14829 W EL CASCO ST 91342
Certificate Information: 14829 W EL CASCO ST 91342
- Application / Permit
- 19014-20004-02374
- Plan Check / Job No.
- B20VN01871
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTAL TO PERMIT #: 19014-20003-02374 TO REVISE WORK DESCRIPTION FOR NEW 53'-0" X 74'-4" 1-STORY SFD W/ ATTACHED 21'-6" X 22'-0" 2-CAR GARAGE AND COVERED PATIOS AT FRONT AND REAR OF BUILDING. ALL WORK PER ENGINEERING. [NFPA -13D FIRE SPRINKLERS REQUIRED THROUGHOUT]
- Permit Issued
- Issued on 3/2/2020
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 5/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/6/2020 | JENNIFER LEE |
| Corrections Issued | 2/6/2020 | JENNIFER LEE |
| Plan Check Approved | 2/11/2020 | JENNIFER LEE |
| Issued | 3/2/2020 | LADBS |
| Permit Finaled | 4/29/2022 | JOHN HAYES |
Permit Application Clearance Information
| Green Code | Cleared | 2/7/2020 | MICHAEL AYERS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/5/2020 | Corrections Issued | PIERRE VEGA |
| Special/Order Compliance | 3/5/2020 | Approved | TROY SANDERS |
| Pre-Inspection | 4/6/2020 | Approved | TROY SANDERS |
| Footing/Foundation/Slab | 4/15/2020 | Approved | TROY SANDERS |
| Deputy Reinf. Concrete | 4/16/2020 | No Result Entered | KENNETH KUROWSKI |
| Insulation | 4/29/2020 | Partial Approval | TROY SANDERS |
| Deputy Wood Construction | 6/11/2020 | Approved | GREGG CUMMINGS |
| Deputy Wood Construction | 6/11/2020 | Approved | PIERRE VEGA |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2020 | Approved | GREGG CUMMINGS |
| Pre-Inspection | 6/15/2020 | Approved | GREGG CUMMINGS |
| Green Building Rough | 8/13/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 8/13/2020 | Approved | MISAEL ESPARZA |
| Wood Frame | 8/13/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 9/30/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| Pre-Inspection | 9/30/2020 | Approved | MISAEL ESPARZA |
| Wood Frame | 9/30/2020 | Approved | MISAEL ESPARZA |
| Insulation | 10/7/2020 | Conditional Approval | MISAEL ESPARZA |
| Insulation | 10/15/2020 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 10/15/2020 | Partial Approval | MISAEL ESPARZA |
| Drywall Nailing | 10/30/2020 | Approved | DANIEL ORRANTE |
| Green Building Rough | 10/30/2020 | Approved | DANIEL ORRANTE |
| Final | 12/4/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 12/4/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 8/26/2021 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 8/26/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 9/23/2021 | Corrections Issued | JOHN HAYES |
| Green Building Final | 9/23/2021 | Not Ready for Inspection | JOHN HAYES |
| Final | 11/19/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 11/19/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Pre-Inspection | 3/4/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 4/29/2022 | Permit Finaled | JOHN HAYES |
| Green Building Final | 4/29/2022 | Approved | JOHN HAYES |