6627 N MURIETTA AVE 91405

Certificate Information: 6627 N MURIETTA AVE 91405

Application / Permit
19014-20000-07101
Plan Check / Job No.
B19VN22475
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
TWO STORY ADU ADDITION TO (E) DETACHED GARAGE
Permit Issued
Issued on 9/2/2022
Issuing Office
Valley
Current Status
CofO Issued on 7/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/26/2019 APPLICANT
Assigned to Plan Check Engineer 1/30/2020 ALBERT SERVIN
Corrections Issued 2/14/2020 ALBERT SERVIN
Quality Review Completed 2/20/2020 KEN GILL
Building Plans Picked Up 3/3/2020 APPLICANT
Green Plans Picked Up 3/10/2020 APPLICANT
Applicant returned to address corrections 6/16/2022 ALBERT SERVIN
Applicant returned to address corrections 7/15/2022 ALBERT SERVIN
Plan Check Approved 9/1/2022 ALBERT SERVIN
Issued 9/2/2022 APPLICANT
CofO in Progress 6/26/2023 RYAN SALAZAR
Permit Finaled 7/6/2023 MICHAEL SMITH
CofO Issued 7/6/2023 MICHAEL SMITH
Permit Finaled 7/6/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/29/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 10/1/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 10/1/2020 JOHN TRIANTAFYLLOS
Low Impact Development Cleared 12/21/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 8/22/2022 DAGOVERTO GUERRERO
Green Code Cleared 9/1/2022 AARON COSTA

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/9/2022 Partial Approval RICHARD DOCKUS
Deputy Drilled-In Anchors 9/15/2022 Conditional Approval CALEB MEISTER
Footing/Foundation/Slab 9/16/2022 Approved RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 10/17/2022 Corrections Issued JENNIFER RABUCHIN
Deputy Wood Construction 12/21/2022 Conditional Approval MICHAEL SMITH
Floor/Roof Diaphrgm/Shear Wall 12/21/2022 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 1/11/2023 Approved RYAN SALAZAR
HVAC-Rough 1/11/2023 Approved RYAN SALAZAR
PLUMBING-Rough 1/11/2023 Approved RYAN SALAZAR
Wood Frame 1/11/2023 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 1/25/2023 Approved RYAN SALAZAR
Underground Mechanical 1/25/2023 Approved RYAN SALAZAR
Insulation 2/1/2023 Conditional Approval RYAN SALAZAR
Interior/Exterior Lathing 2/1/2023 Partial Approval RYAN SALAZAR
Drywall Nailing 2/6/2023 Approved RYAN SALAZAR
PLUMBING-Rough 2/8/2023 Approved RYAN SALAZAR
Sewer 2/8/2023 Approved RYAN SALAZAR
Underground Mechanical 2/8/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 3/6/2023 Approved RYAN SALAZAR
Shower Pan 3/6/2023 Approved RYAN SALAZAR
ELECTRICAL-Rough 3/16/2023 Approved MATTHEW NELSON
Insulation 3/16/2023 Approved MATTHEW NELSON
BUILDING-Rough-Frame 4/27/2023 Approved RYAN SALAZAR
ELECTRICAL-Final 4/27/2023 Corrections Issued RYAN SALAZAR
Final 4/27/2023 Corrections Issued RYAN SALAZAR
Green Building Final 4/27/2023 Not Ready for Inspection RYAN SALAZAR
Green Building Rough 4/27/2023 Approved RYAN SALAZAR
HVAC-Final 4/27/2023 Conditional Approval RYAN SALAZAR
PLUMBING-Final 4/27/2023 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 4/27/2023 SGSOV Not Ready RYAN SALAZAR
Smoke Detectors 4/27/2023 Approved RYAN SALAZAR
Final 5/15/2023 Not Ready for Inspection RYAN SALAZAR
Green Building Final 5/15/2023 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 5/15/2023 SGSOV Approved RYAN SALAZAR
Final 6/26/2023 OK to Issue CofO RYAN SALAZAR