3510 S 10TH AVE 90018
Certificate Information: 3510 S 10TH AVE 90018
- Application / Permit
- 19014-20000-07233
- Plan Check / Job No.
- B19VN22765
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION OF 2-STORY ACCESSORY DWELLING UNIT TO (E) GARAGE
- Permit Issued
- Issued on 4/6/2021
- Issuing Office
- Current Status
- CofO Issued on 11/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/31/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 2/24/2020 | NILOOFAR MEHRAIN |
| Quality Review Completed | 2/25/2020 | GUANG MIN TUNG |
| Building Plans Picked Up | 3/10/2020 | APPLICANT |
| Green Plans Picked Up | 7/6/2020 | APPLICANT |
| Plan Check Approved | 7/14/2020 | NILOOFAR MEHRAIN |
| Issued | 4/6/2021 | APPLICANT |
| CofO in Progress | 11/16/2023 | CALEB MEISTER |
| CofO in Progress | 11/16/2023 | CALEB MEISTER |
| Permit Finaled | 11/18/2023 | DEROLD HAUFF |
| CofO Issued | 11/18/2023 | DEROLD HAUFF |
| Permit Finaled | 11/18/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 4/5/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 4/5/2020 | RIDWAN HARDY |
| Low Impact Development | Cleared | 6/8/2020 | SARAH YOUSSEF |
| Address approval | Cleared | 6/10/2020 | CECILIO NAVARRO |
| Permit | Cleared | 6/15/2020 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 6/15/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 6/18/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 6/18/2020 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 6/30/2020 | KURT CORRAL |
| Green Code | Cleared | 7/1/2020 | COLIN LOREDO |
Contact Information
| Architect | Gilliam,, Jonathan; Lic. No.: C33995 | 15017 ARCHWOOD STREET VAN NUYS, CA 91405 |
| Contractor | All In One Construction; Lic. No.: 674782-B | 1056 CYPRESS AVENUE #H LA HABRA, CA 90631 |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 5525 CANOGA AVE APT 208 WOODLAND HILLS, CA 91367 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/15/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 4/15/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 4/15/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 4/22/2021 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Rough | 4/22/2021 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 4/23/2021 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2021 | Partial Approval | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 6/8/2021 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 6/8/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Deputy Drilled-In Anchors | 6/18/2021 | No Access for Inspection | ELMER BLAND |
| Footing/Foundation/Slab | 6/22/2021 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 7/8/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2021 | Partial Approval | SCOTT FINNILA |
| Rough-Elec/Plmb/HVAC | 10/13/2021 | Partial Approval | JUSTIN HAWLEY |
| Special/Order Compliance | 10/13/2021 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2021 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 1/18/2022 | Conditional Approval | SCOTT FINNILA |
| Rough-Elec/Plmb/HVAC | 1/18/2022 | Corrections Issued | SCOTT FINNILA |
| Rough-Elec/Plmb/HVAC | 5/5/2022 | Corrections Issued | STUART CHAPMAN |
| BUILDING-Rough-Frame | 5/11/2022 | Corrections Issued | STUART CHAPMAN |
| ELECTRICAL-Rough | 5/11/2022 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 5/11/2022 | Approved | STUART CHAPMAN |
| Green Building Rough | 5/11/2022 | Approved | STUART CHAPMAN |
| HVAC-Rough | 5/11/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 5/11/2022 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Rough | 5/11/2022 | Approved | STUART CHAPMAN |
| Rough-Elec/Plmb/HVAC | 5/11/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 5/20/2022 | Corrections Issued | SCOTT FINNILA |
| BUILDING-Rough-Frame | 5/26/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 5/26/2022 | Partial Approval | STUART CHAPMAN |
| Insulation | 6/17/2022 | Approved | STUART CHAPMAN |
| Drywall Nailing | 7/12/2022 | Approved | STUART CHAPMAN |
| Shower Pan | 8/29/2022 | Approved | STUART CHAPMAN |
| Gas Test | 9/23/2022 | Not Ready for Inspection | RYAN SALAZAR |
| Interior/Exterior Lathing | 9/23/2022 | Approved | RYAN SALAZAR |
| Final | 5/15/2023 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Final | 5/15/2023 | Not Ready for Inspection | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 5/15/2023 | SGSOV Not Ready | CALEB MEISTER |
| Smoke Detectors | 5/15/2023 | Not Ready for Inspection | CALEB MEISTER |
| Service/Power Release | 6/9/2023 | Not Ready for Inspection | CALEB MEISTER |
| ELECTRICAL-Final | 6/21/2023 | Not Ready for Inspection | CALEB MEISTER |
| Final | 6/21/2023 | Not Ready for Inspection | CALEB MEISTER |
| Gas Test | 6/21/2023 | Approved | CALEB MEISTER |
| Green Building Final | 6/21/2023 | Not Ready for Inspection | CALEB MEISTER |
| HVAC-Final | 6/21/2023 | Corrections Issued | CALEB MEISTER |
| PLUMBING-Final | 6/21/2023 | Not Ready for Inspection | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 6/21/2023 | SGSOV Approved | CALEB MEISTER |
| Service/Power Release | 6/21/2023 | Not Ready for Inspection | CALEB MEISTER |
| Smoke Detectors | 6/21/2023 | Approved | CALEB MEISTER |
| Final | 8/18/2023 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Final | 8/18/2023 | Not Ready for Inspection | CALEB MEISTER |
| ELECTRICAL-Final | 9/22/2023 | Approved | CALEB MEISTER |
| Final | 9/22/2023 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Final | 9/22/2023 | Approved | CALEB MEISTER |
| HVAC-Final | 9/22/2023 | Approved | CALEB MEISTER |
| PLUMBING-Final | 9/22/2023 | Approved | CALEB MEISTER |
| Final | 10/6/2023 | Conditional Approval | CALEB MEISTER |
| Final | 11/16/2023 | OK to Issue CofO | CALEB MEISTER |