5636 N STANSBURY AVE 91401

Certificate Information: 5636 N STANSBURY AVE 91401

Application / Permit
19014-20000-07142
Plan Check / Job No.
B19VN22586
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) DETACHED ONE STORY 32'-9" X 38'-9" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d), ALL WORK PER WFPP NFPA 13-D REQ'D THROUGHOUT
Permit Issued
Issued on 10/5/2020
Issuing Office
Current Status
CofO Issued on 12/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2019 APPLICANT
Assigned to Plan Check Engineer 1/23/2020 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 1/28/2020 SEWADA ZADOORIAN MILAGARDI
Green Plans Picked Up 2/10/2020 APPLICANT
Quality Review Completed 2/18/2020 OMID HEDAYAT
Building Plans Picked Up 2/25/2020 APPLICANT
Plan Check Approved 10/5/2020 SEWADA ZADOORAN MILAGARDI
Issued 10/5/2020 APPLICANT
CofO in Progress 10/28/2022 RICHARD DOCKUS
CofO Issued 12/24/2022 MICHAEL SMITH
Permit Finaled 12/24/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 4/15/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 4/15/2020 ADRIAN CASTRO
Sewer availability Cleared 4/15/2020 ADRIAN CASTRO
Green Code Cleared 5/6/2020 DAVID MATSON
Hydrant and Access approval Cleared 5/22/2020 MATTHEW CRAIG
Low Impact Development Cleared 7/13/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 7/17/2020 LEE GUILBEAUX

Contact Information

Contractor Pampa Investment Inc; Lic. No.: 832632-B 984 BROADWAY #302      CHULA VISTA, CA 91911

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/8/2020 Approved WILLIAM KUEHN
PLUMBING-Rough 10/8/2020 Partial Inspection WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 11/25/2020 Partial Inspection WILLIAM KUEHN
BUILDING-Rough-Frame 12/23/2020 Partial Approval ARAM AVEDISIAN
Green Building Rough 12/23/2020 Not Ready for Inspection ARAM AVEDISIAN
Rough-Elec/Plmb/HVAC 12/23/2020 Approved ARAM AVEDISIAN
Verify Sprinkler Sign Off 12/23/2020 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 1/11/2021 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 1/19/2021 Corrections Issued JENNIFER RABUCHIN
Insulation 1/19/2021 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 1/26/2021 No Access for Inspection JOHN HAYES
Green Building Rough 1/26/2021 No Access for Inspection JOHN HAYES
Insulation 1/26/2021 No Access for Inspection JOHN HAYES
BUILDING-Rough-Frame 1/27/2021 Approved DAVID SCANTLIN
Green Building Rough 1/27/2021 Approved DAVID SCANTLIN
Insulation 1/27/2021 Approved DAVID SCANTLIN
Drywall Nailing 2/1/2021 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 3/1/2021 Partial Approval CHRISTOPHER DELLEFIELD
Shower Pan 3/1/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Shower Pan 3/4/2021 Approved JENNIFER RABUCHIN
PLUMBING-Final 6/8/2022 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 6/8/2022 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 6/8/2022 Approved RICHARD DOCKUS
ELECTRICAL-Final 6/14/2022 Approved RICHARD DOCKUS
Gas Test 6/14/2022 Approved RICHARD DOCKUS
HVAC-Final 6/14/2022 Approved RICHARD DOCKUS
Final 10/21/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Green Building Final 10/21/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Service/Power Release 10/21/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 10/27/2022 OK to Issue CofO RICHARD DOCKUS
Green Building Final 10/28/2022 Approved RICHARD DOCKUS
Service/Power Release 10/28/2022 Approved RICHARD DOCKUS