130 N VISTA ST 90036

Certificate Information: 130 N VISTA ST 90036

Application / Permit
19014-30000-00076
Plan Check / Job No.
B19WL00061
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1ST FLOOR AND NEW 2ND FLOOR ADDITIONS TO (E) SINGLE FAMILY DWELLING.
Permit Issued
Issued on 1/13/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 2/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/7/2019 APPLICANT
Assigned to Plan Check Engineer 1/31/2019 ERWIN PASCUA
Green Plans Picked Up 2/4/2019 APPLICANT
Corrections Issued 2/12/2019 ERWIN PASCUA
Quality Review Completed 2/20/2019 MARJAN SHENASI
Building Plans Picked Up 2/25/2019 APPLICANT
Applicant returned to address corrections 3/6/2019 ERWIN PASCUA
Applicant returned to address corrections 12/27/2019 ERWIN PASCUA
Plan Check Approved 1/10/2020 ERWIN PASCUA
Issued 1/13/2020 LADBS
CofO in Progress 2/9/2021 CHRIS CHRISTENSEN
Permit Finaled 2/13/2021 DEROLD HAUFF
CofO Issued 2/13/2021 DEROLD HAUFF
Permit Finaled 2/13/2021 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/26/2019 JAMES MORALEZ
Hydrant and Access approval Cleared 11/26/2019 ROBERT DUFF
Sewer availability Cleared 11/26/2019 JAMES MORALEZ
HPOZ Cleared 12/2/2019 MICAELA TORRES-GIL
ZI Cleared 12/2/2019 MICAELA TORRES-GIL
Low Impact Development Cleared 12/9/2019 MITESH PATEL
Roof/Waste drainage to street Cleared 12/9/2019 ERIK BEASLEY
Green Code Cleared 12/17/2019 RICHARD GARCIA
CPC Cleared 12/27/2019 RICHARD REASER

Contact Information

Architect Feld,, Dovid Yitzchak; Lic. No.: C37588 921 S HOLT AVENUE      LOS ANGELES, CA 90035
Contractor Owner-Builder       ,
Engineer Vasquez,, Luis Fernando; Lic. No.: C56232 1551 RANDALL ST      GLENDALE, CA 91201

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/21/2020 Corrections Issued BRAD BESCOS
METHANE-Barrier 2/21/2020 Not Ready for Inspection BRAD BESCOS
METHANE-Subgrade 2/21/2020 Not Ready for Inspection BRAD BESCOS
BUILDING-Rough-Frame 3/11/2020 Partial Approval ARTHUR SARGSYAN
Green Building Rough 3/11/2020 Partial Inspection ARTHUR SARGSYAN
METHANE-Rough 3/11/2020 Approved ARTHUR SARGSYAN
Drywall Nailing 3/12/2020 Not Ready for Inspection ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 6/9/2020 Partial Approval CHRIS CHRISTENSEN
HVAC-Rough 6/9/2020 Corrections Issued CHRIS CHRISTENSEN
PLUMBING-Rough 6/9/2020 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 6/15/2020 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 6/17/2020 Approved CHRIS CHRISTENSEN
HVAC-Rough 6/17/2020 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 6/19/2020 Approved CHRIS CHRISTENSEN
Green Building Rough 6/19/2020 Not Ready for Inspection CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 6/26/2020 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 6/30/2020 Approved CHRIS CHRISTENSEN
Insulation 6/30/2020 Conditional Approval CHRIS CHRISTENSEN
Interior/Exterior Lathing 6/30/2020 Not Ready for Inspection THOMAS LOGRASSO
Drywall Nailing 7/8/2020 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 7/8/2020 Partial Approval THOMAS LOGRASSO
Shower Pan 7/14/2020 Corrections Issued THOMAS LOGRASSO
Interior/Exterior Lathing 7/17/2020 Approved THOMAS LOGRASSO
Shower Pan 7/17/2020 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 11/25/2020 SGSOV Not Ready CHRIS CHRISTENSEN
ELECTRICAL-Final 12/1/2020 Approved CHRIS CHRISTENSEN
Final 12/1/2020 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 12/1/2020 Approved CHRIS CHRISTENSEN
HVAC-Final 12/1/2020 Approved CHRIS CHRISTENSEN
PLUMBING-Final 12/1/2020 Approved CHRIS CHRISTENSEN
Pre-Inspection 12/1/2020 Approved CHRIS CHRISTENSEN
Final 12/10/2020 Not Ready for Inspection CHRIS CHRISTENSEN
Footing/Foundation/Slab 12/10/2020 Approved CHRIS CHRISTENSEN
METHANE-Barrier 12/10/2020 Approved CHRIS CHRISTENSEN
METHANE-Subgrade 12/10/2020 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 12/10/2020 SGSOV Not Required CHRIS CHRISTENSEN
Smoke Detectors 12/10/2020 Not Ready for Inspection CHRIS CHRISTENSEN
Final 2/8/2021 OK to Issue CofO CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 2/8/2021 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 2/8/2021 Approved CHRIS CHRISTENSEN