9165 W CORDELL DR 90069
Certificate Information: 9165 W CORDELL DR 90069
- Application / Permit
- 19014-20004-01304
- Plan Check / Job No.
- B19VN21621
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTAL PERMIT FOR 19014-20000-01304 TO REVISE SCOPE OF WORK TO (N) 2-STORY SFD W/ ATTACHED GARAGE & BASEMENT
- Permit Issued
- Issued on 1/31/2020
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 10/7/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2019 | NILOOFAR MEHRAIN |
| Corrections Issued | 12/23/2019 | NILOOFAR MEHRAIN |
| Quality Review Completed | 12/23/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 12/30/2019 | APPLICANT |
| Green Plans Picked Up | 12/30/2019 | APPLICANT |
| Applicant returned to address corrections | 1/17/2020 | NILOOFAR MEHRAIN |
| Plan Check Approved | 1/23/2020 | NILOOFAR MEHRAIN |
| Issued | 1/31/2020 | LADBS |
| Permit Finaled | 10/7/2021 | RAUL BARAJAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/31/2019 | APEKSHYA BAJRACHARYA |
| Roof/Waste drainage to street | Cleared | 12/31/2019 | APEKSHYA BAJRACHARYA |
| Encroachment in public way | Cleared | 1/17/2020 | LEE GUILBEAUX |
| Work Adjacent to Public Way | Cleared | 1/17/2020 | LEE GUILBEAUX |
| Green Code | Cleared | 1/21/2020 | DAVID MATSON |
Contact Information
| Contractor | Call Bryce Construction Inc; Lic. No.: 675054-B | P O BOX 220053 NEWHALL, CA 91322 |
| Engineer | Pirbadian,, Amir; Lic. No.: C72413 | 5435 BALBOA BLVD 214 ENCINO, CA 91342 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/28/2020 | Partial Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 2/28/2020 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 3/2/2020 | Conditional Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 3/18/2020 | Partial Approval | RICHARD STEINBACH |
| Pre-Inspection | 3/18/2020 | Partial Approval | RICHARD STEINBACH |
| Deputy Reinf. Concrete | 3/19/2020 | Conditional Approval | RICHARD STEINBACH |
| Reinforced Concrete Frame | 4/17/2020 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 4/23/2020 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 4/24/2020 | Conditional Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 5/8/2020 | Partial Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 5/28/2020 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 6/10/2020 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 6/23/2020 | Conditional Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 7/2/2020 | Partial Approval | RAUL BARAJAS |
| Green Building Rough | 7/17/2020 | Partial Approval | RAUL BARAJAS |
| Green Building Rough | 8/10/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 8/10/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Wood Frame | 8/10/2020 | Partial Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2020 | Partial Approval | RAUL BARAJAS |
| Drywall Nailing | 9/10/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2020 | Partial Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2020 | Partial Inspection | RAUL BARAJAS |
| Interior/Exterior Lathing | 1/19/2021 | Approved | RAUL BARAJAS |
| Masonry Wall/Backfill | 1/26/2021 | Approved | RAUL BARAJAS |
| Drywall Nailing | 2/18/2021 | Partial Approval | RAUL BARAJAS |
| Interior/Exterior Lathing | 2/18/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Drywall Nailing | 3/1/2021 | Approved | RAUL BARAJAS |
| Drywall Nailing | 3/19/2021 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 3/22/2021 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 3/22/2021 | Approved | RAUL BARAJAS |
| Light Gage Steel Frame | 6/1/2021 | Approved | RAUL BARAJAS |
| Final | 9/8/2021 | Partial Inspection | RICHARD STEINBACH |