7912 N ST CLAIR AVE 91605

Certificate Information: 7912 N ST CLAIR AVE 91605

Application / Permit
19014-20000-07217
Plan Check / Job No.
B19VN22735
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 23'-9" x 21'-0" ADDITION TO EXISTING SINGLE FAMILY DWELLING AT REAR.
Permit Issued
Issued on 1/3/2020
Issuing Office
Metro
Current Status
CofO Issued on 3/2/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/31/2019 APPLICANT
Assigned to Plan Check Engineer 12/31/2019 SARKIS HARABEDIAN
Corrections Issued 12/31/2019 SARKIS HARABEDIAN
Plan Check Approved 1/3/2020 ADAM HEGAZI
Issued 1/3/2020 LADBS
CofO in Progress 7/27/2020 JOHN HAYES
Permit Finaled 3/2/2021 MICHAEL SMITH
CofO Issued 3/2/2021 MICHAEL SMITH
Permit Finaled 3/2/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/31/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 12/31/2019 APEKSHYA BAJRACHARYA
Low Impact Development Cleared 1/3/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 1/3/2020 ERIK BEASLEY

Contact Information

Contractor Owner-Builder       ,
Engineer Samadzadeh,, Ali Reza; Lic. No.: C87661 20655 SHERMAN WAY #5      LOS ANGELES, CA 91306

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/15/2020 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 1/15/2020 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 2/11/2020 Approved JOHN HAYES
Footing/Foundation/Slab 2/11/2020 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 2/21/2020 Not Ready for Inspection PIERRE VEGA
PLUMBING-Rough 2/21/2020 Not Ready for Inspection PIERRE VEGA
BUILDING-Rough-Frame 2/24/2020 Corrections Issued JOHN HAYES
PLUMBING-Rough 2/24/2020 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 2/26/2020 Partial Approval JOHN HAYES
PLUMBING-Rough 2/26/2020 Partial Approval JOHN HAYES
Sewer 2/26/2020 Partial Approval JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 3/9/2020 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 3/20/2020 Partial Approval JOHN HAYES
Interior/Exterior Lathing 3/28/2020 Approved MICHEL ABAJAN
ELECTRICAL-Rough 4/2/2020 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 4/2/2020 Partial Approval JOHN HAYES
HVAC-Rough 4/2/2020 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 4/2/2020 Not Ready for Inspection JOHN HAYES
HVAC-Rough 4/3/2020 Approved JOHN HAYES
ELECTRICAL-Rough 4/8/2020 Approved JOHN HAYES
Service/Power Release 4/20/2020 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 4/22/2020 Not Ready for Inspection JOHN HAYES
Green Building Rough 4/22/2020 Not Ready for Inspection JOHN HAYES
Service/Power Release 4/22/2020 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Rough 4/23/2020 Approved JOHN HAYES
Reinforced Concrete Frame 4/23/2020 Approved JOHN HAYES
Service/Power Release 4/23/2020 Approved JOHN HAYES
Special/Order Compliance 4/23/2020 Approved JOHN HAYES
Drywall Nailing 4/30/2020 Approved JOHN HAYES
Green Building Rough 4/30/2020 Approved JOHN HAYES
Insulation 4/30/2020 Approved JOHN HAYES
Shower Pan 4/30/2020 Approved JOHN HAYES
Interior/Exterior Lathing 5/5/2020 Approved PIERRE VEGA
BUILDING-Rough-Frame 6/30/2020 No Access for Inspection PIERRE VEGA
Final 6/30/2020 No Access for Inspection PIERRE VEGA
Green Building Final 6/30/2020 No Access for Inspection PIERRE VEGA
SGSOV-Seismic Gas S/O Valve 6/30/2020 SGSOV Not Ready PIERRE VEGA
Smoke Detectors 6/30/2020 No Access for Inspection PIERRE VEGA
BUILDING-Rough-Frame 7/15/2020 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Final 7/15/2020 Not Ready for Inspection JOHN HAYES
Final 7/15/2020 Not Ready for Inspection JOHN HAYES
Green Building Final 7/15/2020 Not Ready for Inspection JOHN HAYES
HVAC-Final 7/15/2020 Not Ready for Inspection JOHN HAYES
PLUMBING-Final 7/15/2020 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 7/15/2020 SGSOV Not Ready JOHN HAYES
Smoke Detectors 7/15/2020 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 7/22/2020 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Final 7/22/2020 Not Ready for Inspection JOHN HAYES
Final 7/22/2020 Not Ready for Inspection JOHN HAYES
Green Building Final 7/22/2020 Not Ready for Inspection JOHN HAYES
HVAC-Final 7/22/2020 Not Ready for Inspection JOHN HAYES
PLUMBING-Final 7/22/2020 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 7/22/2020 SGSOV Not Ready JOHN HAYES
Smoke Detectors 7/22/2020 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 7/24/2020 Approved JOHN HAYES
Final 7/24/2020 OK to Issue CofO JOHN HAYES
Green Building Final 7/24/2020 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 7/24/2020 SGSOV Approved JOHN HAYES
Smoke Detectors 7/24/2020 Approved JOHN HAYES