3424 W SUNSET BLVD 90026

Certificate Information: 3424 W SUNSET BLVD 90026

Application / Permit
19014-20000-07226
Plan Check / Job No.
B19VN22748
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(8) Automobile Body & Fender Repairing
Work Description
ADD 23' X 110' METAL ROOF TO COVER PORTION OF (E) ROOF PARKING OF 1-STORY REPAIR SHOP. COMPLY WITH DEPARTMENT ORDER effective date 02/06/2017. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
Permit Issued
Issued on 6/11/2021
Issuing Office
Current Status
CofO Issued on 12/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/31/2019 APPLICANT
Assigned to Plan Check Engineer 1/16/2020 JEROME MAGAT PALMA
Green Plans Picked Up 1/17/2020 APPLICANT
Corrections Issued 1/22/2020 JEROME MAGAT PALMA
Quality Review Completed 1/23/2020 ABDUL CHEGENI
Disabled Access Plans Picked Up 2/10/2020 APPLICANT
Applicant returned to address corrections 6/3/2020 JEROME MAGAT PALMA
Plan Check Approved 2/23/2021 JEROME MAGAT PALMA
Issued 6/11/2021 APPLICANT
Building Plans Picked Up 6/15/2021 APPLICANT
CofO in Progress 12/9/2021 EDWIN GREGORYONA
CofO Issued 12/15/2021 ERNESTO CORRAL
Permit Finaled 12/15/2021 ERNESTO CORRAL

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/28/2020 JUAN ASHTON
Sewer availability Cleared 1/28/2020 JUAN ASHTON
Green Code Cleared 5/29/2020 ABDUL CHEGENI
Roof/Waste drainage to street Cleared 6/12/2020 JAMES KHO
DAS Clearance Cleared 1/21/2021 ABDUL CHEGENI
"Q" conditions Cleared 2/5/2021 DENZEL HENDERSON
ZA Case Cleared 2/5/2021 DENZEL HENDERSON

Contact Information

Contractor Eurotech Construction Services; Lic. No.: 1015499-B 15333 MINNESOTA AVENUE      PARAMOUNT, CA 90723
Engineer Allan,, Collins; Lic. No.: C60527 17906 CORRINE WY      RIVERSIDE, CA 92504

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Final 8/3/2021 Partial Inspection EDWIN GREGORYONA
Final 12/9/2021 OK to Issue CofO EDWIN GREGORYONA
Footing/Foundation/Slab 12/9/2021 Approved EDWIN GREGORYONA