7752 W VALMONT ST 91042

Certificate Information: 7752 W VALMONT ST 91042

Application / Permit
19014-20000-07065
Plan Check / Job No.
B19VN22403
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION AND CONVERSION OF GARAGE/ STORAGE TO ACCESSORY DWELLING UNIT
Permit Issued
Issued on 5/11/2020
Issuing Office
Current Status
Permit Finaled on 1/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/24/2019 APPLICANT
Assigned to Plan Check Engineer 1/30/2020 ALBERT SERVIN
Corrections Issued 2/3/2020 ALBERT SERVIN
Quality Review Completed 2/5/2020 KEN GILL
Green Plans Picked Up 2/7/2020 APPLICANT
Building Plans Picked Up 2/13/2020 APPLICANT
Plan Check Approved 3/26/2020 ALBERT SERVIN
Issued 5/11/2020 APPLICANT
Permit Finaled 1/28/2025 DAVID ANDERSON

Permit Application Clearance Information

Address approval Cleared 3/4/2020 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 3/4/2020 THOMAS LANG
Roof/Waste drainage to street Cleared 3/4/2020 THOMAS LANG
Green Code Cleared 3/16/2020 MICHAEL AYERS
Grading Pre-Inspection Cleared 3/26/2020 ALBERT SERVIN
Sewer availability Cleared 3/31/2020 THOMAS LANG

Contact Information

Contractor Owner-Builder       ,
Engineer Yeghiayan,, Armond; Lic. No.: C69935 16873 MCKEEVER ST      GRANADA HILLS, CA 91344

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/16/2021 Corrections Issued BEAU COLLINS
Excavation/Setback/Form/Re-Bar 4/13/2021 Partial Approval BEAU COLLINS
PLUMBING-Rough 4/22/2021 Partial Approval BEAU COLLINS
Sewer 4/22/2021 Approved BEAU COLLINS
Excavation/Setback/Form/Re-Bar 4/28/2021 Conditional Approval BEAU COLLINS
Footing/Foundation/Slab 4/28/2021 Conditional Approval BEAU COLLINS
BUILDING-Rough-Frame 5/28/2021 Not Ready for Inspection DAVID MATSON
Green Building Rough 5/28/2021 Corrections Issued DAVID MATSON
Wood Frame 5/28/2021 Not Ready for Inspection DAVID MATSON
Wood Frame 6/7/2021 Not Ready for Inspection DAVID MATSON
Wood Frame 6/15/2021 Not Ready for Inspection MATTHEW NELSON
Rough-Elec/Plmb/HVAC 3/21/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 4/4/2022 Not Ready for Inspection DAVID MATSON
Green Building Rough 4/4/2022 Not Ready for Inspection DAVID MATSON
BUILDING-Rough-Frame 1/28/2025 Approved DAVID ANDERSON
Final 1/28/2025 Permit Finaled DAVID ANDERSON
Footing/Foundation/Slab 1/28/2025 Approved DAVID ANDERSON
Green Building Final 1/28/2025 Approved DAVID ANDERSON
Green Building Rough 1/28/2025 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 1/28/2025 SGSOV Approved DAVID ANDERSON
Smoke Detectors 1/28/2025 Approved DAVID ANDERSON