7019 W 83RD ST 90045

Certificate Information: 7019 W 83RD ST 90045

Application / Permit
19014-30000-00209
Plan Check / Job No.
B19WL00229
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
2-story accessory dwelling unit (ADU) addition to (e) det. 2-car garage per AB 494 and SB 229.
Permit Issued
Issued on 2/24/2021
Issuing Office
West Los Angeles
Current Status
CofO Issued on 4/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/15/2019 APPLICANT
Green Plans Picked Up 1/30/2019 APPLICANT
Assigned to Plan Check Engineer 1/31/2019 REZA HAGHIGHAT
Corrections Issued 2/7/2019 REZA HAGHIGHAT
Quality Review Completed 2/14/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 11/26/2019 REZA HAGHIGHAT
Applicant returned to address corrections 1/8/2020 REZA HAGHIGHAT
Applicant returned to address corrections 6/29/2020 REZA HAGHIGHAT
Plan Check Approved 2/18/2021 REZA HAGHIGHAT
Issued 2/24/2021 APPLICANT
Building Plans Picked Up 2/25/2021 APPLICANT
Permit Finaled 4/29/2024 DANIEL ORRANTE
CofO Issued 4/29/2024 DANIEL ORRANTE
Permit Finaled 4/29/2024 DANIEL ORRANTE

Permit Application Clearance Information

Construction near power lines Cleared 2/20/2019 WALTER RAMIREZ
Miscellaneous Cleared 2/20/2019 NOAH MCCOY
ZA Case Cleared 2/20/2019 NOAH MCCOY
Address approval Cleared 10/24/2019 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 10/24/2019 ANTHONY MAINEZ
Sewer availability Cleared 10/24/2019 ANTHONY MAINEZ
Green Code Cleared 11/5/2019 RICHARD GARCIA
Roof/Waste drainage to street Cleared 12/17/2019 DINAH GARIN
Low Impact Development Cleared 9/23/2020 ROBIN YAMADA
Miscellaneous Cleared 2/8/2021 JENSON LEE

Contact Information

Contractor Owner-Builder       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 5/11/2022 Approved CLAYTON GRAHAM
Excavation/Setback/Form/Re-Bar 5/20/2022 Partial Approval BOBBY KEY
Footing/Foundation/Slab 5/20/2022 Partial Approval BOBBY KEY
Footing/Foundation/Slab 6/8/2022 Approved BOBBY KEY
BUILDING-Rough-Frame 7/14/2022 Corrections Issued JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 7/14/2022 Conditional Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 7/27/2022 Approved BOBBY KEY
Green Building Rough 7/27/2022 Not Ready for Inspection BOBBY KEY
Deputy Steel/Welding 8/2/2022 Conditional Approval BOBBY KEY
Interior/Exterior Lathing 8/31/2022 Partial Approval BOBBY KEY
HVAC-Rough 9/30/2022 Approved BOBBY KEY
PLUMBING-Rough 9/30/2022 Approved BOBBY KEY
BUILDING-Rough-Frame 10/4/2022 Approved BOBBY KEY
ELECTRICAL-Final 10/4/2022 Approved BOBBY KEY
Green Building Rough 10/4/2022 Approved BOBBY KEY
Interior/Exterior Lathing 10/12/2022 Approved BOBBY KEY
Insulation 10/17/2022 Approved BOBBY KEY
Drywall Nailing 11/14/2022 Partial Approval DAVID FEILER
Drywall Nailing 1/31/2023 Approved EVAN COOPER
ELECTRICAL-Final 5/8/2023 Corrections Issued BOBBY KEY
Final 5/8/2023 Corrections Issued BOBBY KEY
Green Building Final 5/8/2023 Approved BOBBY KEY
HVAC-Final 5/8/2023 Partial Approval BOBBY KEY
PLUMBING-Final 5/8/2023 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 5/8/2023 SGSOV Not Ready BOBBY KEY
Smoke Detectors 5/8/2023 Approved BOBBY KEY
Final 6/21/2023 Not Ready for Inspection BOBBY KEY
SGSOV-Seismic Gas S/O Valve 6/21/2023 SGSOV Approved BOBBY KEY
ELECTRICAL-Final 8/29/2023 Approved BOBBY KEY
HVAC-Final 8/29/2023 Approved BOBBY KEY
PLUMBING-Final 8/29/2023 Approved BOBBY KEY
Final 4/29/2024 Conditional Approval RICHARD STEINBACH