1017 N ENCHANTED WAY 90272

Certificate Information: 1017 N ENCHANTED WAY 90272

Application / Permit
19014-30000-00480
Plan Check / Job No.
B19WL00471
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
GROUND FLOOR ADDITION & MAJOR REMODEL TO (E) SFD
Permit Issued
Issued on 7/30/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/8/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/29/2019 APPLICANT
Assigned to Plan Check Engineer 2/13/2019 TARIK SAOUD
Corrections Issued 2/19/2019 TARIK SAOUD
Quality Review Completed 2/28/2019 KAMRAN GHOTBI RAVANDI
Plan Check Approved 7/18/2019 TARIK SAOUD
Issued 7/30/2019 LADBS
Building Plans Picked Up 7/20/2020 APPLICANT
Green Plans Picked Up 7/30/2020 APPLICANT
CofO in Progress 5/19/2021 ANDREW NAVE
Permit Finaled 6/8/2021 KENNETH NAGLE
CofO Issued 6/8/2021 KENNETH NAGLE
Permit Finaled 6/8/2021 KENNETH NAGLE

Permit Application Clearance Information

Low Impact Development Cleared 7/1/2019 JORGE MEJIA LEMUS
Coastal Zone Cleared 7/9/2019 TREVOR MARTIN
Green Code Cleared 7/10/2019 RICHARD GARCIA
Eng Process Fee Ord 176,300 Cleared 7/12/2019 JENNY CEA
Roof/Waste drainage to street Cleared 7/12/2019 JENNY CEA
Grading Pre-Inspection Cleared 7/18/2019 TARIK SAOUD

Contact Information

Architect Borghei,, Mo; Lic. No.: C17777 12249 DOROTHY STREET      LOS ANGELES, CA 90049
Contractor Owner-Builder       ,
Engineer Pirbadian,, Amir; Lic. No.: C72413 5435 BALBOA BLVD 214      ENCINO, CA 91342

Inspector Information

DANIEL VERA, (213) 577-9924 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/2/2019 Partial Inspection DAVID FEILER
Deputy Drilled-In Anchors 12/19/2019 Conditional Approval MICHAEL TEMPLE
Excavation/Setback/Form/Re-Bar 12/20/2019 Corrections Issued ANDREW NAVE
PLUMBING-Rough 12/20/2019 Approved ANDREW NAVE
Footing/Foundation/Slab 12/30/2019 Approved ANDREW NAVE
Deputy Steel/Welding 1/21/2020 Conditional Approval MICHAEL TEMPLE
Floor/Roof Diaphrgm/Shear Wall 2/13/2020 Partial Approval ANDREW NAVE
PLUMBING-Rough 2/19/2020 Approved MICHAEL TEMPLE
ELECTRICAL-Rough 5/1/2020 Approved ANDREW NAVE
Green Building Rough 5/1/2020 Not Ready for Inspection ANDREW NAVE
BUILDING-Rough-Frame 5/4/2020 Partial Inspection ANDREW NAVE
HVAC-Rough 5/4/2020 Approved ANDREW NAVE
Verify Sprinkler Sign Off 5/4/2020 Approved ANDREW NAVE
Green Building Rough 7/21/2020 Partial Inspection ANDREW NAVE
Green Building Rough 8/18/2020 Approved ANDREW NAVE
Insulation 8/18/2020 Approved ANDREW NAVE
Interior/Exterior Lathing 8/18/2020 Partial Approval ANDREW NAVE
Drywall Nailing 9/3/2020 Approved ANDREW NAVE
Interior/Exterior Lathing 9/3/2020 Partial Approval ANDREW NAVE
Interior/Exterior Lathing 9/18/2020 Approved ANDREW NAVE
Deputy Reinf. Concrete 12/3/2020 Conditional Approval ANDREW NAVE
ELECTRICAL-Final 4/1/2021 Corrections Issued ANDREW NAVE
HVAC-Final 4/1/2021 Corrections Issued ANDREW NAVE
ELECTRICAL-Final 4/12/2021 Approved ANDREW NAVE
HVAC-Final 4/12/2021 Corrections Issued ANDREW NAVE
PLUMBING-Final 4/12/2021 Corrections Issued ANDREW NAVE
BUILDING-Rough-Frame 4/19/2021 Approved ANDREW NAVE
Green Building Final 4/19/2021 Approved ANDREW NAVE
HVAC-Final 4/19/2021 Approved ANDREW NAVE
PLUMBING-Final 4/19/2021 Approved ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 4/19/2021 SGSOV Approved ANDREW NAVE
Smoke Detectors 4/19/2021 Approved ANDREW NAVE
Final 4/23/2021 Corrections Issued ANDREW NAVE
Final 5/19/2021 OK to Issue CofO ANDREW NAVE