
19014-30000-00787
Plan Check / Job No.
B19WL00844
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition of 2nd floor to (e) 1-story SFD and interior alteration.
Permit Issued
Issued on 7/19/2019
Issuing Office
Valley
Current Status
CofO Issued on 4/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/15/2019 APPLICANT
Assigned to Plan Check Engineer 2/21/2019 MANUEL GARCIA
Corrections Issued 2/26/2019 MANUEL GARCIA
Building Plans Picked Up 2/28/2019 APPLICANT
Plan Check Approved 7/2/2019 ALFREDO JARA
No Progress 7/2/2019 ALFREDO JARA
Plan Check Approved 7/2/2019 ALFREDO JARA
Issued 7/19/2019 LADBS
CofO in Progress 9/10/2022 RAUL BARAJAS
No Progress 4/1/2023 MICHAEL PELHAM
CofO in Progress 4/13/2023 RAUL BARAJAS
Permit Finaled 4/15/2023 DANIEL ORRANTE
CofO Issued 4/15/2023 DANIEL ORRANTE
Permit Finaled 4/15/2023 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 6/14/2019 ALYCIA WITZLING
Eng Process Fee Ord 176,300 Cleared 7/2/2019 KRISTEN LY
Grading Pre-Inspection Cleared 7/2/2019 MANUEL GARCIA
Roof/Waste drainage to street Cleared 7/2/2019 KRISTEN LY
Sewer availability Cleared 7/2/2019 KRISTEN LY
ZA Case Cleared 7/2/2019 NOAH MCCOY
ZA Case Cleared 7/2/2019 NOAH MCCOY

Contact Information

Contractor Aram G Construction Inc; Lic. No.: 961066-B 441 E SAN JOSE AVENUE #301      BURBANK, CA 91501
Engineer Song,, Zhenyu Michael; Lic. No.: S5266 12540 DESTINO ST      CERRITOS, CA 90703

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/22/2019 Partial Inspection RICHARD STEINBACH
Special/Order Compliance 5/1/2020 Corrections Issued CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 6/11/2020 Not Ready for Inspection ENRIQUE MIRELES
Wood Frame 6/11/2020 Corrections Issued ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 6/24/2020 Corrections Issued RAUL BARAJAS
Interior/Exterior Lathing 6/24/2020 Not Ready for Inspection RAUL BARAJAS
Deputy Wood Construction 6/25/2020 No Access for Inspection ELMER BLAND
BUILDING-Rough-Frame 6/26/2020 Not Ready for Inspection RAUL BARAJAS
Green Building Rough 6/26/2020 Not Ready for Inspection RAUL BARAJAS
Interior/Exterior Lathing 6/26/2020 Not Ready for Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 7/8/2020 Not Ready for Inspection RAUL BARAJAS
Interior/Exterior Lathing 8/25/2020 Partial Approval RAUL BARAJAS
ELECTRICAL-Rough 9/30/2020 Approved RAUL BARAJAS
HVAC-Rough 9/30/2020 Corrections Issued RAUL BARAJAS
Interior/Exterior Lathing 9/30/2020 Approved RAUL BARAJAS
Shower Pan 9/30/2020 Approved RAUL BARAJAS
Pre-Inspection 11/6/2020 Corrections Issued RAUL BARAJAS
HVAC-Rough 2/25/2021 Partial Approval RAUL BARAJAS
Pre-Inspection 2/25/2021 Corrections Issued RAUL BARAJAS
PLUMBING-Rough 3/11/2021 Corrections Issued RAUL BARAJAS
PLUMBING-Rough 4/1/2021 Partial Approval RAUL BARAJAS
BUILDING-Rough-Frame 4/8/2021 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Rough 4/8/2021 Not Ready for Inspection RAUL BARAJAS
Green Building Rough 4/8/2021 Approved RAUL BARAJAS
ELECTRICAL-Rough 4/27/2021 Approved RAUL BARAJAS
Interior/Exterior Lathing 5/7/2021 Approved RAUL BARAJAS
Insulation 5/20/2021 Approved RAUL BARAJAS
Drywall Nailing 6/14/2021 Approved WILLIAM WREN
Footing/Foundation/Slab 6/25/2021 Approved RAUL BARAJAS
Masonry Wall/Backfill 8/5/2021 Partial Inspection RICHARD STEINBACH
Underground Mechanical 8/26/2021 Approved RAUL BARAJAS
Underground Mechanical 12/1/2021 Approved RAUL BARAJAS
ELECTRICAL-Final 12/29/2021 Partial Approval RAUL BARAJAS
PLUMBING-Final 12/29/2021 Partial Inspection RAUL BARAJAS
Service/Power Release 12/29/2021 Partial Inspection RAUL BARAJAS
BUILDING-Rough-Frame 1/6/2022 Approved RAUL BARAJAS
Final 1/6/2022 Not Ready for Inspection RAUL BARAJAS
Gas Test 1/6/2022 Approved RAUL BARAJAS
Green Building Final 1/6/2022 Not Ready for Inspection RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 1/6/2022 SGSOV Approved RAUL BARAJAS
Smoke Detectors 1/6/2022 Not Ready for Inspection RAUL BARAJAS
Gas Test 1/10/2022 Approved RAUL BARAJAS
ELECTRICAL-Final 8/10/2022 Approved RYAN SALAZAR
HVAC-Final 8/10/2022 Approved RYAN SALAZAR
PLUMBING-Final 8/10/2022 Approved RYAN SALAZAR
Green Building Final 8/15/2022 Approved RAUL BARAJAS
Final 9/9/2022 OK to Issue CofO RAUL BARAJAS
Smoke Detectors 9/9/2022 Approved RAUL BARAJAS