4424 S CORINTH AVE 90230

Certificate Information: 4424 S CORINTH AVE 90230

Application / Permit
19014-20001-06337
Plan Check / Job No.
B21VN15954
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
SUPP. PERMIT TO 19014-20000-06337 TO ADD TO ADU AND INCREASE THE HEIGHT
Permit Issued
Issued on 8/18/2022
Issuing Office
Metro
Current Status
Permit Finaled on 9/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/17/2021 APPLICANT
Assigned to Plan Check Engineer 11/17/2021 MOHAMMAD ESMAILI
Corrections Issued 12/6/2021 MOHAMMAD ESMAILI
Plan Check Approved 8/11/2022 MOHAMMAD ESMAILI
Issued 8/18/2022 APPLICANT
Permit Finaled 9/1/2022 JESUS RODRIGUEZ

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/6/2021 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 12/6/2021 HISASHI KOBAYAKAWA
Construction near power lines Cleared 7/12/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Ng,, Edward T W; Lic. No.: C38552 979 E MUNCIE AVE      FRESNO, CA 93720

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/29/2022 Not Ready for Inspection JESUS RODRIGUEZ
BUILDING-Rough-Frame 8/31/2022 Not Ready for Inspection JESUS RODRIGUEZ
Final 8/31/2022 Partial Inspection JESUS RODRIGUEZ
Green Building Rough 8/31/2022 Not Ready for Inspection JESUS RODRIGUEZ
MERV13>=Rough 8/31/2022 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Rough 8/31/2022 Not Ready for Inspection JESUS RODRIGUEZ
Final 9/1/2022 Permit Finaled JESUS RODRIGUEZ