2801 S BARRY AVE 90064
Certificate Information: 2801 S BARRY AVE 90064
- Application / Permit
- 19014-30000-00073
- Plan Check / Job No.
- B19WL00057
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and interior remodel to (E) SFD .
- Permit Issued
- Issued on 3/15/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 3/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/7/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/17/2019 | ALFREDO JARA |
| Corrections Issued | 1/23/2019 | ALFREDO JARA |
| Green Plans Picked Up | 1/24/2019 | APPLICANT |
| Quality Review Completed | 2/1/2019 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 2/6/2019 | APPLICANT |
| Plan Check Approved | 3/13/2019 | ALFREDO JARA |
| Issued | 3/15/2019 | LADBS |
| CofO in Progress | 3/29/2025 | MICHAEL PELHAM |
| Permit Finaled | 3/29/2025 | RICHARD STEINBACH |
| CofO Issued | 3/29/2025 | RICHARD STEINBACH |
| Permit Finaled | 3/29/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2019 | JOSE CRUZ RODRIGUEZ |
| Roof/Waste drainage to street | Cleared | 2/25/2019 | JOSE CRUZ RODRIGUEZ |
| Green Code | Cleared | 3/5/2019 | RICHARD GARCIA |
| Low Impact Development | Cleared | 3/8/2019 | JORGE MEJIA LEMUS |
| Permit | Cleared | 3/13/2019 | HISASHI KOBAYAKAWA |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Williamson Const; Lic. No.: 451421-B | 3503 LILIENTIAL AVE LOS ANGELES, CA 90045 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Service/Power Release | 3/21/2019 | Approved | EVAN COOPER |
| Footing/Foundation/Slab | 4/12/2019 | Not Ready for Inspection | KEVIN BEAULIEU |
| Footing/Foundation/Slab | 4/24/2019 | Approved | KEVIN BEAULIEU |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2019 | Conditional Approval | KEVIN BEAULIEU |
| Excavation/Setback/Form/Re-Bar | 5/14/2019 | Approved | KEVIN BEAULIEU |
| BUILDING-Rough-Frame | 6/14/2019 | Partial Approval | KEVIN BEAULIEU |
| Green Building Rough | 6/14/2019 | Not Ready for Inspection | KEVIN BEAULIEU |
| BUILDING-Rough-Frame | 7/2/2019 | Not Ready for Inspection | KEVIN BEAULIEU |
| Green Building Rough | 7/2/2019 | Not Ready for Inspection | KEVIN BEAULIEU |
| BUILDING-Rough-Frame | 7/18/2019 | Corrections Issued | ROBERT SHELLY |
| Green Building Rough | 7/18/2019 | Not Ready for Inspection | ROBERT SHELLY |
| Rough-Elec/Plmb/HVAC | 7/18/2019 | Not Ready for Inspection | ROBERT SHELLY |
| Deputy Drilled-In Anchors | 7/24/2019 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 7/25/2019 | Partial Approval | KEVIN BEAULIEU |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2019 | Partial Approval | KEVIN BEAULIEU |
| Green Building Rough | 7/25/2019 | Not Ready for Inspection | KEVIN BEAULIEU |
| HVAC-Rough | 7/25/2019 | Not Ready for Inspection | KEVIN BEAULIEU |
| PLUMBING-Rough | 7/25/2019 | Not Ready for Inspection | KEVIN BEAULIEU |
| Rough-Elec/Plmb/HVAC | 8/1/2019 | Approved | KEVIN BEAULIEU |
| BUILDING-Rough-Frame | 8/7/2019 | Approved | KEVIN BEAULIEU |
| Green Building Rough | 8/7/2019 | Approved | KEVIN BEAULIEU |
| Insulation | 8/21/2019 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 8/29/2019 | Approved | KEVIN BEAULIEU |
| Gas Test | 10/1/2019 | Approved | KEVIN BEAULIEU |
| Interior/Exterior Lathing | 10/1/2019 | Approved | KEVIN BEAULIEU |
| ELECTRICAL-Final | 10/25/2019 | Not Ready for Inspection | KEVIN BEAULIEU |
| Underground Mechanical | 10/29/2019 | Not Ready for Inspection | DAVID FEILER |
| Gas Test | 11/6/2019 | Not Ready for Inspection | KEVIN BEAULIEU |
| Gas Test | 11/12/2019 | Not Ready for Inspection | KEVIN BEAULIEU |
| ELECTRICAL-Final | 11/23/2019 | Not Ready for Inspection | KENNETH NAGLE |
| Service/Power Release | 3/6/2020 | Approved | KEVIN BEAULIEU |
| Final | 4/23/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 4/23/2020 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 4/23/2020 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 4/23/2020 | Approved | OGANES TARAKHCHYAN |
| Final | 6/23/2020 | Conditional Approval | JUSTIN CURTIS |
| SGSOV-Seismic Gas S/O Valve | 6/23/2020 | SGSOV Approved | JUSTIN CURTIS |
| Final | 10/12/2024 | Corrections Issued | MICHAEL PELHAM |
| Final | 3/29/2025 | OK to Issue CofO | MICHAEL PELHAM |