11421 W CANTON DR 91604

Certificate Information: 11421 W CANTON DR 91604

Application / Permit
19014-20001-04414
Plan Check / Job No.
B21VN02622
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SUPPLEMENTAL PERMT TO 19014-20000-04414 TO REMOVE BASEMENT FROM SCOPE OF WORK; ADD 3'-6" X 13'-4" TO ENLARGE KITCHEN; REVISE COMMENTS AND STRUCTURAL INVENTORY
Permit Issued
Issued on 4/30/2021
Issuing Office
Valley
Current Status
Permit Finaled on 2/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/5/2021 APPLICANT
Assigned to Plan Check Engineer 3/5/2021 SELLA BENYAMIN
Corrections Issued 3/5/2021 SELLA BENYAMIN
Plan Check Approved 4/20/2021 SELLA BENYAMIN
Issued 4/30/2021 APPLICANT
Permit Finaled 2/20/2025 CHRISTOPHE COCHRAN

Permit Application Clearance Information

Low Impact Development Cleared 3/21/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 4/5/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 4/6/2021 ADRIAN CASTRO

Contact Information

Architect Applebaum,, David Lyle; Lic. No.: C21089 12400 VENTURA BLVD 352      STUDIO CITY, CA 91604
Contractor Triple T Construction; Lic. No.: 630238-B 1822 E ROUTE 66 #251      GLENDORA, CA 91740
Engineer Niver,, Kenneth Earl; Lic. No.: S2554 10845 LINDBROOK DR STE 203      W LOS ANGELES, CA 90024

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/27/2022 Partial Approval CHRISTOPHE COCHRAN
Piling/Pier/Caisson 7/27/2022 Partial Approval CHRISTOPHE COCHRAN
Piling/Pier/Caisson 8/4/2022 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 10/5/2022 Partial Approval CHRISTOPHE COCHRAN
Structural Steel Frame 10/5/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 12/16/2022 Partial Approval CHRISTOPHE COCHRAN
Footing/Foundation/Slab 12/16/2022 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 2/20/2025 Approved CHRISTOPHE COCHRAN
Final 2/20/2025 Permit Finaled CHRISTOPHE COCHRAN
Green Building Final 2/20/2025 Approved CHRISTOPHE COCHRAN
Green Building Rough 2/20/2025 Approved CHRISTOPHE COCHRAN