819 E PALMS BLVD 90291

Certificate Information: 819 E PALMS BLVD 90291

Application / Permit
19014-30000-00094
Plan Check / Job No.
B19WL00081
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Interior remodel and 1st and 2nd story additon to (e) 1-story sfd with addition of a rec. room to the rear side of bldg.
Permit Issued
Issued on 2/18/2020
Issuing Office
Valley
Current Status
CofO Issued on 3/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/8/2019 APPLICANT
Assigned to Plan Check Engineer 1/31/2019 REZA HAGHIGHAT
Corrections Issued 2/7/2019 REZA HAGHIGHAT
Quality Review Completed 2/14/2019 KAMRAN GHOTBI RAVANDI
Green Plans Picked Up 2/14/2019 APPLICANT
Building Plans Picked Up 3/1/2019 APPLICANT
Applicant returned to address corrections 4/8/2019 REZA HAGHIGHAT
Applicant returned to address corrections 5/1/2019 REZA HAGHIGHAT
Plan Check Approved 12/5/2019 REZA HAGHIGHAT
Issued 2/18/2020 LADBS
CofO in Progress 3/2/2023 RICHARD STEINBACH
Permit Finaled 3/4/2023 DANIEL ORRANTE
CofO Issued 3/4/2023 DANIEL ORRANTE
Permit Finaled 3/4/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/21/2019 KARAN PATEL
Eng Process Fee Ord 176,300 Cleared 3/21/2019 KARAN PATEL
Roof/Waste drainage to street Cleared 3/21/2019 KARAN PATEL
Sewer availability Cleared 3/21/2019 KARAN PATEL
Miscellaneous Cleared 4/8/2019 SARAH GOLDMAN
Miscellaneous Cleared 4/8/2019 SARAH GOLDMAN
Coastal Zone Cleared 5/3/2019 SHEILA GERSHON
Specific Plan Cleared 5/3/2019 SHEILA GERSHON
ZI Cleared 5/3/2019 SHEILA GERSHON
Low Impact Development Cleared 6/17/2019 JORGE MEJIA LEMUS
Green Code Cleared 6/18/2019 RICHARD GARCIA

Contact Information

Architect Gallagher,, Andrew J; Lic. No.: C26962 6926 PEAR TREE DRIVE      CARLSBAD, CA 92011
Contractor Klein Construction; Lic. No.: 891079-B 13858 CHANDLER BLVD      SHERMAN OAKS, CA 91401

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/4/2020 Partial Approval DAVID HEINE
Deputy Drilled-In Anchors 3/5/2020 Partial Approval DAVID HEINE
Footing/Foundation/Slab 3/6/2020 Partial Approval DAVID HEINE
BUILDING-Rough-Frame 3/27/2020 Partial Approval DAVID HEINE
Green Building Rough 3/27/2020 Not Ready for Inspection DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 4/13/2020 Partial Approval DAVID HEINE
Deputy Wood Construction 5/6/2020 Approved DAVID HEINE
ELECTRICAL-Rough 5/6/2020 Approved DAVID HEINE
PLUMBING-Rough 5/6/2020 Approved DAVID HEINE
BUILDING-Rough-Frame 5/7/2020 Partial Approval DAVID HEINE
Green Building Rough 5/7/2020 Not Ready for Inspection DAVID HEINE
Interior/Exterior Lathing 5/26/2020 Partial Approval DAVID HEINE
Shower Pan 5/26/2020 Approved DAVID HEINE
HVAC-Rough 5/27/2020 Approved DAVID HEINE
BUILDING-Rough-Frame 6/2/2020 Approved DAVID HEINE
Green Building Rough 6/2/2020 Approved DAVID HEINE
Insulation 6/4/2020 Approved DAVID HEINE
Interior/Exterior Lathing 6/4/2020 Approved DAVID HEINE
Drywall Nailing 6/24/2020 Approved DAVID HEINE
Final 11/5/2020 Corrections Issued DAVID HEINE
Footing/Foundation/Slab 11/5/2020 Approved DAVID HEINE
Green Building Final 11/5/2020 Approved DAVID HEINE
SGSOV-Seismic Gas S/O Valve 11/5/2020 SGSOV Not Ready DAVID HEINE
Smoke Detectors 11/5/2020 Approved DAVID HEINE
ELECTRICAL-Final 3/2/2023 Approved RICHARD STEINBACH
Final 3/2/2023 OK to Issue CofO RICHARD STEINBACH
HVAC-Final 3/2/2023 Approved RICHARD STEINBACH
PLUMBING-Final 3/2/2023 Approved RICHARD STEINBACH
SGSOV-Seismic Gas S/O Valve 3/2/2023 SGSOV Approved RICHARD STEINBACH