13800 W MULHOLLAND DR 90210
Certificate Information: 13800 W MULHOLLAND DR 90210
- Application / Permit
- 19014-20001-06806
- Plan Check / Job No.
- B20VN16161
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTAL TO 19014-20000-06806 FOR 13'-4" X 10'-1" IRREG SHAPED ADDITION TO ADD ELEVATOR LOBBY. CHANGE CONTRACTOR AND ENGINEER ON RECORD.
- Permit Issued
- Issued on 7/21/2021
- Issuing Office
- Current Status
- Permit Finaled on 12/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 1/3/2021 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 6/17/2021 | JEROME MAGAT PALMA |
| Issued | 7/21/2021 | APPLICANT |
| Building Plans Picked Up | 8/11/2021 | APPLICANT |
| Permit Finaled | 12/13/2023 | BRENDAN LOONEY |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/24/2021 | CATHERINE ADROVER |
| Roof/Waste drainage to street | Cleared | 5/25/2021 | CATHERINE ADROVER |
| Specific Plan | Cleared | 6/3/2021 | OLGA AYALA |
| ZA Case | Cleared | 6/18/2021 | OLGA AYALA |
Contact Information
| Contractor | Cain Interiors & Construction Llc; Lic. No.: 1051938-B | 6155 W 75TH PLACE LOS ANGELES, CA 90045 |
| Engineer | Ilasin,, John Lacebal; Lic. No.: C67469 | 1011 OARFISH LN OXNARD, CA 93035 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/17/2021 | Partial Approval | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 3/1/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 4/10/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 4/10/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 4/10/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 4/10/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Drywall Nailing | 5/15/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 5/15/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 12/13/2023 | Approved | BRENDAN LOONEY |
| Final | 12/13/2023 | Permit Finaled | BRENDAN LOONEY |
| Footing/Foundation/Slab | 12/13/2023 | Approved | BRENDAN LOONEY |
| Green Building Final | 12/13/2023 | Approved | BRENDAN LOONEY |
| Green Building Rough | 12/13/2023 | Approved | BRENDAN LOONEY |
| Smoke Detectors | 12/13/2023 | Approved | BRENDAN LOONEY |