7912 N ST CLAIR AVE 91605
Certificate Information: 7912 N ST CLAIR AVE 91605
- Application / Permit
- 19014-20000-07217
- Plan Check / Job No.
- B19VN22735
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 23'-9" x 21'-0" ADDITION TO EXISTING SINGLE FAMILY DWELLING AT REAR.
- Permit Issued
- Issued on 1/3/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/2/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/31/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/31/2019 | SARKIS HARABEDIAN |
| Corrections Issued | 12/31/2019 | SARKIS HARABEDIAN |
| Plan Check Approved | 1/3/2020 | ADAM HEGAZI |
| Issued | 1/3/2020 | LADBS |
| CofO in Progress | 7/27/2020 | JOHN HAYES |
| Permit Finaled | 3/2/2021 | MICHAEL SMITH |
| CofO Issued | 3/2/2021 | MICHAEL SMITH |
| Permit Finaled | 3/2/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/31/2019 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 12/31/2019 | APEKSHYA BAJRACHARYA |
| Low Impact Development | Cleared | 1/3/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 1/3/2020 | ERIK BEASLEY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Samadzadeh,, Ali Reza; Lic. No.: C87661 | 20655 SHERMAN WAY #5 LOS ANGELES, CA 91306 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/15/2020 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 1/15/2020 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 2/11/2020 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 2/11/2020 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2020 | Not Ready for Inspection | PIERRE VEGA |
| PLUMBING-Rough | 2/21/2020 | Not Ready for Inspection | PIERRE VEGA |
| BUILDING-Rough-Frame | 2/24/2020 | Corrections Issued | JOHN HAYES |
| PLUMBING-Rough | 2/24/2020 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 2/26/2020 | Partial Approval | JOHN HAYES |
| PLUMBING-Rough | 2/26/2020 | Partial Approval | JOHN HAYES |
| Sewer | 2/26/2020 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2020 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2020 | Partial Approval | JOHN HAYES |
| Interior/Exterior Lathing | 3/28/2020 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 4/2/2020 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2020 | Partial Approval | JOHN HAYES |
| HVAC-Rough | 4/2/2020 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 4/2/2020 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 4/3/2020 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 4/8/2020 | Approved | JOHN HAYES |
| Service/Power Release | 4/20/2020 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 4/22/2020 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 4/22/2020 | Not Ready for Inspection | JOHN HAYES |
| Service/Power Release | 4/22/2020 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 4/23/2020 | Approved | JOHN HAYES |
| Reinforced Concrete Frame | 4/23/2020 | Approved | JOHN HAYES |
| Service/Power Release | 4/23/2020 | Approved | JOHN HAYES |
| Special/Order Compliance | 4/23/2020 | Approved | JOHN HAYES |
| Drywall Nailing | 4/30/2020 | Approved | JOHN HAYES |
| Green Building Rough | 4/30/2020 | Approved | JOHN HAYES |
| Insulation | 4/30/2020 | Approved | JOHN HAYES |
| Shower Pan | 4/30/2020 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 5/5/2020 | Approved | PIERRE VEGA |
| BUILDING-Rough-Frame | 6/30/2020 | No Access for Inspection | PIERRE VEGA |
| Final | 6/30/2020 | No Access for Inspection | PIERRE VEGA |
| Green Building Final | 6/30/2020 | No Access for Inspection | PIERRE VEGA |
| SGSOV-Seismic Gas S/O Valve | 6/30/2020 | SGSOV Not Ready | PIERRE VEGA |
| Smoke Detectors | 6/30/2020 | No Access for Inspection | PIERRE VEGA |
| BUILDING-Rough-Frame | 7/15/2020 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Final | 7/15/2020 | Not Ready for Inspection | JOHN HAYES |
| Final | 7/15/2020 | Not Ready for Inspection | JOHN HAYES |
| Green Building Final | 7/15/2020 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Final | 7/15/2020 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Final | 7/15/2020 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 7/15/2020 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 7/15/2020 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 7/22/2020 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Final | 7/22/2020 | Not Ready for Inspection | JOHN HAYES |
| Final | 7/22/2020 | Not Ready for Inspection | JOHN HAYES |
| Green Building Final | 7/22/2020 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Final | 7/22/2020 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Final | 7/22/2020 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 7/22/2020 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 7/22/2020 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 7/24/2020 | Approved | JOHN HAYES |
| Final | 7/24/2020 | OK to Issue CofO | JOHN HAYES |
| Green Building Final | 7/24/2020 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 7/24/2020 | SGSOV Approved | JOHN HAYES |
| Smoke Detectors | 7/24/2020 | Approved | JOHN HAYES |