11121 N RINCON AVE 91340
Certificate Information: 11121 N RINCON AVE 91340
- Application / Permit
- 19014-20000-07252
- Plan Check / Job No.
- B19VN22812
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY ADU AT REAR OF LOT W/ ATTACHED GARAGE.
- Permit Issued
- Issued on 3/12/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/31/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/8/2020 | JOE VO |
| Corrections Issued | 1/13/2020 | JOE VO |
| Quality Review Completed | 1/17/2020 | KEN GILL |
| Green Plans Picked Up | 1/22/2020 | APPLICANT |
| Building Plans Picked Up | 1/28/2020 | APPLICANT |
| Plan Check Approved | 3/9/2020 | JOE VO |
| Issued | 3/12/2020 | LADBS |
| CofO in Progress | 7/11/2022 | JENNIFER RABUCHIN |
| Permit Finaled | 7/14/2022 | MICHAEL SMITH |
| CofO Issued | 7/14/2022 | MICHAEL SMITH |
| Permit Finaled | 7/14/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Low Impact Development | Cleared | 2/24/2020 | JORGE MEJIA LEMUS |
| Address approval | Cleared | 3/6/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 3/6/2020 | ADRIAN CASTRO |
| Green Code | Cleared | 3/6/2020 | MICHAEL AYERS |
| Hydrant and Access approval | Cleared | 3/6/2020 | ROBERT DUFF |
| Roof/Waste drainage to street | Cleared | 3/6/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 3/6/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/4/2020 | Approved | WILLIAM KUEHN |
| PLUMBING-Rough | 7/24/2020 | Corrections Issued | MICHAEL TEMPLE |
| Underground Mechanical | 7/24/2020 | Partial Approval | MICHAEL TEMPLE |
| Underground Mechanical | 8/6/2020 | Approved | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 8/12/2020 | Corrections Issued | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 8/18/2020 | Approved | KATHRYN BUTTERWORTH |
| Underground Mechanical | 10/8/2020 | Approved | DANIEL ORRANTE |
| BUILDING-Rough-Frame | 12/4/2020 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 12/4/2020 | Not Ready for Inspection | JENNIFER RABUCHIN |
| MERV13>=Rough | 12/4/2020 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 12/4/2020 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2020 | Partial Approval | MISAEL ESPARZA |
| ELECTRICAL-Rough | 3/10/2021 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 3/10/2021 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/10/2021 | Partial Approval | JENNIFER RABUCHIN |
| HVAC-Rough | 4/14/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/14/2021 | Approved | JENNIFER RABUCHIN |
| Insulation | 8/25/2021 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 8/25/2021 | Partial Approval | JENNIFER RABUCHIN |
| Shower Pan | 8/25/2021 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 9/1/2021 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 9/1/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 9/24/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 12/29/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 3/29/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 3/29/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 3/29/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 3/29/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 3/29/2022 | Approved | JENNIFER RABUCHIN |
| MERV13>=Final | 3/29/2022 | Corrections Issued | JENNIFER RABUCHIN |
| MERV13>=Rough | 3/29/2022 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 3/29/2022 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Service/Power Release | 3/29/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 3/29/2022 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 4/6/2022 | Approved | JENNIFER RABUCHIN |
| Gas Test | 4/6/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 4/6/2022 | Approved | JENNIFER RABUCHIN |
| MERV13>=Final | 4/6/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 4/6/2022 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 4/6/2022 | SGSOV Approved | JENNIFER RABUCHIN |
| Final | 4/8/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Service/Power Release | 4/8/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 4/8/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 6/23/2022 | Approved | JENNIFER RABUCHIN |
| Final | 6/23/2022 | OK to Issue CofO | JENNIFER RABUCHIN |
| Service/Power Release | 6/23/2022 | Approved | JENNIFER RABUCHIN |