8830 N ZELZAH AVE 91325

Certificate Information: 8830 N ZELZAH AVE 91325

Application / Permit
19014-20000-07144
Plan Check / Job No.
B19VN22592
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
13'1" X 17'11" ADDITION OF DEN AND ATTACHED 20' X 20' GARAGE TP (E) SFD PER ENGINEER.
Permit Issued
Issued on 1/7/2020
Issuing Office
Valley
Current Status
CofO Issued on 8/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2019 APPLICANT
Assigned to Plan Check Engineer 12/30/2019 PINANK PATEL
Corrections Issued 12/30/2019 PINANK PATEL
Plan Check Approved 1/7/2020 SARKIS HARABEDIAN
Issued 1/7/2020 LADBS
CofO in Progress 4/23/2021 SEAN WIRCH
Permit Finaled 8/29/2022 DANIEL ORRANTE
CofO Issued 8/29/2022 DANIEL ORRANTE
Permit Finaled 8/29/2022 DANIEL ORRANTE

Permit Application Clearance Information

Low Impact Development Cleared 1/6/2020 MITESH PATEL
Eng Process Fee Ord 176,300 Cleared 1/7/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 1/7/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia, Zelada, Eddy Alexander; Lic. No.: S6159 17958 LULL ST      RESEDA, CA 91335

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/28/2020 Corrections Issued MARK JOHNSON
Footing/Foundation/Slab 2/28/2020 Not Ready for Inspection MARK JOHNSON
Excavation/Setback/Form/Re-Bar 3/9/2020 Approved MARK JOHNSON
Footing/Foundation/Slab 3/9/2020 Approved MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 3/26/2020 Partial Approval MARK JOHNSON
PLUMBING-Rough 3/26/2020 Partial Approval MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 3/31/2020 Approved MARK JOHNSON
BUILDING-Rough-Frame 4/3/2020 Not Ready for Inspection MARK JOHNSON
Green Building Rough 4/3/2020 Not Ready for Inspection MARK JOHNSON
Rough-Elec/Plmb/HVAC 4/3/2020 Not Ready for Inspection MARK JOHNSON
ELECTRICAL-Rough 4/7/2020 Approved MARK JOHNSON
PLUMBING-Rough 4/7/2020 Approved MARK JOHNSON
BUILDING-Rough-Frame 4/9/2020 Approved MARK JOHNSON
Green Building Rough 4/9/2020 Approved MARK JOHNSON
HVAC-Rough 4/9/2020 Approved MARK JOHNSON
Interior/Exterior Lathing 4/9/2020 Approved MARK JOHNSON
Insulation 4/10/2020 Approved MARK JOHNSON
Drywall Nailing 4/14/2020 Approved MARK JOHNSON
Interior/Exterior Lathing 4/17/2020 Approved MARK JOHNSON
Shower Pan 4/17/2020 Approved MARK JOHNSON
Final 7/9/2020 Not Ready for Inspection MARK JOHNSON
Green Building Final 7/9/2020 Approved MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 7/9/2020 SGSOV Approved MARK JOHNSON
Smoke Detectors 7/9/2020 Approved MARK JOHNSON
Final 8/18/2020 No Access for Inspection MICHAEL TEMPLE
Final 4/23/2021 OK to Issue CofO SEAN WIRCH