7730 N WILKINSON AVE 91605
Certificate Information: 7730 N WILKINSON AVE 91605
- Application / Permit
- 19014-20000-07056
- Plan Check / Job No.
- B19VN22385
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 8' X 7' ADDITION TO (E) SINGLE FAMILY DWELLING FOR NEW BATHROOM. ALL WORK PER WFPP.
- Permit Issued
- Issued on 1/21/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/22/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/24/2019 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 12/24/2019 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 1/21/2020 | ROSENDO MEDINA |
| Issued | 1/21/2020 | LADBS |
| CofO in Progress | 10/27/2021 | CHRISTOPHER DELLEFIELD |
| CofO in Progress | 11/22/2021 | MICHAEL SMITH |
| CofO Issued | 11/22/2021 | MICHAEL SMITH |
| Permit Finaled | 11/22/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/21/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 1/21/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 1/6/2021 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 1/6/2021 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 1/6/2021 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 1/6/2021 | Not Ready for Inspection | JOHN HAYES |
| MERV13>=Rough | 1/6/2021 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 1/6/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 1/8/2021 | Corrections Issued | JOHN HAYES |
| Green Building Rough | 1/8/2021 | Not Ready for Inspection | JOHN HAYES |
| MERV13>=Rough | 1/8/2021 | Not Ready for Inspection | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 1/8/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 1/29/2021 | Approved | JOHN HAYES |
| Drywall Nailing | 1/29/2021 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 1/29/2021 | Approved | JOHN HAYES |
| Green Building Rough | 1/29/2021 | Approved | JOHN HAYES |
| MERV13>=Rough | 1/29/2021 | Approved | JOHN HAYES |
| Insulation | 3/2/2021 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 3/2/2021 | Partial Approval | JOHN HAYES |
| Shower Pan | 3/2/2021 | Approved | JOHN HAYES |
| Drywall Nailing | 3/16/2021 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 3/16/2021 | Approved | JOHN HAYES |
| Final | 9/24/2021 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 9/24/2021 | Approved | MATTHEW NELSON |
| Green Building Final | 9/24/2021 | Approved | MATTHEW NELSON |
| MERV13>=Final | 9/24/2021 | Approved | MATTHEW NELSON |
| Smoke Detectors | 9/24/2021 | Approved | MATTHEW NELSON |
| Final | 10/19/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 10/27/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 10/27/2021 | OK to Issue CofO | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 10/27/2021 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 10/27/2021 | Approved | CHRISTOPHER DELLEFIELD |