607 N RADCLIFFE AVE 90272
Certificate Information: 607 N RADCLIFFE AVE 90272
- Application / Permit
- 19014-20002-00184
- Plan Check / Job No.
- B19VN17997
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTAL TO 19014-20000-00184 TO REVISE WORK DESCRIPTION TO 'REMOVE (E) SFD & NORTH EXTERIOR WALL TO REMAIN. REBUILD 1368 SF SFD DUE TO 85% TERMITE DAMAGE IN SAME LOCATION. ADD 187 SF AND (N) ATTACHED DECK. ALL WORK PER ENGINEERING. NFPA 13D FIRE SPRINKLERS THROUGHOUT."
- Permit Issued
- Issued on 2/5/2020
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 8/9/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/18/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2019 | RAPHAEL ROSAS |
| Corrections Issued | 11/2/2019 | RAPHAEL ROSAS |
| Quality Review Completed | 11/12/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 11/15/2019 | APPLICANT |
| Applicant returned to address corrections | 12/18/2019 | RAPHAEL ROSAS |
| Plan Check Approved | 2/4/2020 | RAPHAEL ROSAS |
| No Progress | 2/4/2020 | RAPHAEL ROSAS |
| Plan Check Approved | 2/5/2020 | RAPHAEL ROSAS |
| Issued | 2/5/2020 | LADBS |
| Permit Finaled | 8/9/2021 | ANDREW NAVE |
Permit Application Clearance Information
| Address approval | Cleared | 11/20/2019 | MARKOS PEREZ-BRAN |
| BHO/Hillside ordinance | Cleared | 11/20/2019 | MARKOS PEREZ-BRAN |
| BHO/Hillside ordinance | Cleared | 11/20/2019 | MARKOS PEREZ-BRAN |
| BHO/Hillside ordinance | Cleared | 11/20/2019 | MARKOS PEREZ-BRAN |
| Coastal Zone | Cleared | 11/20/2019 | SOPHIE GABEL-SCHEINBAU |
| Distance to fire station | Cleared | 11/20/2019 | GEORGE SUCHAND |
| Eng Process Fee Ord 176,300 | Cleared | 11/20/2019 | MARKOS PEREZ-BRAN |
| Miscellaneous | Cleared | 11/20/2019 | SOPHIE GABEL-SCHEINBAU |
| Sewer availability | Cleared | 11/20/2019 | MARKOS PEREZ-BRAN |
| ZA Case | Cleared | 11/20/2019 | SOPHIE GABEL-SCHEINBAU |
| Low Impact Development | Cleared | 12/10/2019 | RYAN HUDSON |
| Roof/Waste drainage to street | Cleared | 12/10/2019 | GUILLERMO PETRA |
| Grading Pre-Inspection | Cleared | 12/18/2019 | RAPHAEL ROSAS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 8/9/2021 | Approved | ANDREW NAVE |
| Drywall Nailing | 8/9/2021 | Approved | ANDREW NAVE |
| Final | 8/9/2021 | Permit Finaled | ANDREW NAVE |
| Smoke Detectors | 8/9/2021 | Approved | ANDREW NAVE |
| Structural Steel Frame | 8/9/2021 | Approved | ANDREW NAVE |
| Verify Sprinkler Sign Off | 8/9/2021 | Approved | ANDREW NAVE |