22932-22934 W ROSCOE BLVD 91304

Certificate Information: 22932-22934 W ROSCOE BLVD 91304

Application / Permit
19014-20000-07192
Plan Check / Job No.
B19VN22694
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD MASTER BEDROOM, BATHROOM & FAMILY ROOM TO (E) 1-STORY SFD; ADD ACCESSORY DWELLING UNIT TO (E) SFD CREATING A 1-STORY SFD W/ ATTACHED ACCESSORY DWELLING PER WFPP; INTERIOR REMODEL
Permit Issued
Issued on 3/13/2020
Issuing Office
Valley
Current Status
CofO Issued on 7/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2019 APPLICANT
Assigned to Plan Check Engineer 2/6/2020 NILOOFAR MEHRAIN
Corrections Issued 2/19/2020 NILOOFAR MEHRAIN
Quality Review Completed 2/20/2020 GUANG MIN TUNG
Building Plans Picked Up 2/25/2020 APPLICANT
Green Plans Picked Up 2/25/2020 APPLICANT
Applicant returned to address corrections 3/10/2020 NILOOFAR MEHRAIN
Plan Check Approved 3/13/2020 NILOOFAR MEHRAIN
Issued 3/13/2020 LADBS
CofO in Progress 7/9/2021 DAVID STEPANYAN
Permit Finaled 7/15/2021 JOHN JANSON
CofO Issued 7/15/2021 JOHN JANSON
Permit Finaled 7/15/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 2/25/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 2/25/2020 ADRIAN CASTRO
Sewer availability Cleared 2/25/2020 ADRIAN CASTRO
Hydrant and Access approval Cleared 3/10/2020 GEORGE SUCHAND
Green Code Cleared 3/11/2020 AARON COSTA
Low Impact Development Cleared 3/12/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 3/13/2020 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/23/2020 Partial Approval DAVID STEPANYAN
PLUMBING-Rough 5/26/2020 Corrections Issued DAVID STEPANYAN
Sewer 5/26/2020 Not Ready for Inspection DAVID STEPANYAN
PLUMBING-Rough 6/4/2020 Partial Approval DAVID STEPANYAN
Sewer 6/4/2020 Approved DAVID STEPANYAN
Deputy Drilled-In Anchors 6/15/2020 Conditional Approval DAVID STEPANYAN
Excavation/Setback/Form/Re-Bar 6/22/2020 Corrections Issued DAVID STEPANYAN
Excavation/Setback/Form/Re-Bar 6/25/2020 Approved DAVID STEPANYAN
BUILDING-Rough-Frame 11/25/2020 Not Ready for Inspection DAVID STEPANYAN
Green Building Rough 11/25/2020 Not Ready for Inspection DAVID STEPANYAN
Wood Frame 11/25/2020 Not Ready for Inspection DAVID STEPANYAN
ELECTRICAL-Rough 1/26/2021 Approved DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 1/26/2021 Approved DAVID STEPANYAN
Gas Test 1/26/2021 Partial Approval DAVID STEPANYAN
HVAC-Rough 1/26/2021 Approved DAVID STEPANYAN
PLUMBING-Rough 1/26/2021 Corrections Issued DAVID STEPANYAN
PLUMBING-Rough 2/3/2021 Not Ready for Inspection DAVID STEPANYAN
Sewer 2/3/2021 Not Ready for Inspection DAVID STEPANYAN
BUILDING-Rough-Frame 2/9/2021 Approved DAVID STEPANYAN
Green Building Rough 2/9/2021 Approved DAVID STEPANYAN
Interior/Exterior Lathing 2/9/2021 Partial Approval DAVID STEPANYAN
PLUMBING-Rough 2/9/2021 Approved DAVID STEPANYAN
Sewer 2/9/2021 Approved DAVID STEPANYAN
Insulation 2/17/2021 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 3/1/2021 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 3/1/2021 Partial Approval CHRISTOPHER DELLEFIELD
Shower Pan 3/1/2021 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 5/18/2021 Approved DAVID STEPANYAN
Final 5/18/2021 Not Ready for Inspection DAVID STEPANYAN
Footing/Foundation/Slab 5/18/2021 Approved DAVID STEPANYAN
Gas Test 5/18/2021 Approved DAVID STEPANYAN
Green Building Final 5/18/2021 Corrections Issued DAVID STEPANYAN
HVAC-Final 5/18/2021 Not Ready for Inspection DAVID STEPANYAN
PLUMBING-Final 5/18/2021 Corrections Issued DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 5/18/2021 SGSOV Not Ready DAVID STEPANYAN
Service/Power Release 5/18/2021 Not Ready for Inspection DAVID STEPANYAN
Smoke Detectors 5/18/2021 Approved DAVID STEPANYAN
ELECTRICAL-Final 6/3/2021 Approved DAVID STEPANYAN
HVAC-Final 6/3/2021 Approved DAVID STEPANYAN
PLUMBING-Final 6/3/2021 Approved DAVID STEPANYAN
Final 7/9/2021 OK to Issue CofO DAVID STEPANYAN
Green Building Final 7/9/2021 Approved DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 7/9/2021 SGSOV Approved DAVID STEPANYAN