2734-2736 S BAGLEY AVE 90034

Certificate Information: 2734-2736 S BAGLEY AVE 90034

Application / Permit
19014-20001-06576
Plan Check / Job No.
B20VN06241
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SUPPLEMENTAL PERMIT TO REVISE SCOPE OF WORK TO - 69'-6" X 40'-0" IRREG SHAPED ADDITION FOR (N) 20'-3" X 18'-9" ATTACHED ACCESSORY DWELLING UNIT (388 SQ FT) AND TO ENLARGE AND REMODEL (E) SINGLE FAMILY DWELLING.
Permit Issued
Issued on 7/10/2020
Issuing Office
Current Status
Permit Finaled on 11/12/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/2/2020 APPLICANT
Assigned to Plan Check Engineer 5/7/2020 JEROME MAGAT PALMA
Corrections Issued 5/11/2020 JEROME MAGAT PALMA
Plan Check Approved 6/25/2020 JEROME MAGAT PALMA
Issued 7/10/2020 APPLICANT
Permit Finaled 11/12/2021 KEVIN SARGSYAN

Permit Application Clearance Information

Address approval Cleared 5/15/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 5/19/2020 DINAH GARIN
Sewer availability Cleared 5/19/2020 DINAH GARIN
Low Impact Development Cleared 6/15/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 6/24/2020 DINAH GARIN

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor A 1 Construction & Designs Inc; Lic. No.: 1002697-B 2817 SOUTH ROBERTSON BLVD      LOS ANGELES, CA 90034
Contractor Best Builders & Development Inc; Lic. No.: 850444-B 15260 VENTURA BLVD STE 1200      SHERMAN OAKS, CA 91403

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/27/2020 Corrections Issued KEVIN SARGSYAN
METHANE-Barrier 7/27/2020 Not Ready for Inspection KEVIN SARGSYAN
METHANE-Subgrade 7/27/2020 Not Ready for Inspection KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 7/30/2020 Approved KEVIN SARGSYAN
Footing/Foundation/Slab 7/30/2020 Approved KEVIN SARGSYAN
METHANE-Barrier 7/30/2020 Approved KEVIN SARGSYAN
METHANE-Subgrade 7/30/2020 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 8/13/2020 Partial Approval KEVIN SARGSYAN
Green Building Rough 8/13/2020 Not Ready for Inspection KEVIN SARGSYAN
METHANE-Rough 8/13/2020 Approved KEVIN SARGSYAN
PLUMBING-Rough 8/13/2020 Corrections Issued KEVIN SARGSYAN
Sewer 8/13/2020 Not Ready for Inspection KEVIN SARGSYAN
Underground Mechanical 8/13/2020 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 8/14/2020 Corrections Issued KEVIN SARGSYAN
Insulation 8/17/2020 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 8/17/2020 Partial Approval KEVIN SARGSYAN
Underground Mechanical 8/17/2020 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 8/20/2020 Partial Approval KEVIN SARGSYAN
ELECTRICAL-Rough 10/9/2020 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 10/9/2020 Approved KEVIN SARGSYAN
HVAC-Rough 10/9/2020 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 10/9/2020 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 10/23/2020 Approved KEVIN SARGSYAN
HVAC-Rough 10/23/2020 Approved KEVIN SARGSYAN
PLUMBING-Rough 10/23/2020 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 11/6/2020 Not Ready for Inspection KEVIN SARGSYAN
Green Building Rough 11/6/2020 Corrections Issued KEVIN SARGSYAN
Shower Pan 11/6/2020 Corrections Issued KEVIN SARGSYAN
BUILDING-Rough-Frame 11/10/2020 Approved KEVIN SARGSYAN
Green Building Rough 11/10/2020 Approved KEVIN SARGSYAN
Shower Pan 11/10/2020 Approved KEVIN SARGSYAN
Insulation 11/16/2020 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 11/16/2020 Approved KEVIN SARGSYAN
Shower Pan 11/16/2020 Approved KEVIN SARGSYAN
Drywall Nailing 12/2/2020 Approved KEVIN SARGSYAN
Gas Test 4/21/2021 Approved KEVIN SARGSYAN
Service/Power Release 4/21/2021 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Final 5/5/2021 Approved KEVIN SARGSYAN
HVAC-Final 5/5/2021 Corrections Issued KEVIN SARGSYAN
PLUMBING-Final 5/5/2021 Approved KEVIN SARGSYAN
Final 5/7/2021 No Access for Inspection KEVIN SARGSYAN
Green Building Final 5/7/2021 No Access for Inspection KEVIN SARGSYAN
Smoke Detectors 5/7/2021 No Access for Inspection KEVIN SARGSYAN
ELECTRICAL-Final 5/12/2021 Approved KEVIN SARGSYAN
Final 5/12/2021 Corrections Issued KEVIN SARGSYAN
Green Building Final 5/12/2021 Approved KEVIN SARGSYAN
HVAC-Final 5/12/2021 Approved KEVIN SARGSYAN
PLUMBING-Final 5/12/2021 Approved KEVIN SARGSYAN
Smoke Detectors 5/12/2021 Approved KEVIN SARGSYAN
Final 6/28/2021 Not Ready for Inspection KEVIN SARGSYAN
Final 11/12/2021 Permit Finaled KEVIN SARGSYAN
Service/Power Release 11/12/2021 Not Required KEVIN SARGSYAN