5636 N STANSBURY AVE 91401
Certificate Information: 5636 N STANSBURY AVE 91401
- Application / Permit
- 19014-20000-07142
- Plan Check / Job No.
- B19VN22586
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) DETACHED ONE STORY 32'-9" X 38'-9" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d), ALL WORK PER WFPP NFPA 13-D REQ'D THROUGHOUT
- Permit Issued
- Issued on 10/5/2020
- Issuing Office
- Current Status
- CofO Issued on 12/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2020 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 1/28/2020 | SEWADA ZADOORIAN MILAGARDI |
| Green Plans Picked Up | 2/10/2020 | APPLICANT |
| Quality Review Completed | 2/18/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 2/25/2020 | APPLICANT |
| Plan Check Approved | 10/5/2020 | SEWADA ZADOORAN MILAGARDI |
| Issued | 10/5/2020 | APPLICANT |
| CofO in Progress | 10/28/2022 | RICHARD DOCKUS |
| CofO Issued | 12/24/2022 | MICHAEL SMITH |
| Permit Finaled | 12/24/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 4/15/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 4/15/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 4/15/2020 | ADRIAN CASTRO |
| Green Code | Cleared | 5/6/2020 | DAVID MATSON |
| Hydrant and Access approval | Cleared | 5/22/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 7/13/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 7/17/2020 | LEE GUILBEAUX |
Contact Information
| Contractor | Pampa Investment Inc; Lic. No.: 832632-B | 984 BROADWAY #302 CHULA VISTA, CA 91911 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/8/2020 | Approved | WILLIAM KUEHN |
| PLUMBING-Rough | 10/8/2020 | Partial Inspection | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 11/25/2020 | Partial Inspection | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 12/23/2020 | Partial Approval | ARAM AVEDISIAN |
| Green Building Rough | 12/23/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| Rough-Elec/Plmb/HVAC | 12/23/2020 | Approved | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 12/23/2020 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 1/11/2021 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 1/19/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 1/19/2021 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 1/26/2021 | No Access for Inspection | JOHN HAYES |
| Green Building Rough | 1/26/2021 | No Access for Inspection | JOHN HAYES |
| Insulation | 1/26/2021 | No Access for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 1/27/2021 | Approved | DAVID SCANTLIN |
| Green Building Rough | 1/27/2021 | Approved | DAVID SCANTLIN |
| Insulation | 1/27/2021 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 2/1/2021 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 3/1/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Shower Pan | 3/1/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Shower Pan | 3/4/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 6/8/2022 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 6/8/2022 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 6/8/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 6/14/2022 | Approved | RICHARD DOCKUS |
| Gas Test | 6/14/2022 | Approved | RICHARD DOCKUS |
| HVAC-Final | 6/14/2022 | Approved | RICHARD DOCKUS |
| Final | 10/21/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Green Building Final | 10/21/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Service/Power Release | 10/21/2022 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 10/27/2022 | OK to Issue CofO | RICHARD DOCKUS |
| Green Building Final | 10/28/2022 | Approved | RICHARD DOCKUS |
| Service/Power Release | 10/28/2022 | Approved | RICHARD DOCKUS |