6605 N CLYBOURN AVE 91606

Certificate Information: 6605 N CLYBOURN AVE 91606

Application / Permit
19014-20000-07184
Plan Check / Job No.
B19VN22678
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE AND 13'x10'-6" ADDITION FOR ACCESSORY DWELLING UNIT . ADD 20X4'-10" STORAGE TO ADU WITH EXTERIOR ACCESS
Permit Issued
Issued on 2/24/2021
Issuing Office
Current Status
CofO Issued on 3/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2019 APPLICANT
Assigned to Plan Check Engineer 2/6/2020 ALYSSA N NARCISO
Corrections Issued 2/11/2020 ALYSSA N NARCISO
Quality Review Completed 2/13/2020 CHON CHIO KUO
Building Plans Picked Up 2/13/2020 APPLICANT
Green Plans Picked Up 2/13/2020 APPLICANT
Applicant returned to address corrections 1/4/2021 ALYSSA N NARCISO
Applicant returned to address corrections 2/19/2021 ALYSSA N NARCISO
Plan Check Approved 2/24/2021 ALYSSA N NARCISO
Issued 2/24/2021 APPLICANT
CofO in Progress 7/28/2021 DANIEL DREW
Permit Finaled 3/23/2022 DANIEL ORRANTE
CofO Issued 3/23/2022 DANIEL ORRANTE
Permit Finaled 3/23/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/14/2020 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 2/14/2020 LEE GUILBEAUX
Construction near power lines Cleared 4/6/2020 WALTER RAMIREZ
Construction within easement Cleared 4/6/2020 WALTER RAMIREZ
Hydrant and Access approval Cleared 9/29/2020 MATTHEW CRAIG
Eng Process Fee Ord 176,300 Cleared 12/4/2020 GABRIEL ROBLES
Sewer availability Cleared 12/4/2020 GABRIEL ROBLES
Green Code Cleared 12/31/2020 DAVID MATSON

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/8/2021 Approved DANIEL DREW
PLUMBING-Rough 3/8/2021 Partial Approval DANIEL DREW
ELECTRICAL-Rough 4/1/2021 Approved DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 4/1/2021 Partial Approval DANIEL DREW
PLUMBING-Rough 4/1/2021 Approved DANIEL DREW
BUILDING-Rough-Frame 4/27/2021 Not Ready for Inspection BEAU COLLINS
Green Building Rough 4/27/2021 Not Ready for Inspection BEAU COLLINS
Insulation 4/27/2021 Partial Approval BEAU COLLINS
Interior/Exterior Lathing 4/27/2021 Partial Approval BEAU COLLINS
BUILDING-Rough-Frame 5/6/2021 Approved DANIEL DREW
Green Building Rough 5/6/2021 Approved DANIEL DREW
Drywall Nailing 5/17/2021 Approved ALAN MORELOS
Interior/Exterior Lathing 5/17/2021 Approved ALAN MORELOS
Final 7/12/2021 Corrections Issued DANIEL DREW
Green Building Final 7/12/2021 Not Ready for Inspection DANIEL DREW
SGSOV-Seismic Gas S/O Valve 7/12/2021 SGSOV Not Ready DANIEL DREW
Smoke Detectors 7/12/2021 Corrections Issued DANIEL DREW
ELECTRICAL-Final 7/27/2021 Approved DANIEL DREW
Final 7/27/2021 OK to Issue CofO DANIEL DREW
Green Building Final 7/27/2021 Approved DANIEL DREW
HVAC-Final 7/27/2021 Approved DANIEL DREW
PLUMBING-Final 7/27/2021 Approved DANIEL DREW
SGSOV-Seismic Gas S/O Valve 7/27/2021 SGSOV Approved DANIEL DREW
Smoke Detectors 7/27/2021 Approved DANIEL DREW