17106 W CEREDO PL 91344
Certificate Information: 17106 W CEREDO PL 91344
- Application / Permit
- 19014-20000-07200
- Plan Check / Job No.
- B19VN22717
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT ATTACHED GARAGE TO FAMILY ROOM. ADD 2'-6" X 6'-0" COVERED PORCH, ADD 33'-0" X 10'-2" ATTACHED TWO CAR CARPORT, ADD 5'-0" X 17'-6" LAUNDRY ROOM, AND 4'-11" X 5'-10" ADDITION TO ENLARGE (E) BATHROOM.
- Permit Issued
- Issued on 1/27/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/22/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/31/2019 | JEROME MAGAT PALMA |
| Corrections Issued | 1/1/2020 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 1/2/2020 | APPLICANT |
| Plan Check Approved | 1/27/2020 | JEROME MAGAT PALMA |
| Issued | 1/27/2020 | LADBS |
| CofO in Progress | 10/22/2020 | DAVID SCANTLIN |
| Permit Finaled | 10/22/2020 | JOHN JANSON |
| CofO Issued | 10/22/2020 | JOHN JANSON |
| Permit Finaled | 10/22/2020 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/13/2020 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 1/13/2020 | GABRIEL ROBLES |
| GPI Written Notices | Cleared | 1/27/2020 | MANUEL TEJADA |
| Grading Pre-Inspection | Cleared | 1/27/2020 | JEROME MAGAT PALMA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Arakelyan,, Aram; Lic. No.: C82796 | 145 S GLENOAKS BI 328 BURBANK, CA 91502 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/17/2020 | Approved | DAVID SCANTLIN |
| Footing/Foundation/Slab | 6/22/2020 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 7/16/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| ELECTRICAL-Rough | 7/16/2020 | Approved | DAVID SCANTLIN |
| Green Building Rough | 7/16/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| PLUMBING-Rough | 7/16/2020 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 7/28/2020 | Approved | DAVID SCANTLIN |
| Green Building Rough | 7/28/2020 | Approved | DAVID SCANTLIN |
| Insulation | 7/28/2020 | Partial Approval | DAVID SCANTLIN |
| Interior/Exterior Lathing | 7/28/2020 | Partial Approval | DAVID SCANTLIN |
| Shower Pan | 7/28/2020 | Approved | DAVID SCANTLIN |
| Insulation | 8/4/2020 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 8/11/2020 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 8/11/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| Interior/Exterior Lathing | 8/17/2020 | Approved | DAVID SCANTLIN |
| Final | 9/30/2020 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 9/30/2020 | Approved | DAVID SCANTLIN |
| HVAC-Final | 9/30/2020 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 9/30/2020 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 9/30/2020 | Approved | DAVID SCANTLIN |
| Final | 10/14/2020 | Corrections Issued | DAVID SCANTLIN |
| Final | 10/21/2020 | OK to Issue CofO | DAVID SCANTLIN |