12810 W WADDELL ST 91607

Certificate Information: 12810 W WADDELL ST 91607

Application / Permit
19014-20000-07218
Plan Check / Job No.
B19VN22737
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF 450 sf TO REAR PORTION OF (E) SINGLE FAMILY DWELLING AND MAJOR REMODEL
Permit Issued
Issued on 11/4/2020
Issuing Office
Current Status
CofO Issued on 2/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/31/2019 APPLICANT
Assigned to Plan Check Engineer 2/13/2020 SEAN SHAHMIRI
Corrections Issued 2/14/2020 SEAN SHAHMIRI
Quality Review Completed 2/24/2020 OMID HEDAYAT
Building Plans Picked Up 3/5/2020 APPLICANT
Green Plans Picked Up 9/8/2020 APPLICANT
Applicant returned to address corrections 9/22/2020 SEAN SHAHMIRI
Plan Check Approved 10/13/2020 SEAN SHAHMIRI
Issued 11/4/2020 APPLICANT
CofO in Progress 1/25/2022 CHRISTOPHE COCHRAN
Permit Finaled 2/5/2022 MICHAEL SMITH
CofO Issued 2/5/2022 MICHAEL SMITH
Permit Finaled 2/5/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/11/2020 GABRIEL ROBLES
Low Impact Development Cleared 8/13/2020 ORVAL HERNANDEZ-MARCI
Green Code Cleared 8/27/2020 COLIN LOREDO
Roof/Waste drainage to street Cleared 10/6/2020 GUILLERMO PETRA
Sewer availability Cleared 10/6/2020 GUILLERMO PETRA

Contact Information

Architect Sturgill,, Ben Curtis; Lic. No.: C23174 314 E BROADWAY # E      GLENDALE, CA 91205
Contractor Owner-Builder       ,
Engineer O'Brien,, Kathleen Anne; Lic. No.: C49498 1058 PACIFIC AVE      SIMI VALLEY, CA 93065

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/25/2021 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 4/21/2021 Partial Approval DAVID MATSON
BUILDING-Rough-Frame 4/28/2021 Not Ready for Inspection THOMAS FINNILA
Rough-Elec/Plmb/HVAC 4/28/2021 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 5/5/2021 Approved DANIEL ORRANTE
ELECTRICAL-Rough 5/12/2021 Approved RICHARD DOCKUS
PLUMBING-Rough 5/12/2021 Approved RICHARD DOCKUS
Shower Pan 5/18/2021 Approved RICHARD DOCKUS
HVAC-Rough 5/28/2021 Corrections Issued MICHAEL TEMPLE
Interior/Exterior Lathing 5/28/2021 Partial Approval MICHAEL TEMPLE
HVAC-Rough 6/7/2021 No Access for Inspection RICHARD DOCKUS
Pre-Inspection 6/7/2021 No Access for Inspection RICHARD DOCKUS
HVAC-Rough 6/8/2021 Not Ready for Inspection RICHARD DOCKUS
HVAC-Rough 6/18/2021 Partial Approval RICHARD DOCKUS
BUILDING-Rough-Frame 6/24/2021 Approved RICHARD DOCKUS
Green Building Rough 6/24/2021 Approved RICHARD DOCKUS
HVAC-Rough 6/24/2021 Approved RICHARD DOCKUS
Insulation 6/28/2021 Not Ready for Inspection JAVIER RAMOS JR
Insulation 6/29/2021 Approved MORRIS JACKSON
Drywall Nailing 7/13/2021 Approved CALEB MEISTER
Smoke Detectors 7/13/2021 Corrections Issued CALEB MEISTER
ELECTRICAL-Final 10/15/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 10/15/2021 Corrections Issued CHRISTOPHE COCHRAN
HVAC-Final 10/15/2021 Approved CHRISTOPHE COCHRAN
PLUMBING-Final 10/15/2021 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 10/20/2021 Approved CHRISTOPHE COCHRAN
Final 10/20/2021 Conditional Approval CHRISTOPHE COCHRAN
Green Building Final 10/20/2021 Approved CHRISTOPHE COCHRAN
HVAC-Final 10/20/2021 Approved CHRISTOPHE COCHRAN
PLUMBING-Final 10/20/2021 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 10/20/2021 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 10/20/2021 Approved CHRISTOPHE COCHRAN
Final 1/6/2022 Conditional Approval CHRISTOPHE COCHRAN
Service/Power Release 1/6/2022 Not Ready for Inspection CHRISTOPHE COCHRAN