20424 W SCHOENBORN ST 91306

Certificate Information: 20424 W SCHOENBORN ST 91306

Application / Permit
19014-20000-07250
Plan Check / Job No.
B19VN22807
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION OF 18'x20' TO (E) GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT
Permit Issued
Issued on 4/14/2020
Issuing Office
Current Status
CofO Issued on 3/16/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/31/2019 APPLICANT
Green Plans Picked Up 2/6/2020 APPLICANT
Assigned to Plan Check Engineer 2/13/2020 SEAN SHAHMIRI
Corrections Issued 2/18/2020 SEAN SHAHMIRI
Quality Review Completed 2/25/2020 OMID HEDAYAT
Building Plans Picked Up 2/26/2020 APPLICANT
Applicant returned to address corrections 3/19/2020 SEAN SHAHMIRI
Applicant returned to address corrections 3/25/2020 SEAN SHAHMIRI
Plan Check Approved 3/25/2020 SEAN SHAHMIRI
Issued 4/14/2020 APPLICANT
CofO in Progress 3/12/2021 DAVID STEPANYAN
Permit Finaled 3/16/2021 JOHN JANSON
CofO Issued 3/16/2021 JOHN JANSON
Permit Finaled 3/16/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/2/2020 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 3/2/2020 JOHN LIN
Hydrant and Access approval Cleared 3/2/2020 GEORGE SUCHAND
Roof/Waste drainage to street Cleared 3/2/2020 JOHN LIN
Sewer availability Cleared 3/2/2020 JOHN LIN
ZA Case Cleared 3/2/2020 MIGUEL GAMBOA
Green Code Cleared 3/11/2020 VIVIAN LAO

Contact Information

Contractor Owner-Builder       ,
Engineer Gosen,, James W; Lic. No.: C43590 15315 BLEDSOE ST      SYLMAR, CA 91342

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 4/29/2020 Not Ready for Inspection DAVID STEPANYAN
ELECTRICAL-Rough 4/29/2020 Corrections Issued DAVID STEPANYAN
Excavation/Setback/Form/Re-Bar 4/29/2020 Corrections Issued DAVID STEPANYAN
PLUMBING-Rough 4/29/2020 Not Ready for Inspection DAVID STEPANYAN
Excavation/Setback/Form/Re-Bar 5/6/2020 Partial Inspection MICHAEL TEMPLE
PLUMBING-Rough 5/6/2020 Corrections Issued MICHAEL TEMPLE
PLUMBING-Rough 5/11/2020 Partial Approval MICHAEL TEMPLE
Deputy Drilled-In Anchors 5/13/2020 Approved MICHAEL TEMPLE
Excavation/Setback/Form/Re-Bar 5/13/2020 Corrections Issued MICHAEL TEMPLE
Footing/Foundation/Slab 5/14/2020 Approved MICHAEL TEMPLE
BUILDING-Rough-Frame 6/5/2020 Not Ready for Inspection DAVID STEPANYAN
Green Building Rough 6/5/2020 Not Ready for Inspection DAVID STEPANYAN
PLUMBING-Final 6/5/2020 Not Ready for Inspection DAVID STEPANYAN
PLUMBING-Rough 6/5/2020 Not Ready for Inspection DAVID STEPANYAN
Sewer 6/5/2020 Approved DAVID STEPANYAN
Wood Frame 6/5/2020 Not Ready for Inspection DAVID STEPANYAN
BUILDING-Rough-Frame 7/7/2020 Corrections Issued DAVID STEPANYAN
ELECTRICAL-Rough 7/7/2020 Corrections Issued DAVID STEPANYAN
Green Building Rough 7/7/2020 Not Ready for Inspection DAVID STEPANYAN
PLUMBING-Rough 7/7/2020 Corrections Issued DAVID STEPANYAN
BUILDING-Rough-Frame 7/16/2020 Corrections Issued DAVID STEPANYAN
ELECTRICAL-Rough 7/16/2020 Corrections Issued DAVID STEPANYAN
Green Building Rough 7/16/2020 Not Ready for Inspection DAVID STEPANYAN
PLUMBING-Rough 7/16/2020 Approved DAVID STEPANYAN
ELECTRICAL-Rough 7/21/2020 Approved DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 7/21/2020 Approved DAVID STEPANYAN
HVAC-Rough 7/21/2020 Approved DAVID STEPANYAN
BUILDING-Rough-Frame 8/3/2020 Approved DAVID STEPANYAN
Green Building Rough 8/3/2020 Approved DAVID STEPANYAN
Insulation 8/6/2020 Approved DAVID STEPANYAN
Interior/Exterior Lathing 8/6/2020 Approved DAVID STEPANYAN
Shower Pan 8/6/2020 Approved DAVID STEPANYAN
Drywall Nailing 8/13/2020 Approved DAVID STEPANYAN
ELECTRICAL-Final 12/18/2020 Corrections Issued DAVID STEPANYAN
Final 12/18/2020 Not Ready for Inspection DAVID STEPANYAN
Green Building Final 12/18/2020 Corrections Issued DAVID STEPANYAN
PLUMBING-Final 12/18/2020 Corrections Issued DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 12/18/2020 SGSOV Not Ready DAVID STEPANYAN
Smoke Detectors 12/18/2020 Approved DAVID STEPANYAN
Final 1/19/2021 Not Ready for Inspection TROY SANDERS
Green Building Final 1/19/2021 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 1/19/2021 SGSOV Not Ready TROY SANDERS
Final 2/8/2021 Corrections Issued DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 2/8/2021 SGSOV Not Ready DAVID STEPANYAN
Final 3/11/2021 OK to Issue CofO DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 3/11/2021 SGSOV Approved DAVID STEPANYAN