7636 N LOUISE AVE 91406
Certificate Information: 7636 N LOUISE AVE 91406
- Application / Permit
- 19014-20002-03325
- Plan Check / Job No.
- B20VN11397
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- SUPPLEMENTAL PERMIT FOR 19014-20000-03325 TO REVISE SCOPE OF WORK TO (N) DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c) & (d)
- Permit Issued
- Issued on 1/7/2021
- Issuing Office
- Current Status
- Permit Finaled on 8/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/11/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 9/15/2020 | NILOOFAR MEHRAIN |
| Building Plans Picked Up | 9/15/2020 | APPLICANT |
| Applicant returned to address corrections | 12/1/2020 | NILOOFAR MEHRAIN |
| Plan Check Approved | 12/8/2020 | NILOOFAR MEHRAIN |
| Issued | 1/7/2021 | APPLICANT |
| Permit Finaled | 8/19/2024 | RAUL OLAGI |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/18/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 9/18/2020 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 10/15/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 12/16/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 12/28/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rodriguez,, Jacob; Lic. No.: S5084 | 8206 ENCINO AVE NORTHRIDGE, CA 91325 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 6/15/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| HVAC-Rough | 6/15/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Rough | 6/15/2021 | Corrections Issued | JACK KARGODORIAN |
| Wood Frame | 6/15/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Rough | 7/15/2021 | Corrections Issued | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 7/20/2021 | Approved | JACK KARGODORIAN |
| Green Building Rough | 7/20/2021 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 7/20/2021 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 7/20/2021 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 8/20/2021 | Corrections Issued | AMY COLIN |
| Insulation | 8/20/2021 | Corrections Issued | AMY COLIN |
| HVAC-Rough | 9/8/2021 | Approved | AMY COLIN |
| Insulation | 9/8/2021 | Approved | AMY COLIN |
| Drywall Nailing | 9/22/2021 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 9/22/2021 | Approved | JACK KARGODORIAN |
| Shower Pan | 2/8/2022 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 2/15/2022 | Approved | RAUL OLAGI |
| Final | 2/14/2023 | Corrections Issued | RAUL OLAGI |
| Pre-Inspection | 2/22/2023 | Corrections Issued | JUAN VALENZUELA |