2693 N CARMAR DR 90046

Certificate Information: 2693 N CARMAR DR 90046

Application / Permit
19014-30000-00120
Plan Check / Job No.
B19WL00123
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
IRREGULAR SHAPE ADDITION TO (E) SFD TO ATTACH (E) REC ROOM & DET. GARAGE TO SFD AND CONVERT THE REC ROOM TO A NEW BEDROOM.
Permit Issued
Issued on 5/9/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 8/5/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/10/2019 APPLICANT
Assigned to Plan Check Engineer 1/24/2019 REZA HAGHIGHAT
Corrections Issued 1/28/2019 REZA HAGHIGHAT
Green Plans Picked Up 1/28/2019 APPLICANT
Quality Review Completed 2/8/2019 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 2/8/2019 APPLICANT
Applicant returned to address corrections 3/28/2019 REZA HAGHIGHAT
Applicant returned to address corrections 4/10/2019 REZA HAGHIGHAT
Plan Check Approved 5/8/2019 REZA HAGHIGHAT
Issued 5/9/2019 LADBS
CofO in Progress 6/17/2021 RAUL BARAJAS
Permit Finaled 8/5/2021 DEROLD HAUFF
CofO Issued 8/5/2021 DEROLD HAUFF
Permit Finaled 8/5/2021 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 1/25/2019 REZA HAGHIGHAT
Green Code Cleared 3/21/2019 DONALD CRICHLOW
ZA Case Cleared 3/26/2019 NOAH MCCOY
Eng Process Fee Ord 176,300 Cleared 3/27/2019 JAMES MORALEZ
Roof/Waste drainage to street Cleared 3/27/2019 JAMES MORALEZ
Sewer availability Cleared 3/27/2019 JAMES MORALEZ
Specific Plan Cleared 4/30/2019 DOMINICK ORTIZ
ZI Cleared 4/30/2019 DOMINICK ORTIZ

Contact Information

Contractor Owner-Builder       ,
Engineer Yaprak,, Taskin Tolga; Lic. No.: C72927 708 SOUTH REDONDO AVE      MANHATTAN BEACH, CA 90266

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/14/2019 Partial Inspection DANNY TOLENTINO
Underground Mechanical 5/14/2019 Partial Approval DANNY TOLENTINO
Excavation/Setback/Form/Re-Bar 6/21/2019 Partial Approval DANNY TOLENTINO
Deputy Drilled-In Anchors 8/29/2019 Conditional Approval RICHARD STEINBACH
Footing/Foundation/Slab 9/24/2019 Partial Approval ROBERT CORNELL
Pre-Inspection 9/24/2019 Partial Approval ROBERT CORNELL
Deputy Reinf. Concrete 9/27/2019 Conditional Approval RICHARD STEINBACH
Footing/Foundation/Slab 10/10/2019 Partial Approval RICHARD STEINBACH
PLUMBING-Rough 10/10/2019 Partial Approval RICHARD STEINBACH
Sewer 10/10/2019 Partial Approval RICHARD STEINBACH
Footing/Foundation/Slab 10/16/2019 Partial Approval RICHARD STEINBACH
Deputy Reinf. Concrete 10/17/2019 Conditional Approval RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 1/3/2020 Conditional Approval RICHARD STEINBACH
ELECTRICAL-Rough 2/11/2020 Approved RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 2/11/2020 Approved RICHARD STEINBACH
HVAC-Rough 2/11/2020 Approved RICHARD STEINBACH
PLUMBING-Rough 2/11/2020 Approved RICHARD STEINBACH
Rough-Elec/Plmb/HVAC 2/19/2020 Partial Approval RICHARD STEINBACH
Shower Pan 2/19/2020 Approved RICHARD STEINBACH
BUILDING-Rough-Frame 3/2/2020 Approved RICHARD STEINBACH
Green Building Rough 3/2/2020 Approved RICHARD STEINBACH
Interior/Exterior Lathing 3/2/2020 Approved RICHARD STEINBACH
Insulation 3/16/2020 Approved RICHARD STEINBACH
Drywall Nailing 3/24/2020 Approved RAUL BARAJAS
Pre-Inspection 3/24/2020 Not Ready for Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 6/5/2020 Not Ready for Inspection RAUL BARAJAS
Footing/Foundation/Slab 6/5/2020 Not Ready for Inspection RAUL BARAJAS
Pre-Inspection 6/5/2020 Not Ready for Inspection RAUL BARAJAS
Deputy Reinf. Concrete 7/24/2020 Conditional Approval CHRISTOPHER DELLEFIELD
Deputy Wood Construction 9/11/2020 No Access for Inspection ELMER BLAND
Final 4/14/2021 Corrections Issued JOSEPH MCGARRY
Footing/Foundation/Slab 4/14/2021 Approved JOSEPH MCGARRY
Green Building Final 4/14/2021 Approved JOSEPH MCGARRY
HVAC-Final 4/14/2021 Approved JOSEPH MCGARRY
PLUMBING-Final 4/14/2021 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 4/14/2021 SGSOV Approved JOSEPH MCGARRY
Smoke Detectors 4/14/2021 Approved JOSEPH MCGARRY
Structural Steel Frame 4/14/2021 Approved JOSEPH MCGARRY
Gas Test 4/20/2021 Approved RAUL BARAJAS
Final 5/3/2021 Not Ready for Inspection RAUL BARAJAS
Final 5/4/2021 Not Ready for Inspection RAUL BARAJAS
ELECTRICAL-Final 6/17/2021 Approved RAUL BARAJAS
Final 6/17/2021 OK to Issue CofO RAUL BARAJAS
Grading Pre-Inspection 6/17/2021 Approved RAUL BARAJAS