6309 E CRESCENT ST 90042
Certificate Information: 6309 E CRESCENT ST 90042
- Application / Permit
- 19014-20000-07170
- Plan Check / Job No.
- B19VN22653
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 26'-10" x 44'-11" IRREGULAR SHAPED ADDITION TO FIRST FLOOR OF EXISTING SINGLE FAMILY DWELLING; ADD 26'-10" X 32'-3" ON SECOND FLOOR; CONVERT 5' X 11'-10 PORTION OF DWELLING TO NEW PORCH; REMODEL; EQUIPPED WITH NFPA-13D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 5/17/2021
- Issuing Office
- Current Status
- CofO Issued on 8/1/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2019 | APPLICANT |
| Green Plans Picked Up | 2/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/6/2020 | SELLA BENYAMIN |
| Corrections Issued | 2/19/2020 | SELLA BENYAMIN |
| Quality Review Completed | 2/21/2020 | STEVEN KIM |
| Building Plans Picked Up | 2/25/2020 | APPLICANT |
| Plan Check Approved | 2/19/2021 | SELLA BENYAMIN |
| Issued | 5/17/2021 | APPLICANT |
| CofO in Progress | 8/1/2023 | AMY COLIN |
| Permit Finaled | 8/1/2023 | RONALD MYRICK |
| CofO Issued | 8/1/2023 | RONALD MYRICK |
| Permit Finaled | 8/1/2023 | RONALD MYRICK |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/29/2020 | WALLIE JONG |
| Sewer availability | Cleared | 6/29/2020 | WALLIE JONG |
| Low Impact Development | Cleared | 12/22/2020 | ORVAL HERNANDEZ-MARCI |
| GPI Written Notices | Cleared | 12/29/2020 | SELLA BENYAMIN |
| Grading Pre-Inspection | Cleared | 12/29/2020 | SELLA BENYAMIN |
| Roof/Waste drainage to street | Cleared | 12/31/2020 | WALLIE JONG |
| HPOZ | Cleared | 2/8/2021 | KATIE DEBIASE |
| Miscellaneous | Cleared | 2/8/2021 | KATIE DEBIASE |
| Green Code | Cleared | 2/11/2021 | DAVID MATSON |
Contact Information
| Contractor | C B Home Construction; Lic. No.: 961219-B | 1168 N SAN GABRIEL BLVD UNIT P ROSEMEAD, CA 91770 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/8/2021 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 7/13/2021 | Partial Approval | COREY HUPP |
| BUILDING-Rough-Frame | 7/29/2021 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 7/29/2021 | Partial Approval | CRAIG VAUGHAN |
| Insulation | 8/2/2021 | Partial Approval | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2021 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 10/29/2021 | Not Ready for Inspection | COREY HUPP |
| ELECTRICAL-Rough | 10/29/2021 | Not Ready for Inspection | COREY HUPP |
| Green Building Rough | 10/29/2021 | Not Ready for Inspection | COREY HUPP |
| HVAC-Rough | 10/29/2021 | Not Ready for Inspection | COREY HUPP |
| PLUMBING-Rough | 10/29/2021 | Not Ready for Inspection | COREY HUPP |
| BUILDING-Rough-Frame | 11/8/2021 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 11/8/2021 | Approved | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2021 | Approved | ARTHUR SARGSYAN |
| Green Building Rough | 11/8/2021 | Approved | ARTHUR SARGSYAN |
| HVAC-Rough | 11/8/2021 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 11/8/2021 | Approved | ARTHUR SARGSYAN |
| Insulation | 12/6/2021 | Approved | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 12/6/2021 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 12/16/2021 | Partial Approval | ALIZAH MAYAGOITIA |
| Drywall Nailing | 1/5/2022 | Approved | ADAM ESCOTO |
| Interior/Exterior Lathing | 2/25/2022 | Partial Approval | KATHRYN BUTTERWORTH |
| Shower Pan | 2/25/2022 | Approved | KATHRYN BUTTERWORTH |
| Underground Mechanical | 4/4/2022 | Approved | AMY COLIN |
| Gas Test | 4/20/2022 | Approved | AMY COLIN |
| Final | 5/13/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 5/13/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Green Building Final | 5/13/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 5/13/2022 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| Smoke Detectors | 5/13/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 1/20/2023 | Corrections Issued | AMY COLIN |
| Footing/Foundation/Slab | 1/20/2023 | Approved | AMY COLIN |
| Green Building Final | 1/20/2023 | Approved | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 1/20/2023 | SGSOV Not Ready | AMY COLIN |
| Smoke Detectors | 1/20/2023 | Approved | AMY COLIN |
| Final | 6/21/2023 | Partial Approval | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 6/21/2023 | SGSOV Approved | AMY COLIN |
| Final | 8/1/2023 | OK to Issue CofO | AMY COLIN |