6001 N VAN NUYS BLVD 91401

Certificate Information: 6001 N VAN NUYS BLVD 91401

Application / Permit
19014-20000-07084
Plan Check / Job No.
B19VN22443
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(8) Automobile Sales - new
Work Description
(1 OF 2) 204' x 340' IRREG. 2-STORY ADDITION /REMODEL AUTO DEALERSHIP WITH AUTO SERVICE /PART STORAGE
Permit Issued
Issued on 1/13/2021
Issuing Office
Valley
Current Status
CofO Issued on 12/20/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/26/2019 APPLICANT
Green Plans Picked Up 1/7/2020 APPLICANT
Assigned to Plan Check Engineer 1/9/2020 CHON CHIO KUO
Corrections Issued 1/13/2020 CHON CHIO KUO
Disabled Access Plans Picked Up 1/13/2020 APPLICANT
Quality Review Completed 1/15/2020 GUANG MIN TUNG
Building Plans Picked Up 1/17/2020 APPLICANT
Applicant returned to address corrections 4/1/2020 CHON CHIO KUO
Applicant returned to address corrections 4/7/2020 CHON CHIO KUO
Applicant returned to address corrections 5/14/2020 CHON CHIO KUO
Applicant returned to address corrections 6/4/2020 CHON CHIO KUO
Applicant returned to address corrections 6/23/2020 CHON CHIO KUO
Applicant returned to address corrections 7/9/2020 CHON CHIO KUO
Applicant returned to address corrections 8/12/2020 CHON CHIO KUO
Applicant returned to address corrections 10/19/2020 CHON CHIO KUO
Applicant returned to address corrections 11/4/2020 CHON CHIO KUO
Plan Check Approved 12/17/2020 CHON CHIO KUO
Issued 1/13/2021 APPLICANT
TCO Issued (Expire Date: 04-10-2024) 10/13/2023 JEFFREY DURAN
CofO in Progress 6/18/2024 ANDREW DORSO
CofO in Progress 6/20/2024 JEFFREY DURAN
Permit Finaled 12/20/2024 JEFFREY DURAN
CofO Issued 12/20/2024 JEFFREY DURAN
Permit Finaled 12/20/2024 JEFFREY DURAN

Permit Application Clearance Information

Address approval Cleared 1/23/2020 HOWARD COOPER
Eng Process Fee Ord 176,300 Cleared 1/23/2020 ADRIAN CASTRO
Work Adjacent to Public Way Cleared 1/23/2020 ADRIAN CASTRO
Sewer availability Cleared 4/2/2020 GABRIEL ROBLES
Green Code Cleared 4/14/2020 MICHAEL AYERS
Highway dedication Cleared 6/5/2020 LEE GUILBEAUX
Permit Cleared 6/5/2020 LEE GUILBEAUX
ZA Case Cleared 6/5/2020 JASON CHAN
Miscellaneous Cleared 7/9/2020 CHON CHIO KUO
Prkng lot landscape/Water mgmt Cleared 8/6/2020 JASON CHAN
Low Impact Development Cleared 9/17/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 9/25/2020 GUILLERMO PETRA
Hydrant and Access approval Cleared 12/7/2020 MATTHEW CRAIG
DAS Clearance Cleared 12/8/2020 OLLIE CARTER

Contact Information

Architect Flynn,, Dennis Joseph; Lic. No.: C17001 190 SOUTH GLASSELL ST STE 200      ORANGE, CA 92866
Contractor Pacific West Builders Inc; Lic. No.: 752705-B 1197 LOS ANGELES AVE STE C 166      SIMI VALLEY, CA 93065
Engineer Grimm,, Samuel Dunham; Lic. No.: S4730 17500 REDHILL AVENUE SUITE 240      IRVINE, CA 92614
Engineer Thorpe,, Bret Jensen; Lic. No.: C82754 2806 TRAKELL ST      ROSAMOND, CA 93560

Inspector Information

BRIAN KELLY, (818) 374-1127 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/16/2021 Partial Inspection ANDREW DORSO
Deputy Reinf. Concrete 4/22/2021 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 4/22/2021 Partial Approval HAMID PISHEHVAR
Deputy Reinf. Concrete 4/23/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 4/30/2021 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 4/30/2021 Partial Approval CAMERON CHABAN
Reinforced Concrete Frame 5/4/2021 Partial Inspection ANDREW DORSO
Deputy Reinf. Concrete 5/5/2021 Conditional Approval ANDREW DORSO
Deputy Reinf. Concrete 5/6/2021 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 5/10/2021 Conditional Approval JEFFREY DURAN
Reinforced Concrete Frame 5/10/2021 Approved HAMID PISHEHVAR
Deputy Reinf. Concrete 5/11/2021 Conditional Approval JEFFREY DURAN
Masonry Wall/Backfill 5/18/2021 Not Ready for Inspection ANDREW DORSO
Green Building Rough 5/19/2021 Not Ready for Inspection ANDREW DORSO
Reinforced Masonry Frame 5/19/2021 Partial Inspection ANDREW DORSO
Masonry Wall/Backfill 5/25/2021 Partial Inspection ANDREW DORSO
Deputy Reinf. Concrete 5/27/2021 Conditional Approval ANDREW DORSO
Masonry Wall/Backfill 6/1/2021 Partial Approval CAMERON CHABAN
Deputy Reinf. Masonry 6/3/2021 Conditional Approval CAMERON CHABAN
Masonry Wall/Backfill 6/4/2021 Partial Approval CAMERON CHABAN
Masonry Wall/Backfill 6/10/2021 Partial Inspection ANDREW DORSO
Deputy Reinf. Masonry 6/15/2021 Conditional Approval ANDREW DORSO
Masonry Wall/Backfill 6/15/2021 Partial Approval DANIEL VARNUM
Deputy Reinf. Masonry 6/17/2021 Conditional Approval DANIEL VARNUM
Deputy Reinf. Masonry 6/18/2021 Conditional Approval DANIEL VARNUM
Masonry Wall/Backfill 6/18/2021 Partial Approval DANIEL VARNUM
Deputy Reinf. Masonry 6/21/2021 Conditional Approval JEFFREY DURAN
Masonry Wall/Backfill 6/22/2021 Not Ready for Inspection HAMID PISHEHVAR
Masonry Wall/Backfill 6/23/2021 Partial Inspection ANDREW DORSO
Deputy Reinf. Masonry 6/24/2021 Conditional Approval ANDREW DORSO
Deputy Reinf. Concrete 7/1/2021 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 7/1/2021 Partial Approval CAMERON CHABAN
Deputy Reinf. Concrete 7/2/2021 Conditional Approval KENNETH ROBERTS
Footing/Foundation/Slab 7/7/2021 Partial Inspection ANDREW DORSO
Deputy Reinf. Concrete 7/8/2021 Conditional Approval ANDREW DORSO
Deputy Reinf. Concrete 7/9/2021 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 7/9/2021 Partial Inspection ANDREW DORSO
Deputy Reinf. Concrete 7/12/2021 No Result Entered GARY EWELL
Deputy Reinf. Concrete 7/20/2021 Conditional Approval ANDREW DORSO
Footing/Foundation/Slab 7/20/2021 Partial Inspection ANDREW DORSO
Deputy Reinf. Concrete 7/21/2021 Conditional Approval ANDREW DORSO
Deputy Reinf. Concrete 8/2/2021 Conditional Approval ANDREW DORSO
Deputy Reinf. Concrete 8/3/2021 Conditional Approval ANDREW DORSO
Deputy Reinf. Concrete 8/4/2021 Conditional Approval ANDREW DORSO
Deputy Reinf. Concrete 8/5/2021 Conditional Approval ANDREW DORSO
Deputy Reinf. Concrete 8/6/2021 Conditional Approval ANDREW DORSO
Deputy Reinf. Concrete 8/9/2021 Conditional Approval ANDREW DORSO
Deputy Reinf. Concrete 8/12/2021 Conditional Approval ANDREW DORSO
Footing/Foundation/Slab 8/18/2021 Partial Inspection ANDREW DORSO
Deputy Reinf. Concrete 8/20/2021 Conditional Approval ANDREW DORSO
Deputy Pre-Stress Concrete 9/17/2021 Conditional Approval JOHN KITCKO
Footing/Foundation/Slab 9/17/2021 Partial Approval JONATHAN QUACH
Deputy Pre-Stress Concrete 9/20/2021 Conditional Approval JONATHAN QUACH
Deputy Reinf. Concrete 9/20/2021 Conditional Approval JONATHAN QUACH
Deputy Shotcrete 9/20/2021 Conditional Approval ANDREW DORSO
Deputy Shotcrete 9/21/2021 Conditional Approval ANDREW DORSO
Deputy Reinf. Concrete 9/22/2021 Conditional Approval ANDREW DORSO
Deputy Shotcrete 9/22/2021 Conditional Approval ANDREW DORSO
Footing/Foundation/Slab 9/22/2021 Partial Inspection ANDREW DORSO
Deputy Reinf. Concrete 9/23/2021 Conditional Approval ANDREW DORSO
Deputy Shotcrete 9/23/2021 Conditional Approval ANDREW DORSO
Deputy Shotcrete 9/24/2021 Conditional Approval ANDREW DORSO
Masonry Wall/Backfill 10/14/2021 Partial Inspection ANDREW DORSO
Deputy Reinf. Masonry 10/18/2021 Conditional Approval JEFFREY DURAN
Masonry Wall/Backfill 10/19/2021 Partial Inspection ANDREW DORSO
Deputy Reinf. Concrete 10/20/2021 Conditional Approval ANDREW DORSO
Masonry Wall/Backfill 10/21/2021 Partial Inspection ANDREW DORSO
Deputy Reinf. Masonry 10/28/2021 Conditional Approval ANDREW DORSO
Masonry Wall/Backfill 10/29/2021 Partial Inspection ANDREW DORSO
Deputy Reinf. Masonry 11/3/2021 Conditional Approval JEFFREY DURAN
Masonry Wall/Backfill 11/3/2021 Partial Inspection ANDREW DORSO
Deputy Reinf. Concrete 11/15/2021 Conditional Approval ANDREW DORSO
Deputy Reinf. Masonry 11/15/2021 Conditional Approval ANDREW DORSO
Deputy Reinf. Masonry 11/15/2021 No Result Entered GARY EWELL
Masonry Wall/Backfill 11/15/2021 Partial Inspection ANDREW DORSO
Deputy Reinf. Masonry 11/16/2021 Conditional Approval ANDREW DORSO
Masonry Wall/Backfill 11/18/2021 Partial Inspection ANDREW DORSO
Deputy Reinf. Masonry 12/2/2021 Conditional Approval ANDREW DORSO
Masonry Wall/Backfill 12/2/2021 Partial Inspection ANDREW DORSO
Deputy Reinf. Masonry 12/3/2021 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 12/8/2021 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 12/9/2021 Conditional Approval ANDREW DORSO
Masonry Wall/Backfill 12/21/2021 Partial Approval ANDREW DORSO
Deputy Reinf. Concrete 1/12/2022 Conditional Approval ANDREW DORSO
Deputy Reinf. Concrete 1/13/2022 No Result Entered GARY EWELL
Deputy Drilled-In Anchors 1/31/2022 Conditional Approval ANDREW DORSO
Deputy Drilled-In Anchors 2/2/2022 Conditional Approval ANDREW DORSO
Insulation 3/1/2022 Partial Inspection ANDREW DORSO
Light Gage Steel Frame 3/1/2022 Partial Inspection ANDREW DORSO
Insulation 3/7/2022 Partial Approval DANIEL VARNUM
Drywall Nailing 3/16/2022 Partial Inspection ANDREW DORSO
Deputy Reinf. Concrete 4/5/2022 Conditional Approval ANDREW DORSO
Footing/Foundation/Slab 5/9/2022 Approved DANIEL VARNUM
Deputy Reinf. Concrete 5/10/2022 Conditional Approval DANIEL VARNUM
Masonry Wall/Backfill 5/19/2022 Partial Approval DANIEL VARNUM
Deputy Reinf. Concrete 5/24/2022 Conditional Approval ANDREW DORSO
Interior/Exterior Lathing 6/7/2022 Partial Inspection ANDREW DORSO
Masonry Wall/Backfill 6/7/2022 Partial Inspection ANDREW DORSO
Deputy Reinf. Concrete 6/8/2022 Conditional Approval ANDREW DORSO
Masonry Wall/Backfill 6/15/2022 Partial Approval DANIEL VARNUM
Deputy Reinf. Masonry 6/16/2022 Conditional Approval ANDREW DORSO
Masonry Wall/Backfill 6/21/2022 Partial Inspection ANDREW DORSO
Masonry Wall/Backfill 8/18/2022 Partial Inspection ANDREW DORSO
Piling/Pier/Caisson 8/23/2022 Partial Inspection ANDREW DORSO
Deputy Reinf. Concrete 8/24/2022 Conditional Approval ANDREW DORSO
Deputy Reinf. Concrete 8/25/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/30/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 8/30/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 8/31/2022 Approved ANDREW DORSO
Deputy Drilled-In Anchors 9/22/2022 Conditional Approval JEFFREY DURAN
Deputy Drilled-In Anchors 10/19/2022 Conditional Approval ANDREW DORSO
T-Bar Ceiling 10/21/2022 Not Ready for Inspection DANIEL VARNUM
Masonry Wall/Backfill 4/12/2023 Partial Approval BRIAN KELLY
Green Building Rough 6/26/2023 Approved ANDREW DORSO
Final 8/15/2023 Not Ready for Inspection BRIAN KELLY
Green Building Final 8/15/2023 Not Ready for Inspection BRIAN KELLY
Reinforced Masonry Frame 8/15/2023 Not Ready for Inspection BRIAN KELLY
SGSOV-Seismic Gas S/O Valve 8/15/2023 SGSOV Not Ready BRIAN KELLY
Smoke Detectors 8/15/2023 Not Ready for Inspection BRIAN KELLY
Wood Frame 8/15/2023 Not Ready for Inspection BRIAN KELLY
Special/Order Compliance 8/16/2023 Corrections Issued ANDREW DORSO
Final 9/20/2023 Not Ready for Inspection ANDREW DORSO
Green Building Final 9/20/2023 Approved ANDREW DORSO
Reinforced Masonry Frame 9/20/2023 Approved ANDREW DORSO
SGSOV-Seismic Gas S/O Valve 9/20/2023 SGSOV Approved ANDREW DORSO
Smoke Detectors 9/20/2023 Partial Inspection ANDREW DORSO
Wood Frame 9/20/2023 Approved ANDREW DORSO
Final 11/16/2023 OK to Issue CofO ANDREW DORSO
Smoke Detectors 11/16/2023 Approved ANDREW DORSO
Special/Order Compliance 3/12/2024 Partial Inspection BRIAN KELLY