4424 S CORINTH AVE 90230
Certificate Information: 4424 S CORINTH AVE 90230
- Application / Permit
- 19014-20001-06337
- Plan Check / Job No.
- B21VN15954
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- SUPP. PERMIT TO 19014-20000-06337 TO ADD TO ADU AND INCREASE THE HEIGHT
- Permit Issued
- Issued on 8/18/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 9/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/17/2021 | MOHAMMAD ESMAILI |
| Corrections Issued | 12/6/2021 | MOHAMMAD ESMAILI |
| Plan Check Approved | 8/11/2022 | MOHAMMAD ESMAILI |
| Issued | 8/18/2022 | APPLICANT |
| Permit Finaled | 9/1/2022 | JESUS RODRIGUEZ |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/6/2021 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 12/6/2021 | HISASHI KOBAYAKAWA |
| Construction near power lines | Cleared | 7/12/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ng,, Edward T W; Lic. No.: C38552 | 979 E MUNCIE AVE FRESNO, CA 93720 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/29/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 8/31/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Final | 8/31/2022 | Partial Inspection | JESUS RODRIGUEZ |
| Green Building Rough | 8/31/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| MERV13>=Rough | 8/31/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Rough | 8/31/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Final | 9/1/2022 | Permit Finaled | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 9/1/2022 | Approved | JESUS RODRIGUEZ |