6627 N MURIETTA AVE 91405
Certificate Information: 6627 N MURIETTA AVE 91405
- Application / Permit
- 19014-20000-07101
- Plan Check / Job No.
- B19VN22475
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- TWO STORY ADU ADDITION TO (E) DETACHED GARAGE
- Permit Issued
- Issued on 9/2/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2020 | ALBERT SERVIN |
| Corrections Issued | 2/14/2020 | ALBERT SERVIN |
| Quality Review Completed | 2/20/2020 | KEN GILL |
| Building Plans Picked Up | 3/3/2020 | APPLICANT |
| Green Plans Picked Up | 3/10/2020 | APPLICANT |
| Applicant returned to address corrections | 6/16/2022 | ALBERT SERVIN |
| Applicant returned to address corrections | 7/15/2022 | ALBERT SERVIN |
| Plan Check Approved | 9/1/2022 | ALBERT SERVIN |
| Issued | 9/2/2022 | APPLICANT |
| CofO in Progress | 6/26/2023 | RYAN SALAZAR |
| Permit Finaled | 7/6/2023 | MICHAEL SMITH |
| CofO Issued | 7/6/2023 | MICHAEL SMITH |
| Permit Finaled | 7/6/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 9/29/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 10/1/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 10/1/2020 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 12/21/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 8/22/2022 | DAGOVERTO GUERRERO |
| Green Code | Cleared | 9/1/2022 | AARON COSTA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/9/2022 | Partial Approval | RICHARD DOCKUS |
| Deputy Drilled-In Anchors | 9/15/2022 | Conditional Approval | CALEB MEISTER |
| Footing/Foundation/Slab | 9/16/2022 | Approved | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Deputy Wood Construction | 12/21/2022 | Conditional Approval | MICHAEL SMITH |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2022 | Partial Approval | RYAN SALAZAR |
| ELECTRICAL-Rough | 1/11/2023 | Approved | RYAN SALAZAR |
| HVAC-Rough | 1/11/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 1/11/2023 | Approved | RYAN SALAZAR |
| Wood Frame | 1/11/2023 | Partial Approval | RYAN SALAZAR |
| ELECTRICAL-Rough | 1/25/2023 | Approved | RYAN SALAZAR |
| Underground Mechanical | 1/25/2023 | Approved | RYAN SALAZAR |
| Insulation | 2/1/2023 | Conditional Approval | RYAN SALAZAR |
| Interior/Exterior Lathing | 2/1/2023 | Partial Approval | RYAN SALAZAR |
| Drywall Nailing | 2/6/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 2/8/2023 | Approved | RYAN SALAZAR |
| Sewer | 2/8/2023 | Approved | RYAN SALAZAR |
| Underground Mechanical | 2/8/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 3/6/2023 | Approved | RYAN SALAZAR |
| Shower Pan | 3/6/2023 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 3/16/2023 | Approved | MATTHEW NELSON |
| Insulation | 3/16/2023 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 4/27/2023 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 4/27/2023 | Corrections Issued | RYAN SALAZAR |
| Final | 4/27/2023 | Corrections Issued | RYAN SALAZAR |
| Green Building Final | 4/27/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Rough | 4/27/2023 | Approved | RYAN SALAZAR |
| HVAC-Final | 4/27/2023 | Conditional Approval | RYAN SALAZAR |
| PLUMBING-Final | 4/27/2023 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 4/27/2023 | SGSOV Not Ready | RYAN SALAZAR |
| Smoke Detectors | 4/27/2023 | Approved | RYAN SALAZAR |
| Final | 5/15/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Final | 5/15/2023 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 5/15/2023 | SGSOV Approved | RYAN SALAZAR |
| Final | 6/26/2023 | OK to Issue CofO | RYAN SALAZAR |