6960 N COSTELLO AVE 91405

Certificate Information: 6960 N COSTELLO AVE 91405

Application / Permit
19014-20000-07106
Plan Check / Job No.
B19VN22482
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition and remodel to single-family dwelling and add an attached patio cover. Remove existing attached patio cover.
Permit Issued
Issued on 1/15/2020
Issuing Office
Valley
Current Status
CofO Issued on 1/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2019 APPLICANT
Assigned to Plan Check Engineer 12/27/2019 ANGELICA DAVE
Corrections Issued 12/27/2019 ANGELICA DAVE
Plan Check Approved 1/14/2020 ANGELICA MARTINEZ
Issued 1/15/2020 LADBS
CofO in Progress 7/31/2020 WILLIAM KUEHN
CofO Issued 1/21/2023 MICHAEL SMITH
Permit Finaled 1/21/2023 MICHAEL SMITH

Permit Application Clearance Information

Low Impact Development Cleared 1/13/2020 JORGE MEJIA LEMUS
Eng Process Fee Ord 176,300 Cleared 1/14/2020 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 1/14/2020 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 1/14/2020 LEE GUILBEAUX
Public Works-Sewers Cleared 1/14/2020 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Papazyan,, Andranik; Lic. No.: C56824 635 W COLORADO ST STE 104      GLENDALE, CA 91204

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/4/2020 Partial Approval MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 2/11/2020 Conditional Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 2/25/2020 Corrections Issued MISAEL ESPARZA
HVAC-Rough 3/6/2020 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 3/6/2020 Approved MISAEL ESPARZA
Deputy Drilled-In Anchors 3/10/2020 Approved MISAEL ESPARZA
ELECTRICAL-Rough 3/11/2020 Approved MISAEL ESPARZA
HVAC-Rough 3/11/2020 Approved MISAEL ESPARZA
Wood Frame 3/11/2020 Corrections Issued MISAEL ESPARZA
Wood Frame 3/16/2020 Approved MISAEL ESPARZA
Insulation 3/18/2020 Approved MISAEL ESPARZA
Drywall Nailing 3/23/2020 Approved MISAEL ESPARZA
Green Building Rough 3/23/2020 Approved MISAEL ESPARZA
Interior/Exterior Lathing 3/23/2020 Partial Approval MISAEL ESPARZA
Interior/Exterior Lathing 4/14/2020 Approved MISAEL ESPARZA
Shower Pan 4/14/2020 Approved MISAEL ESPARZA
Special/Order Compliance 4/14/2020 Approved GREGG CUMMINGS
Service/Power Release 6/15/2020 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 7/8/2020 Approved MISAEL ESPARZA
ELECTRICAL-Final 7/8/2020 Corrections Issued MISAEL ESPARZA
Final 7/8/2020 Not Ready for Inspection MISAEL ESPARZA
Footing/Foundation/Slab 7/8/2020 Approved MISAEL ESPARZA
Green Building Final 7/8/2020 Approved MISAEL ESPARZA
HVAC-Final 7/8/2020 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 7/8/2020 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 7/8/2020 SGSOV Not Ready MISAEL ESPARZA
Service/Power Release 7/8/2020 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 7/8/2020 Approved MISAEL ESPARZA
ELECTRICAL-Final 7/14/2020 Approved MISAEL ESPARZA
Final 7/14/2020 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 7/14/2020 Approved MISAEL ESPARZA
PLUMBING-Final 7/14/2020 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 7/14/2020 SGSOV Approved MISAEL ESPARZA
Service/Power Release 7/14/2020 Corrections Issued MISAEL ESPARZA
Final 7/24/2020 No Access for Inspection WILLIAM KUEHN
Final 7/30/2020 OK to Issue CofO WILLIAM KUEHN
ELECTRICAL-Final 5/31/2022 Not Ready for Inspection RICHARD DOCKUS
HVAC-Final 5/31/2022 Not Ready for Inspection RICHARD DOCKUS
PLUMBING-Final 5/31/2022 Not Ready for Inspection RICHARD DOCKUS