1505 N VIEWSITE TER 90069

Certificate Information: 1505 N VIEWSITE TER 90069

Application / Permit
19014-30000-00407
Plan Check / Job No.
B19WL00412
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL AND 2ND FLOOR ADDITION TO EXISTING 1-STORY TYPE VB SINGLE FAMILY DWELLING WITH ATTACHED GARAGE, EQUIPPED THROUGHOUT WITH NFPA 13D FIRE SPRINKLERS.
Permit Issued
Issued on 6/26/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/12/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/25/2019 APPLICANT
Assigned to Plan Check Engineer 2/7/2019 SERGIO SILVA
Green Plans Picked Up 2/13/2019 APPLICANT
Corrections Issued 2/14/2019 SERGIO SILVA
Quality Review Completed 2/22/2019 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 2/22/2019 APPLICANT
Applicant returned to address corrections 3/14/2019 SERGIO SILVA
Applicant returned to address corrections 3/20/2019 SERGIO SILVA
Plan Check Approved 6/21/2019 SERGIO SILVA
Issued 6/26/2019 LADBS
CofO in Progress 4/23/2022 RAUL BARAJAS
CofO in Progress 4/23/2022 RAUL BARAJAS
Permit Finaled 5/12/2022 DEROLD HAUFF
CofO Issued 5/12/2022 DEROLD HAUFF
Permit Finaled 5/12/2022 DEROLD HAUFF

Permit Application Clearance Information

CPC Cleared 3/4/2019 SARAH GOLDMAN
Distance to fire station Cleared 3/4/2019 ROBERT DUFF
Hydrant and Access approval Cleared 3/4/2019 ROBERT DUFF
Permit Cleared 3/4/2019 ELENA LOPEZ
ZA Case Cleared 3/4/2019 SARAH GOLDMAN
ZA Case Cleared 3/4/2019 SARAH GOLDMAN
ZA Case Cleared 3/4/2019 SARAH GOLDMAN
ZA Case Cleared 3/4/2019 SARAH GOLDMAN
ZA Case Cleared 3/4/2019 SARAH GOLDMAN
BHO/Hillside ordinance Cleared 3/5/2019 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 3/5/2019 ADRIAN SANCHEZ
Sewer availability Cleared 3/5/2019 ADRIAN SANCHEZ
Trees in Parkway Cleared 3/5/2019 JOHN KIM
Green Code Cleared 3/12/2019 RICHARD GARCIA
GPI Written Notices Cleared 3/20/2019 SERGIO SILVA
Grading Pre-Inspection Cleared 3/20/2019 SERGIO SILVA
Low Impact Development Cleared 3/28/2019 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 3/28/2019 ELAINE LEI
Private street Cleared 6/12/2019 GRACIELA ACOSTA
BHO/Hillside ordinance Cleared 6/21/2019 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 6/21/2019 ADRIAN SANCHEZ
Miscellaneous Cleared 6/21/2019 SERGIO SILVA

Contact Information

Contractor Asterisk* Inc; Lic. No.: 647295-B 3353 CAHUENGA BLVD WEST   UNIT B    LOS ANGELES, CA 90068
Engineer Cai,, Luo B; Lic. No.: C80352 9428 ETAON AVE M      CHATSWORTH, CA 91311
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620
Engineer Nazari,, Arthur; Lic. No.: C53497 PO BOX 7112      NORTHRIDGE, CA 91327
Engineer Obando,, Gaspar Eduardo; Lic. No.: C71382 1453 14TH ST STE A      SANTA MONICA, CA 90404
Geologist Tsao,, Tze-Tzong; Lic. No.: EG1783 9428 ETON AVENUE #M      CHATSWORTH, CA 91311

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 10/4/2019 Partial Approval RICHARD STEINBACH
Deputy Other (see comments) 10/16/2019 Conditional Approval RICHARD STEINBACH
Excavation/Setback/Form/Re-Bar 11/12/2019 Partial Approval RICHARD STEINBACH
Piling/Pier/Caisson 11/12/2019 Partial Approval RICHARD STEINBACH
Deputy Drilled-In Anchors 1/10/2020 Conditional Approval RICHARD STEINBACH
Excavation/Setback/Form/Re-Bar 1/21/2020 Partial Approval RICHARD STEINBACH
Deputy Reinf. Concrete 1/24/2020 Conditional Approval RICHARD STEINBACH
Sewer 3/17/2020 No Access for Inspection RICHARD STEINBACH
HVAC-Rough 3/19/2020 Partial Approval RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 4/16/2020 Partial Approval RAUL BARAJAS
Deputy Steel/Welding 5/18/2020 Conditional Approval RAUL BARAJAS
BUILDING-Rough-Frame 7/9/2020 Partial Approval RAUL BARAJAS
Green Building Rough 7/9/2020 Not Ready for Inspection RAUL BARAJAS
Verify Sprinkler Sign Off 7/9/2020 Not Ready for Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 8/14/2020 Partial Approval RAUL BARAJAS
Green Building Rough 8/14/2020 Not Ready for Inspection RAUL BARAJAS
Verify Sprinkler Sign Off 8/14/2020 Not Ready for Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 10/16/2020 Corrections Issued RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 10/27/2020 No Access for Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 10/30/2020 Approved RAUL BARAJAS
HVAC-Rough 11/12/2020 Partial Approval JOSEPH MCGARRY
PLUMBING-Rough 11/12/2020 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 3/10/2021 Approved RAUL BARAJAS
Shower Pan 3/16/2021 Approved RAUL BARAJAS
BUILDING-Rough-Frame 3/19/2021 Conditional Approval CHRIS CHRISTENSEN
Insulation 3/19/2021 Conditional Approval CHRIS CHRISTENSEN
Interior/Exterior Lathing 3/25/2021 Partial Approval RAUL BARAJAS
Drywall Nailing 4/23/2021 Partial Inspection RAUL BARAJAS
Green Building Rough 4/23/2021 Approved RAUL BARAJAS
Interior/Exterior Lathing 4/30/2021 Approved RAUL BARAJAS
Drywall Nailing 5/28/2021 Partial Approval THOMAS LOGRASSO
Drywall Nailing 6/3/2021 Approved RAUL BARAJAS
Interior/Exterior Lathing 6/25/2021 Approved RAUL BARAJAS
Underground Mechanical 8/23/2021 Partial Approval RICHARD STEINBACH
Special/Order Compliance 9/3/2021 Partial Inspection RAUL BARAJAS
Special/Order Compliance 10/21/2021 Approved HECTOR ALIKHAN
Special/Order Compliance 11/3/2021 Approved AMY COLIN
Excavation/Setback/Form/Re-Bar 11/30/2021 Approved ARTHUR SARGSYAN
PLUMBING-Final 12/16/2021 Approved RAUL BARAJAS
ELECTRICAL-Final 12/20/2021 Corrections Issued RAUL BARAJAS
ELECTRICAL-Final 12/23/2021 Not Ready for Inspection RAUL BARAJAS
Gas Test 12/28/2021 Approved RAUL BARAJAS
Service/Power Release 12/28/2021 Corrections Issued RAUL BARAJAS
ELECTRICAL-Final 1/6/2022 Approved RAUL BARAJAS
BUILDING-Rough-Frame 1/26/2022 Approved RAUL BARAJAS
Final 1/26/2022 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 1/26/2022 Approved RAUL BARAJAS
Green Building Final 1/26/2022 Not Ready for Inspection RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 1/26/2022 SGSOV Approved RAUL BARAJAS
Smoke Detectors 1/26/2022 Approved RAUL BARAJAS
Verify Sprinkler Sign Off 1/26/2022 Approved RAUL BARAJAS
HVAC-Final 1/31/2022 Not Ready for Inspection RAUL BARAJAS
HVAC-Final 2/11/2022 Approved RAUL BARAJAS
Final 4/20/2022 OK to Issue CofO RAUL BARAJAS
Green Building Final 4/20/2022 Approved RAUL BARAJAS