819 E PALMS BLVD 90291
Certificate Information: 819 E PALMS BLVD 90291
- Application / Permit
- 19014-30000-00094
- Plan Check / Job No.
- B19WL00081
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior remodel and 1st and 2nd story additon to (e) 1-story sfd with addition of a rec. room to the rear side of bldg.
- Permit Issued
- Issued on 2/18/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/8/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/31/2019 | REZA HAGHIGHAT |
| Corrections Issued | 2/7/2019 | REZA HAGHIGHAT |
| Quality Review Completed | 2/14/2019 | KAMRAN GHOTBI RAVANDI |
| Green Plans Picked Up | 2/14/2019 | APPLICANT |
| Building Plans Picked Up | 3/1/2019 | APPLICANT |
| Applicant returned to address corrections | 4/8/2019 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 5/1/2019 | REZA HAGHIGHAT |
| Plan Check Approved | 12/5/2019 | REZA HAGHIGHAT |
| Issued | 2/18/2020 | LADBS |
| CofO in Progress | 3/2/2023 | RICHARD STEINBACH |
| Permit Finaled | 3/4/2023 | DANIEL ORRANTE |
| CofO Issued | 3/4/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/4/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 3/21/2019 | KARAN PATEL |
| Eng Process Fee Ord 176,300 | Cleared | 3/21/2019 | KARAN PATEL |
| Roof/Waste drainage to street | Cleared | 3/21/2019 | KARAN PATEL |
| Sewer availability | Cleared | 3/21/2019 | KARAN PATEL |
| Miscellaneous | Cleared | 4/8/2019 | SARAH GOLDMAN |
| Miscellaneous | Cleared | 4/8/2019 | SARAH GOLDMAN |
| Coastal Zone | Cleared | 5/3/2019 | SHEILA GERSHON |
| Specific Plan | Cleared | 5/3/2019 | SHEILA GERSHON |
| ZI | Cleared | 5/3/2019 | SHEILA GERSHON |
| Low Impact Development | Cleared | 6/17/2019 | JORGE MEJIA LEMUS |
| Green Code | Cleared | 6/18/2019 | RICHARD GARCIA |
Contact Information
| Architect | Gallagher,, Andrew J; Lic. No.: C26962 | 6926 PEAR TREE DRIVE CARLSBAD, CA 92011 |
| Contractor | Klein Construction; Lic. No.: 891079-B | 13858 CHANDLER BLVD SHERMAN OAKS, CA 91401 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/4/2020 | Partial Approval | DAVID HEINE |
| Deputy Drilled-In Anchors | 3/5/2020 | Partial Approval | DAVID HEINE |
| Footing/Foundation/Slab | 3/6/2020 | Partial Approval | DAVID HEINE |
| BUILDING-Rough-Frame | 3/27/2020 | Partial Approval | DAVID HEINE |
| Green Building Rough | 3/27/2020 | Not Ready for Inspection | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 4/13/2020 | Partial Approval | DAVID HEINE |
| Deputy Wood Construction | 5/6/2020 | Approved | DAVID HEINE |
| ELECTRICAL-Rough | 5/6/2020 | Approved | DAVID HEINE |
| PLUMBING-Rough | 5/6/2020 | Approved | DAVID HEINE |
| BUILDING-Rough-Frame | 5/7/2020 | Partial Approval | DAVID HEINE |
| Green Building Rough | 5/7/2020 | Not Ready for Inspection | DAVID HEINE |
| Interior/Exterior Lathing | 5/26/2020 | Partial Approval | DAVID HEINE |
| Shower Pan | 5/26/2020 | Approved | DAVID HEINE |
| HVAC-Rough | 5/27/2020 | Approved | DAVID HEINE |
| BUILDING-Rough-Frame | 6/2/2020 | Approved | DAVID HEINE |
| Green Building Rough | 6/2/2020 | Approved | DAVID HEINE |
| Insulation | 6/4/2020 | Approved | DAVID HEINE |
| Interior/Exterior Lathing | 6/4/2020 | Approved | DAVID HEINE |
| Drywall Nailing | 6/24/2020 | Approved | DAVID HEINE |
| Final | 11/5/2020 | Corrections Issued | DAVID HEINE |
| Footing/Foundation/Slab | 11/5/2020 | Approved | DAVID HEINE |
| Green Building Final | 11/5/2020 | Approved | DAVID HEINE |
| SGSOV-Seismic Gas S/O Valve | 11/5/2020 | SGSOV Not Ready | DAVID HEINE |
| Smoke Detectors | 11/5/2020 | Approved | DAVID HEINE |
| ELECTRICAL-Final | 3/2/2023 | Approved | RICHARD STEINBACH |
| Final | 3/2/2023 | OK to Issue CofO | RICHARD STEINBACH |
| HVAC-Final | 3/2/2023 | Approved | RICHARD STEINBACH |
| PLUMBING-Final | 3/2/2023 | Approved | RICHARD STEINBACH |
| SGSOV-Seismic Gas S/O Valve | 3/2/2023 | SGSOV Approved | RICHARD STEINBACH |