3510 S 10TH AVE 90018

Certificate Information: 3510 S 10TH AVE 90018

Application / Permit
19014-20000-07233
Plan Check / Job No.
B19VN22765
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION OF 2-STORY ACCESSORY DWELLING UNIT TO (E) GARAGE
Permit Issued
Issued on 4/6/2021
Issuing Office
Current Status
CofO Issued on 11/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/31/2019 APPLICANT
Assigned to Plan Check Engineer 2/13/2020 NILOOFAR MEHRAIN
Corrections Issued 2/24/2020 NILOOFAR MEHRAIN
Quality Review Completed 2/25/2020 GUANG MIN TUNG
Building Plans Picked Up 3/10/2020 APPLICANT
Green Plans Picked Up 7/6/2020 APPLICANT
Plan Check Approved 7/14/2020 NILOOFAR MEHRAIN
Issued 4/6/2021 APPLICANT
CofO in Progress 11/16/2023 CALEB MEISTER
CofO in Progress 11/16/2023 CALEB MEISTER
Permit Finaled 11/18/2023 DEROLD HAUFF
CofO Issued 11/18/2023 DEROLD HAUFF
Permit Finaled 11/18/2023 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 4/5/2020 RIDWAN HARDY
Construction within easement Cleared 4/5/2020 RIDWAN HARDY
Low Impact Development Cleared 6/8/2020 SARAH YOUSSEF
Address approval Cleared 6/10/2020 CECILIO NAVARRO
Permit Cleared 6/15/2020 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 6/15/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 6/18/2020 CECILIO NAVARRO
Sewer availability Cleared 6/18/2020 CECILIO NAVARRO
Hydrant and Access approval Cleared 6/30/2020 KURT CORRAL
Green Code Cleared 7/1/2020 COLIN LOREDO

Contact Information

Architect Gilliam,, Jonathan; Lic. No.: C33995 15017 ARCHWOOD STREET      VAN NUYS, CA 91405
Contractor All In One Construction; Lic. No.: 674782-B 1056 CYPRESS AVENUE #H      LA HABRA, CA 90631
Engineer Sivushenka,, Mikita; Lic. No.: C87698 5525 CANOGA AVE APT 208      WOODLAND HILLS, CA 91367

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/15/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Footing/Foundation/Slab 4/15/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Rough 4/15/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 4/22/2021 Corrections Issued STUART CHAPMAN
PLUMBING-Rough 4/22/2021 Partial Approval STUART CHAPMAN
Footing/Foundation/Slab 4/23/2021 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 5/27/2021 Partial Approval STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 6/8/2021 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 6/8/2021 Not Ready for Inspection STUART CHAPMAN
Deputy Drilled-In Anchors 6/18/2021 No Access for Inspection ELMER BLAND
Footing/Foundation/Slab 6/22/2021 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 7/8/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Footing/Foundation/Slab 7/8/2021 Partial Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 8/5/2021 Partial Approval SCOTT FINNILA
Rough-Elec/Plmb/HVAC 10/13/2021 Partial Approval JUSTIN HAWLEY
Special/Order Compliance 10/13/2021 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 11/12/2021 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 1/18/2022 Conditional Approval SCOTT FINNILA
Rough-Elec/Plmb/HVAC 1/18/2022 Corrections Issued SCOTT FINNILA
Rough-Elec/Plmb/HVAC 5/5/2022 Corrections Issued STUART CHAPMAN
BUILDING-Rough-Frame 5/11/2022 Corrections Issued STUART CHAPMAN
ELECTRICAL-Rough 5/11/2022 Approved STUART CHAPMAN
Footing/Foundation/Slab 5/11/2022 Approved STUART CHAPMAN
Green Building Rough 5/11/2022 Approved STUART CHAPMAN
HVAC-Rough 5/11/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 5/11/2022 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 5/11/2022 Approved STUART CHAPMAN
Rough-Elec/Plmb/HVAC 5/11/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 5/20/2022 Corrections Issued SCOTT FINNILA
BUILDING-Rough-Frame 5/26/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 5/26/2022 Partial Approval STUART CHAPMAN
Insulation 6/17/2022 Approved STUART CHAPMAN
Drywall Nailing 7/12/2022 Approved STUART CHAPMAN
Shower Pan 8/29/2022 Approved STUART CHAPMAN
Gas Test 9/23/2022 Not Ready for Inspection RYAN SALAZAR
Interior/Exterior Lathing 9/23/2022 Approved RYAN SALAZAR
Final 5/15/2023 Not Ready for Inspection CALEB MEISTER
Green Building Final 5/15/2023 Not Ready for Inspection CALEB MEISTER
SGSOV-Seismic Gas S/O Valve 5/15/2023 SGSOV Not Ready CALEB MEISTER
Smoke Detectors 5/15/2023 Not Ready for Inspection CALEB MEISTER
Service/Power Release 6/9/2023 Not Ready for Inspection CALEB MEISTER
ELECTRICAL-Final 6/21/2023 Not Ready for Inspection CALEB MEISTER
Final 6/21/2023 Not Ready for Inspection CALEB MEISTER
Gas Test 6/21/2023 Approved CALEB MEISTER
Green Building Final 6/21/2023 Not Ready for Inspection CALEB MEISTER
HVAC-Final 6/21/2023 Corrections Issued CALEB MEISTER
PLUMBING-Final 6/21/2023 Not Ready for Inspection CALEB MEISTER
SGSOV-Seismic Gas S/O Valve 6/21/2023 SGSOV Approved CALEB MEISTER
Service/Power Release 6/21/2023 Not Ready for Inspection CALEB MEISTER
Smoke Detectors 6/21/2023 Approved CALEB MEISTER
Final 8/18/2023 Not Ready for Inspection CALEB MEISTER
Green Building Final 8/18/2023 Not Ready for Inspection CALEB MEISTER
ELECTRICAL-Final 9/22/2023 Approved CALEB MEISTER
Final 9/22/2023 Not Ready for Inspection CALEB MEISTER
Green Building Final 9/22/2023 Approved CALEB MEISTER
HVAC-Final 9/22/2023 Approved CALEB MEISTER
PLUMBING-Final 9/22/2023 Approved CALEB MEISTER
Final 10/6/2023 Conditional Approval CALEB MEISTER
Final 11/16/2023 OK to Issue CofO CALEB MEISTER