10319-10321 W SALA PL 91352

Certificate Information: 10319-10321 W SALA PL 91352

Application / Permit
19014-30000-00632
Plan Check / Job No.
B19WL00653
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Addition to (E) SFD for a (N) 2-story ADU per AB 494 & SB 229. Remodel 2- story SFD to convert portion of attached garage to laundry room for the ADU with (N) roof deck above garage.
Permit Issued
Issued on 6/9/2020
Issuing Office
Current Status
CofO Issued on 2/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/7/2019 APPLICANT
Assigned to Plan Check Engineer 2/28/2019 JAHANSHAH POURHASSAN
Corrections Issued 3/8/2019 JAHANSHAH POURHASSAN
Quality Review Completed 3/14/2019 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 4/11/2019 APPLICANT
Green Plans Picked Up 4/11/2019 APPLICANT
Applicant returned to address corrections 7/12/2019 JAHANSHAH POURHASSAN
Applicant returned to address corrections 7/19/2019 JAHANSHAH POURHASSAN
Plan Check Approved 9/16/2019 JAHANSHAH POURHASSAN
Issued 6/9/2020 APPLICANT
CofO in Progress 12/2/2021 WILLIAM KUEHN
Permit Finaled 2/17/2022 MICHAEL SMITH
CofO Issued 2/17/2022 MICHAEL SMITH
Permit Finaled 2/17/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/18/2019 ISRAEL TAMIRU
BHO/Hillside ordinance Cleared 4/18/2019 ISRAEL TAMIRU
Permit Cleared 4/18/2019 ISRAEL TAMIRU
Hydrant and Access approval Cleared 6/18/2019 ROBERT DUFF
BHO/Hillside ordinance Cleared 6/19/2019 APEKSHYA BAJRACHARYA
BHO/Hillside ordinance Cleared 6/19/2019 APEKSHYA BAJRACHARYA
Low Impact Development Cleared 6/24/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 6/24/2019 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 7/2/2019 JOHN LIN
Sewer availability Cleared 7/2/2019 JOHN LIN
Green Code Cleared 7/17/2019 RICHARD GARCIA
GPI Written Notices Cleared 9/5/2019 JAHANSHAH POURHASSAN
Grading Pre-Inspection Cleared 9/5/2019 JAHANSHAH POURHASSAN
Trees in Parkway Cleared 9/6/2019 JOHN KIM
Hold Cleared 6/30/2020 JASON SHEETS

Contact Information

Contractor Owner-Builder       ,
Engineer Manoukian,, Krikor Kerop; Lic. No.: C87010 5649 VANTAGE AVE      VALLEY VILLAGE, CA 91607

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/16/2020 Partial Approval BEAU COLLINS
PLUMBING-Rough 11/19/2020 Partial Approval BEAU COLLINS
Deputy Drilled-In Anchors 12/2/2020 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 12/4/2020 Approved BEAU COLLINS
Deputy Reinf. Concrete 12/8/2020 Conditional Approval BEAU COLLINS
Floor/Roof Diaphrgm/Shear Wall 12/24/2020 Partial Approval BEAU COLLINS
Floor/Roof Diaphrgm/Shear Wall 1/21/2021 Corrections Issued BEAU COLLINS
BUILDING-Rough-Frame 2/24/2021 Corrections Issued BEAU COLLINS
ELECTRICAL-Rough 2/24/2021 Partial Approval BEAU COLLINS
Floor/Roof Diaphrgm/Shear Wall 2/24/2021 Partial Approval BEAU COLLINS
HVAC-Rough 2/24/2021 Corrections Issued BEAU COLLINS
PLUMBING-Rough 2/24/2021 Partial Approval BEAU COLLINS
BUILDING-Rough-Frame 3/3/2021 Not Ready for Inspection BEAU COLLINS
ELECTRICAL-Rough 3/3/2021 Not Ready for Inspection BEAU COLLINS
Green Building Rough 3/3/2021 Not Ready for Inspection BEAU COLLINS
HVAC-Rough 3/3/2021 Not Ready for Inspection BEAU COLLINS
Shower Pan 3/3/2021 Approved BEAU COLLINS
HVAC-Rough 3/10/2021 Approved BEAU COLLINS
Deputy Wood Construction 3/15/2021 Conditional Approval BEAU COLLINS
Wood Frame 3/18/2021 Approved BEAU COLLINS
BUILDING-Rough-Frame 3/26/2021 Approved BEAU COLLINS
Green Building Rough 3/26/2021 Approved BEAU COLLINS
Insulation 3/26/2021 Approved BEAU COLLINS
Interior/Exterior Lathing 3/26/2021 Partial Approval BEAU COLLINS
Rough-Elec/Plmb/HVAC 3/26/2021 Approved BEAU COLLINS
Drywall Nailing 4/1/2021 Approved MATTHEW NELSON
Green Building Rough 4/1/2021 Approved MATTHEW NELSON
Interior/Exterior Lathing 4/1/2021 Approved MATTHEW NELSON
Special/Order Compliance 4/1/2021 Not Ready for Inspection MATTHEW NELSON
Special/Order Compliance 4/8/2021 Approved BEAU COLLINS
PLUMBING-Rough 6/11/2021 Approved MATTHEW NELSON
Final 11/1/2021 Corrections Issued MATTHEW NELSON
Green Building Final 11/1/2021 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 11/1/2021 SGSOV Not Ready MATTHEW NELSON
Smoke Detectors 11/1/2021 Not Ready for Inspection MATTHEW NELSON
Final 11/23/2021 Corrections Issued WILLIAM KUEHN
SGSOV-Seismic Gas S/O Valve 11/23/2021 SGSOV Approved WILLIAM KUEHN
Smoke Detectors 11/23/2021 Approved WILLIAM KUEHN
Final 12/1/2021 OK to Issue CofO WILLIAM KUEHN